Concrete Boom or Line Pumping Safe Work Method Statement

2,000+ Australian Businesses Trust OneClickSWMS

No credit card required • Instant access • 100% compliant in every Australian state

5 sec
Creation Time
100%
Compliant
2,000+
Companies
$3.6K
Fines Avoided

Avoid WHS penalties up to $3.6M—issue compliant SWMS to every crew before work starts.

Concrete boom and line pumping operations deliver concrete from mixer trucks to placement locations using hydraulic pump systems and articulated booms or ground-level pipelines. This critical construction activity enables concrete placement in locations inaccessible to mixer trucks, at elevated heights, or across obstacles. Boom pumps feature articulated arms extending up to 60 metres with hydraulic actuation providing precise placement control, while line pumps use ground-level pipelines directing concrete through flexible or rigid pipes. This Safe Work Method Statement addresses all aspects of concrete pumping safety including pump setup and stabilization, boom operation near overhead services, concrete delivery coordination, pump blockage management, and emergency procedures in accordance with Australian WHS legislation and Safe Work Australia concrete pumping guidance.

Unlimited drafts • Built-in WHS compliance • Works across every Australian state

Overview

What this SWMS covers

Concrete pumping revolutionized construction by enabling efficient concrete placement in locations previously requiring labour-intensive manual methods. Boom pumps mounted on truck chassis feature multi-section articulated booms with reaches extending from 20 to 60 metres vertically and horizontally, delivering concrete through steel pipelines terminating in flexible rubber hoses for precise placement control. Hydraulic systems actuate boom sections through 360-degree rotation and multi-axis movement, with modern pumps incorporating computerized load monitoring and stability systems. Line pumps present a more compact alternative using trailer-mounted pumping units delivering concrete through ground-level pipelines positioned from pump to placement location, suitable for ground slabs, footings, and lower-level applications where boom reach is unnecessary. Concrete pumping operations involve complex coordination between multiple parties including concrete batch plants scheduling deliveries, mixer truck drivers delivering concrete to pump hopper, pump operators controlling equipment and boom movements, concrete placement crews screeding and finishing, and site supervisors managing overall construction sequencing. A typical large concrete pour may involve 200-500 cubic metres delivered over 8-12 hours requiring 25-60 mixer truck loads at 8-10 cubic metre capacity each. The continuous nature of concrete placement creates time pressures as concrete workability degrades approximately 90 minutes after batching, demanding efficient coordination preventing delays that compromise concrete quality or require accelerated placement creating safety risks. Boom pump setup requires careful site assessment evaluating ground conditions supporting outriggers bearing pump loads plus concrete weight in boom pipelines potentially exceeding 50 tonnes. Operators extend outriggers to maximum span providing stability, position outrigger pads distributing loads across ground surface, and verify pump is level within manufacturers specifications typically 3 degrees maximum. Overhead clearance assessment is critical identifying electrical powerlines, communications cables, building overhangs, trees, and other obstructions within boom operating radius. Minimum clearance distances from electrical lines depend on voltage ranging from 3 metres for low-voltage to 8 metres for high-voltage transmission lines under AS/NZS 3000 Electrical Installations regulations. Contact between concrete pump booms and energised electrical conductors has caused multiple fatalities in Australian construction, making electrical clearance verification absolutely critical. Line pump operations involve positioning the pumping unit on stable ground within pipeline reach of placement area and assembling rigid steel or flexible rubber pipelines from pump discharge to placement location. Pipeline routing must account for bends reducing pumping efficiency, with maximum recommended bends depending on line length and concrete mix characteristics. Pipelines require secure support preventing movement under internal pressure from concrete flow and pump pulsation. For elevated placements, pipelines attach to formwork or structural elements using appropriate brackets and fixings capable of supporting pipe weight plus flowing concrete. Flexible hose sections at delivery point enable precise placement control but create significant manual handling and hose whip hazards requiring careful management. Pump operators require high-risk work licenses for boom-type concrete placing operations under Australian WHS Regulation 2011, with licensing requiring completion of approved training covering equipment setup, stability, operation, and emergency procedures. The sophistication of modern concrete pumps with hydraulic systems, multiple boom sections, remote control capabilities, and safety systems demands comprehensive operator competency. Unlicensed operation of boom pumps constitutes a serious breach attracting significant penalties for both operators and employers. Line pump operation does not require specific licensing but operators must demonstrate competency through training and supervised experience. This SWMS establishes requirements ensuring only qualified, licensed, and competent persons operate concrete pumping equipment.

