Structural steel construction SWMS, drafted for your job
Steel erection depends on the frame holding each new member before the crane lets go, while connectors work above people and plant below. Give us the job details and site layout. The draft follows that setup, and your crew checks the steps on site before work starts.
A$39per job
However many high-risk activities it covers.
- However many high-risk activities it covers.
- 3 for A$99
- 10 for A$249
- Yearly A$129 for 120
- Monthly A$60 for 10
You review it on site before work starts.
Your Business
Safe Work Method Statement
Version 1
Draft
Structural steel construction
Site Your site address
Law Your state
High-risk construction work
- Work where someone could fall from height
- Structural alterations that need temporary support
- Work where powered mobile plant is moving
Job steps, hazards and controls
| 1 | Prepare crane and delivery area | Soft ground and shifting steel | High | Check bearing ground and plan unloading restraints |
| 2 | Unload and stage members | Rolling beams and suspended loads | High | Support members and separate the lift area |
| 3 | Erect columns and beams | Unstable frame and swinging loads | High | Follow the erection sequence and fit temporary bracing |
| 4 | Connect and inspect members | Elevated work and closing plates | High | Use protected platforms and alignment tools |
| 5 | Complete bracing and hand over | Premature removal of temporary support | High | Verify permanent stability before removing temporary bracing |
Illustrative first page. Yours carries your business name only.
What you get
What your structural steel construction SWMS will contain
An A4 document your crew can read on site, a PDF for the builder and a sign-on register.
- Job and site detailsYour business, the site, the principal contractor, the dates.
- High-risk construction workThe categories your job involves, ticked.
- Step-by-step methodEach step with its hazards, risk rating and controls.
- How controls are checkedWho puts each control in place, monitors and reviews it.
- PPE, plant and permitsEquipment and training the job needs.
- Emergency planAssembly point, first aid, nearest hospital to confirm on site.
- Consultation and reviewWho was consulted, when it is reviewed.
- Sign-on registerYour crew signs by QR or on paper.
High-risk construction work
Categories this task often involves
You tick the ones your job involves. Each ticked category gets its own steps and controls, in your state's wording.
- Work where someone could fall from height
- Structural alterations that need temporary support
- Work where powered mobile plant is moving
State notes
Rules depend on your state
Pick your state when you start. Your state's regulator publishes the rules and guidance for this work.
Hazards and controls
What goes wrong on a structural steel construction job, and how the SWMS controls it
These rows are written for this task. Your draft adds the ones your site and method need.
- 1
Steel frame collapse before permanent bracing is complete
High- Follow the engineered erection sequence and install temporary bracing as each bay progresses
- Verify the specified connections and stability before releasing crane support
- 2
Suspended steel members swinging through the erection crew
High- Set a separated lift area with a clear landing position for each member
- Use tag lines from outside the load path and keep people out from beneath lifts
- 3
Falls making beam connections on the unfinished steel frame
High- Use protected work platforms or suitable elevating platforms for connection work
- Plan access and recovery before any task relying on fall arrest
- 4
Crushed fingers aligning beam end plates and bolt holes
High- Use alignment tools and controlled crane positioning to bring connections together
- Keep fingers out of bolt holes and clear of closing end plates
- 5
Welding sparks and slag falling through steel erection bays
High- Remove combustible materials and isolate the area below hot work
- Use fire blankets and screens with a fire watch during and after welding
- 6
Steel loads shifting as delivery restraints are released
High- Unload on firm ground with members supported and restrained against rolling
- Attach lifting gear before releasing the restraint that holds the next member
- 7
Crane or steel beam contacting overhead electrical lines
High- Plan crane positions and lift paths away from overhead supplies
- Arrange isolation where needed and keep the operator’s exclusion area clear
- 8
Wind turning suspended steel during frame erection
High- Stop lifting when conditions prevent controlled positioning within the lift plan
- Recheck temporary bracing and access platforms after strong wind before work resumes
How the job usually runs
- 1Prepare crane and delivery areaSoft ground and shifting steel → Check bearing ground and plan unloading restraints
- 2Unload and stage membersRolling beams and suspended loads → Support members and separate the lift area
- 3Erect columns and beamsUnstable frame and swinging loads → Follow the erection sequence and fit temporary bracing
- 4Connect and inspect membersElevated work and closing plates → Use protected platforms and alignment tools
- 5Complete bracing and hand overPremature removal of temporary support → Verify permanent stability before removing temporary bracing
PPE for this job
- Safety helmet
- Safety boots
- Cut-resistant gloves
- Safety glasses
- High-visibility clothing
- Welding protective equipment
- Hearing protection
Your draft lists the PPE your site and method need.
After you finalise
Brief your crew and send it to your builder
Crew signs by QR
Send to my builder
PDF and register
Builder sent it back?
Make their changes and re-issue the same job free. Workers re-sign the new version.
Questions
Structural steel construction SWMS questions
- Last reviewed
- 21 October 2026
- How
- Hazard rows checked against the task; no legal line is stated unless it is logged from primary text.
- Next review
- Every six months, or when the method or rules change
Does it cover temporary bracing during steel erection?
Yes. Include the erection design and sequence. The draft covers installing temporary bracing as work progresses and checking member connections and stability before the crane releases each load.
Can it include bolted and welded steel connections?
Yes. Describe the connection methods and access equipment. The draft covers alignment tools, protected working positions, welding screens and separating people below from sparks, slag and dropped tools.
How much does a structural steel construction SWMS cost?
Drafting is free. Finalising costs A$39 for the job, however many high-risk activities it covers. Packs and Yearly cost less per SWMS.
Is this a template?
No. You describe the job and the site, and the SWMS is drafted for them. You edit anything, then finalise it.
Who checks the SWMS?
You do, with your crew, on site before work starts. The draft gives you a strong starting point; the person running the work makes sure it matches the site.
My builder sent it back. What now?
Open it, make the changes they asked for and re-issue it. Corrections to the same job are free.
How does my crew sign it?
Show the QR code on your phone or print the A4 sign-on sheet. Workers read and sign on their own phones without an account.