Fully editable, audit-ready, and aligned to Australian WHS standards.

Why this SWMS matters

Concrete pumping is explicitly classified as high-risk construction work under WHS Regulation 2011 Section 291 when it involves working on or near energized electrical installations or services, triggering mandatory SWMS requirements. Beyond electrical hazards, the operation of large mobile plant with articulated booms extending multiple storeys creates struck-by hazards affecting both pump operators and other site personnel. Safe Work Australia incident data identifies concrete pumping as a significant contributor to construction fatalities, with boom contact with overhead powerlines, pump instability and overturn, and struck-by injuries from moving booms representing the primary incident mechanisms. Electrical contact incidents involving concrete pump booms contacting overhead powerlines have resulted in multiple Australian construction fatalities over the past decade. In one Queensland incident, a boom pump operator was killed when the concrete delivery boom contacted 11kV overhead powerlines, with electricity conducted through the boom structure electrocuting the operator. Subsequent investigation identified inadequate electrical hazard assessment, failure to maintain required clearance distances, and absence of traffic management controlling boom movements near powerlines. The principal contractor and pumping company received combined fines exceeding $400,000 demonstrating serious consequences for inadequate concrete pumping safety management. These incidents are entirely preventable through proper electrical hazard identification, maintaining clearance distances, and using spotters or boom limiters preventing contact. Pump stability failures causing boom pump overturn result from inadequate ground assessment, incorrect outrigger setup, or ground subsidence under load. A New South Wales incident involved a boom pump overturning when supporting ground beneath one outrigger failed during concrete placement, causing the boom to swing uncontrollably striking two workers and resulting in one fatality and serious injuries to another. Investigation found the pump was positioned over recent excavation backfill with inadequate compaction, and ground assessment was not conducted before setup. The weight of a fully extended boom pump with concrete-filled pipelines can exceed 50 tonnes, demanding engineered ground support particularly on construction sites with variable soil conditions. Ground bearing pressure calculations and physical inspection of support areas are essential elements of pre-operational assessment. Struck-by incidents from moving concrete pump booms occur during boom positioning, concrete placement, and boom stowage operations. The articulated boom structure creates a dynamic hazard field extending throughout the operating radius, with boom movements controlled remotely by operators who may have limited visibility of personnel in movement paths. Workers on elevated levels adjacent to boom operating areas face particular risk from boom sections swinging horizontally at their working height. Exclusion zones around operating concrete pumps are mandatory under Safe Work Australia guidance, with physical barriers and spotters preventing unauthorized access. Recent Victorian prosecution involved serious injuries to a worker struck by a moving boom during concrete placement where adequate exclusion zones were not established or enforced, resulting in $180,000 combined fines. Concrete pumping operations create additional hazards including pipeline blockages requiring clearance under high pressure, concrete washout creating environmental hazards, manual handling of heavy hoses and pipeline sections, noise exposure from pump operation, and fatigue from extended pours often commencing early morning. Pump blockages occurring from concrete segregation, aggregate buildup, or mix setting in pipelines create pressure buildup requiring careful relief procedures. Attempting to clear blockages by striking pipelines or applying excessive pressure has resulted in pipeline bursts causing serious injuries from high-pressure concrete discharge. Emergency blockage clearance procedures must be documented and understood by all pump operators. The complex coordination required between concrete suppliers, truck drivers, pump operators, and placement crews creates communication challenges particularly on large pours with multiple trucks delivering sequentially. Concrete placement crews directing pump operators regarding concrete discharge location and rate must maintain clear communication despite high noise environments. Radio communication systems are standard on commercial projects, with hand signals providing backup communication. Communication breakdown has contributed to incidents including concrete discharge onto workers, boom movements striking personnel or structures, and concrete quality issues from placement delays. This SWMS establishes clear communication protocols, spotter requirements, and coordination procedures ensuring safe concrete pumping operations.

Reinforce licensing, insurance, and regulator expectations for Concrete Boom or Line Pumping Safe Work Method Statement crews before they mobilise.

Hazard identification

Surface the critical risks tied to this work scope and communicate them to every worker.

Risk register

Boom Contact with Overhead Electrical Powerlines

High

Concrete pump booms constructed from steel sections provide excellent electrical conductivity, with contact with energized overhead powerlines causing electricity to flow through boom structure to pump chassis and ground, electrocuting operators and workers in contact with pump or boom. Electrical contact occurs during boom extension when operators misjudge clearance distances, wind-induced boom sway moving boom into powerlines, or inattention during boom movements. High-voltage powerlines carry 11,000 volts or more creating lethal electrical discharge through minimal air gaps. Low-voltage lines at 240/415 volts are equally dangerous despite lower voltage. Boom tips often contact powerlines during setup or initial extension before concrete pumping commences, when operators are focused on positioning rather than electrical clearances. Rescue of electrocuted personnel is dangerous as pump and surrounding area remains energized until power authority isolates supply.

Pump Instability and Overturn from Ground Failure

High

Concrete boom pumps rely on hydraulically-extended outriggers bearing against ground surface to maintain stability during boom extension and concrete placement. Ground failure beneath outriggers from inadequate bearing capacity, subsurface voids or services, undermining from water ingress, or proximity to excavations causes sudden pump instability and potential overturn. A fully extended boom pump creates enormous leverage with concrete-filled boom potentially 40-60 metres from pump chassis, generating overturning moments exceeding 200 tonne-metres. Ground bearing pressures under outrigger pads can exceed 500 kPa demanding competent undisturbed soil or engineered support. Construction sites frequently involve recently placed fill, service trenches, or proximity to basement excavations creating ground instability risks. Pump overturn occurs suddenly without warning as ground fails, causing boom to swing uncontrollably striking structures and personnel.

Personnel Struck by Moving Boom During Operation

High

Concrete pump booms move throughout the placement area under hydraulic control, with boom sections rotating, extending, and articulating creating a large dynamic hazard zone. Operators control boom movements from remote stations using joysticks or control panels, often with limited direct visibility of boom position and surrounding personnel. Workers on elevated levels such as upper floor slabs are particularly vulnerable to boom sections moving horizontally at their working height. Ground-level personnel can be struck by boom movements during positioning or stowage. Boom movements appear slow but generate substantial kinetic energy from the mass of steel boom sections and concrete-filled pipelines. The multiple articulation points create complex movement patterns where boom tip may move in different direction to mid-boom sections, confusing personnel regarding safe positions. Communication difficulties in noisy construction environments impair coordination between pump operators and site personnel.

High-Pressure Pipeline Blockage and Burst

High

Concrete pipelines from pump discharge to placement point develop blockages from concrete segregation, aggregate bridging, or premature setting causing pressure buildup as pump continues operating against restriction. Concrete pumps generate extremely high hydraulic pressures exceeding 200 bar (20 MPa) to move concrete through pipelines, with blockages causing pressure concentration at restriction point. Operators attempting to clear blockages by increasing pump pressure or striking pipeline with hammers can cause explosive pipeline bursts discharging high-pressure concrete and pipeline sections like projectiles. Concrete discharged at high pressure causes devastating injuries penetrating flesh and eyes. Flexible rubber hoses at pipeline terminations are particularly vulnerable to burst under blockage conditions. Cold weather increases blockage risk as concrete temperature drops reducing workability. Delays between trucks delivering concrete allows partial setting in pipelines.

Concrete Hose Whip and Manual Handling Injuries

High

Flexible rubber hoses at boom or line pump discharge enable workers to direct concrete flow during placement, with hoses typically 3-4 metres long and 100-125mm internal diameter. Flowing concrete through hoses generates substantial forces from concrete momentum and pump pulsation, creating hose whip where hose suddenly moves or thrashes when unsecured or partially obstructed. A concrete-filled hose weighs 50-80kg demanding physical strength to control and position. Hose whip during full pumping can strike workers causing serious impact injuries. Manual handling of heavy concrete hoses during multi-hour pours causes acute and cumulative musculoskeletal injuries affecting backs, shoulders, and arms. Workers direct hoses while standing in awkward positions on reinforcement, formwork edges, or uneven surfaces increasing fall and strain risks. Hose end fittings and steel wear sleeves are heavy metal components causing crush injuries if hoses drop or swing uncontrolled.

Inadequate Exclusion Zones Around Operating Pumps

High

Concrete pumping operations create multiple hazards requiring exclusion zones preventing unauthorized personnel accessing hazardous areas. The boom operating radius extending 20-60 metres creates struck-by hazards from boom movements. The pump chassis area presents crush hazards from outriggers and moving components. Concrete delivery area at boom discharge requires exclusion preventing workers being struck by discharged concrete or hose whip. On active construction sites with multiple trades, maintaining effective exclusion zones is challenging as workers attempt to access areas adjacent to pump operations. Inadequate physical barriers, removed or displaced temporary fencing, lack of spotters enforcing exclusion zones, and poor communication about pump operating areas contribute to exclusion zone failures. Workers unfamiliar with concrete pumping hazards may not recognize risks and enter hazardous zones.

Noise Exposure from Pump Operations

Medium

Concrete pumps generate sustained noise levels exceeding 85 dB(A) from diesel engines driving hydraulic systems, pump mechanisms, and concrete flow through pipelines. Pumping operations for large pours continue for 8-12 hours creating prolonged noise exposure for pump operators and concrete placement crews. Noise levels are highest at pump location but extend throughout placement area affecting all site personnel. The continuous nature of pumping prevents operators taking breaks in quiet areas until pour completion. Radio communication systems require increased volume in high-noise environments potentially causing additional hearing damage. Cumulative noise exposure over a career causes permanent noise-induced hearing loss affecting most concrete industry workers. Temporary threshold shift during extended pumping operations reduces hearing sensitivity affecting communication and hazard awareness.

Concrete Spillage and Chemical Burns from Cement Contact

Medium

Concrete pumping operations inevitably cause concrete spillage from hose connections, pump hopper overflow, pipeline disconnection, and discharge overspray. Wet concrete with pH above 12 is highly alkaline causing chemical burns through prolonged skin contact. Pump operators experience concrete splashing during truck discharge into pump hopper. Concrete placement crews experience concrete on hands and arms from directing hoses and screeding operations. Concrete penetrating safety boots or work clothing causes burns developing over hours of contact. Kneeling in spilled concrete during finishing work is particularly hazardous causing severe knee burns. Workers often underestimate chemical burn risk from concrete as burns develop slowly unlike thermal burns, with serious damage occurring before discomfort prompts washing. Lack of immediate washing facilities on construction sites delays removal of concrete from skin.

Control measures

Deploy layered controls aligned to the hierarchy of hazard management.

Implementation guide

Comprehensive Electrical Hazard Assessment and Clearance Management

Elimination

The most effective control for electrical contact hazards is eliminating the hazard by arranging temporary disconnection and removal of overhead powerlines within boom operating radius, or relocating pump setup position to maintain required clearances. When elimination is achievable, the electrical hazard is completely removed. This control represents true elimination following the hierarchy of control and provides absolute protection against electrical contact incidents. Coordination with electrical utility authorities to temporarily isolate and remove overhead conductors for the duration of concrete pumping operations eliminates the single largest cause of concrete pumping fatalities in Australian construction.

Implementation

1. Identify all overhead electrical conductors within 50 metres of proposed pump setup location during site planning phase, weeks before concrete pour date 2. Determine conductor voltage by contacting electrical utility authority with location details and pole/line identification numbers - never assume voltage from appearance 3. Calculate boom operating envelope accounting for maximum boom reach plus 3 metre buffer zone, using pump specifications and planned placement locations 4. Assess whether overhead conductors fall within boom operating envelope or required clearance distances as specified in AS/NZS 3000 5. Where conductors are within operating envelope, contact electrical utility authority requesting temporary isolation and removal of conductors for pour duration 6. Submit formal application to utility authority including site plans, proposed pump location, boom specifications, and pour schedule - applications typically require 4-8 weeks notice 7. Coordinate costs for temporary disconnection with client, typically ranging from $5,000-$20,000 depending on number of affected properties and reconnection complexity 8. Obtain written confirmation from utility authority specifying isolation date, expected completion of reconnection, and any conditions or restrictions 9. Where elimination is not feasible due to cost, timeframe, or essential services, proceed to substitution and engineering controls with comprehensive risk management 10. Document in SWMS the assessment process, cost-benefit analysis, and reasons if elimination control was not implemented 11. For projects involving multiple concrete pours over extended periods, consider permanent relocation of overhead conductors as design phase solution 12. Coordinate with building designers in early design stages to position buildings and access routes avoiding overhead electrical conductor conflicts

Physical Boom Limiters and Electrical Proximity Warning Devices

Engineering

When electrical conductor elimination is not feasible, engineering controls prevent boom contact through physical boom limiters restricting boom movement, and electrical proximity warning devices alerting operators when boom approaches energized conductors. Boom limiters use mechanical or electronic systems preventing boom extension or rotation beyond preset limits, making electrical contact physically impossible. Proximity warning devices use electromagnetic field detection triggering audible and visual alarms when boom enters preset warning zones around electrical conductors. These engineering controls provide reliable protection independent of operator vigilance or judgment, substantially reducing electrical contact risk.

Implementation

1. Assess electrical conductor locations relative to required boom operating envelope and identify specific boom positions that would breach minimum clearance distances 2. Install boom angle limiters or boom extension limiters on pump hydraulic systems preventing boom movements that would contact conductors or breach clearance zones 3. Use pump manufacturer-supplied limiting systems where available, or engage specialist contractors to install aftermarket boom control systems 4. Calibrate boom limiters accurately using surveyed electrical conductor positions and pump setup location, with settings verified by competent person before pumping commences 5. Install electrical proximity warning systems such as 'Guardian' or 'Electrosense' devices detecting electromagnetic fields around energized conductors 6. Mount proximity warning sensors on boom tip oriented toward electrical conductors, with alarm units positioned at operator station providing clear audible and visual warnings 7. Set proximity warning devices to alarm at distance exceeding minimum clearance requirements, typically 5-6 metres for high-voltage providing approach warning before breach occurs 8. Test proximity warning device functionality before pumping by deliberately moving boom toward conductors from safe distance, verifying alarm activation 9. Never defeat, disable, or ignore boom limiters or proximity warnings - these devices provide critical protection and must remain operational throughout pumping operations 10. Supplement engineering controls with trained spotters maintaining visual observation of boom position relative to electrical conductors, providing redundant monitoring 11. Document boom limiter settings and proximity warning device configurations in daily pre-start records, with supervisor verification before pumping authorization 12. Maintain boom limiters and proximity warning devices per manufacturer specifications with regular testing and calibration by qualified technicians

Engineered Ground Support Assessment and Outrigger Setup Protocols

Engineering

Preventing pump instability and overturn requires engineering-based ground assessment calculating bearing pressures and comparing to soil capacity, with physical inspection verifying ground conditions. Outrigger pads distribute pump loads across ground surface, with pad sizing determined by ground bearing capacity calculations. This engineering control uses fundamental structural engineering principles ensuring ground can support imposed loads with adequate safety factors, preventing ground failure and pump instability. Competent persons with geotechnical knowledge assess ground conditions and specify support requirements.

Implementation

1. Engage geotechnical engineer or qualified engineering surveyor to assess ground bearing capacity at proposed pump setup locations during construction planning 2. Obtain soil test data through physical testing or desktop review of geotechnical investigation reports prepared for building design 3. Calculate maximum ground bearing pressures from pump outriggers using pump specifications, maximum boom reach, and concrete load in boom pipelines 4. Compare calculated bearing pressures to soil allowable bearing capacity ensuring adequate safety factor minimum 1.5, preferably 2.0 for variable site conditions 5. Design outrigger pad dimensions distributing loads to achieve acceptable bearing pressures - typical pad sizes 600mm x 600mm minimum for competent natural ground, increasing to 1200mm x 1200mm or larger for poor soils 6. Use engineered timber pads minimum 50mm thickness or steel plates minimum 20mm thickness providing adequate stiffness preventing pad flexure and local ground punching 7. Conduct physical inspection of proposed setup area on pour day before pump positioning, checking for surface water, soft spots, recent fill, service trenches, or proximity to excavations 8. Identify underground services or voids within 5 metres of setup area through service location and ground-penetrating radar survey - voids from stormwater pipes or abandoned services can cause ground subsidence 9. Assess proximity to excavations ensuring pump setup maintains minimum distance equal to excavation depth plus 2 metres from excavation edge preventing ground failure 10. Verify pump is positioned on level surface within manufacturer specifications typically 3 degrees maximum - use pump spirit levels or electronic inclinometers 11. Extend outriggers to full extension providing maximum stability, with all outrigger pads bearing evenly on prepared ground or outrigger pad systems 12. Document ground assessment findings including soil type, bearing capacity, pad specifications used, and inspector sign-off before pumping authorization 13. Monitor ground conditions throughout pumping operation watching for ground movement, water accumulation, or outrigger settlement indicating ground distress 14. Prohibit pump setup on recent fill less than 2 weeks old unless engineered compaction testing demonstrates adequate density, or over service trenches backfilled within previous 6 months

Exclusion Zones with Physical Barriers and Spotter Systems

Engineering/Administrative

Establishing physical exclusion zones with barriers, fencing, and signage prevents unauthorized personnel entering hazardous areas around operating concrete pumps. Spotters positioned with clear visibility of boom operating area and surrounding site personnel enforce exclusion zones and facilitate communication between pump operators and site workers. This combined control uses physical barriers (engineering) and procedural enforcement (administrative) creating reliable protection from struck-by hazards during pump operations.

Implementation

1. Define exclusion zones around pump operations including full boom operating radius plus 3 metre buffer (typically 25-65 metre radius depending on boom reach), pump chassis area 5 metres all sides, and concrete discharge area 10 metre radius from boom tip 2. Install physical barriers at exclusion zone boundaries using temporary fencing panels, bunting, or barrier mesh secured to star pickets or concrete blocks 3. Install warning signage at exclusion zone entry points displaying 'DANGER - CONCRETE PUMPING OPERATIONS - AUTHORIZED PERSONNEL ONLY - HARD HATS AND HIGH-VIS REQUIRED' 4. Create controlled access gates in exclusion barriers at designated locations with spotters stationed at gates controlling personnel entry and exit 5. Ensure all personnel entering exclusion zones are directly involved in concrete pumping or placement operations and have received site-specific induction covering concrete pumping hazards 6. Appoint dedicated spotters minimum one per pump with responsibility for monitoring boom movements, enforcing exclusion zones, and maintaining communication with pump operator 7. Equip spotters with high-visibility vests marked 'SPOTTER' and two-way radios on dedicated channel for pump operation communications 8. Position spotters with clear line-of-sight to both boom tip and surrounding work areas, relocating as boom position changes to maintain visibility 9. Establish standard radio communication protocols with pump operator including 'STOP' command requiring immediate halt of all boom movements until situation assessed 10. Implement stop-work authority empowering spotters to immediately cease pump operations if any person enters exclusion zone or hazard conditions develop 11. Coordinate with other trades scheduling work in adjacent areas to avoid conflicts during concrete pumping operations, using toolbox meetings on pour day to communicate exclusion zones 12. For multi-level buildings, establish exclusion zones on all levels within boom operating envelope, with physical barriers or spotters on upper levels preventing workers accessing areas where boom may swing 13. Maintain exclusion zones throughout pump setup, operation, and pack-down phases - boom movements during stowage after pumping completion present similar struck-by hazards 14. Brief all site personnel in morning pre-start meeting on pour days regarding concrete pumping operations, exclusion zones, and access restrictions during pumping activities 15. Document exclusion zone setup with photographs and spotter assignments in daily pre-start records, with supervisor verification before pumping commences

Pump Operator Licensing and Competency Verification Programme

Administrative

Ensuring concrete pump operators hold current high-risk work licenses and demonstrated competency through training and experience prevents operator error contributing to incidents. The CN (Concrete Placing) high-risk work license mandates assessment of operator knowledge and practical skills in pump setup, operation, and emergency procedures. This administrative control ensures only qualified persons operate concrete pumps, with documented verification providing compliance evidence.

Implementation

1. Verify all boom-type concrete pump operators hold current CN (Concrete Placing) high-risk work license issued under WHS Regulations checking photo identification matches license 2. Maintain copies of operator licenses in company records with expiry date tracking system flagging licenses requiring renewal minimum 30 days before expiry 3. Implement site access procedures preventing unlicensed persons operating boom pumps through site induction requirements and daily pre-start checks 4. Verify operator licensing on arrival at site before permitting pump setup, with site supervisor responsible for license verification and documentation 5. For line pump operations not requiring statutory licensing, implement company competency assessment program documenting operator training, supervision, and signoff by experienced operators 6. Conduct ongoing refresher training minimum annually covering changes to pump technology, incident learnings from industry, and reinforcement of setup and operational procedures 7. Implement operator induction for new pump equipment covering specific controls, safety features, stability characteristics, and emergency procedures for each pump model 8. Establish mentoring system pairing newly-licensed operators with experienced operators for minimum 20 supervised pours before authorizing independent operation 9. Document operator qualifications, experience, and competency assessments in personnel files with regular review ensuring currency 10. Provide operators with pump manufacturer training courses covering specific equipment features, maintenance requirements, and operational limitations 11. Brief operators on site-specific hazards during pre-start meetings including electrical conductor locations, ground conditions, access limitations, and communication protocols 12. Implement operator fatigue management particularly for long pours requiring extended operating periods, with relief operators for pours exceeding 8 hours 13. Conduct debrief with operators after significant pours identifying issues encountered and improvements for future operations, documenting learnings in continuous improvement register

Concrete Delivery Coordination and Communication Systems

Administrative

Effective coordination between concrete suppliers, truck drivers, pump operators, and placement crews prevents delays causing concrete setting in pipelines (blockage risk), rushed placement creating safety hazards, or concrete quality issues from excessive delays. Clear communication protocols and scheduled delivery timing create controlled workflow minimizing time pressures and supporting safe pumping operations. This administrative control establishes systematic coordination procedures.

Implementation

1. Conduct pre-pour planning meeting minimum one week before scheduled pour date with representatives from concrete supplier, pumping contractor, placement contractor, and principal contractor 2. Confirm concrete specifications including mix design, slump (target 120-140mm for pumping), aggregate size (maximum 20mm for boom pumps, 10-14mm for line pumps), retarder additions, and quality requirements 3. Schedule concrete delivery to pump at steady intervals matching placement rate typically 15-20 minute intervals between trucks for standard boom pumps 4. Provide concrete supplier with pump location, site access route, and any restrictions affecting truck movements or positioning at pump hopper 5. Establish primary communication channel typically mobile phone contact between pump operator and batch plant dispatcher coordinating truck dispatch and delivery timing 6. Implement backup communication using two-way radios on construction sites with poor mobile reception or for urgent communications during pumping 7. Appoint site coordinator responsible for overall pour management including pump operator liaison, placement crew coordination, truck driver direction, and incident management 8. Brief truck drivers on site access, waiting areas away from active operations, truck positioning at pump hopper, and discharge procedures during morning pre-start meeting 9. Establish standard hand signals between placement crews and pump operators for communication when radio or verbal communication is impractical due to noise or distance 10. Use standardized signals including 'START PUMPING' (arm extended horizontally), 'STOP' (arm raised vertically fist closed), 'UP/DOWN/LEFT/RIGHT' (directional pointing), and 'EMERGENCY STOP' (both arms crossed overhead) 11. Implement 'stop work' authority empowering any person to immediately halt pumping operations if unsafe conditions develop or communication breakdown occurs 12. Monitor concrete delivery timing watching for delays exceeding planned intervals, communicating with batch plant dispatcher to expedite subsequent trucks or slow deliveries matching placement rate 13. Adjust pumping rate to match placement crew capacity preventing concrete accumulation exceeding crew finishing capability, communicating rate adjustments between pump operator and placement crews 14. Document communications during pour including truck arrival times, volume delivered, any delays or issues, in pour log maintained by site coordinator 15. Conduct real-time pour management adjusting truck scheduling and pumping rates responding to actual site conditions and crew productivity

Pipeline Blockage Prevention and Emergency Clearance Procedures

Administrative

Preventing pipeline blockages through concrete mix management, pipeline maintenance, and operational practices avoids high-pressure blockage clearance creating serious injury risks. Documented emergency procedures for safely clearing blockages that do occur prevent improvised dangerous practices. This administrative control combines preventive measures with emergency response protocols.

Implementation

1. Specify concrete mix designs suitable for pumping including appropriate slump (120-140mm), maximum aggregate size relative to pipeline diameter (1:3 ratio minimum), and adequate cementitious content providing paste volume 2. Conduct pre-pour concrete mix trial pumping for large projects or first use of specific mix designs, verifying pumpability before critical placement activities 3. Prime concrete pipelines before pumping structural concrete using cement-water grout or mortar matching concrete proportions but excluding coarse aggregate, lubricating pipeline and preventing blockage from dry pipeline friction 4. Maintain continuous pumping operation without extended interruptions preventing concrete stiffening in pipelines - if delays occur, pulse pump periodically maintaining concrete movement 5. Monitor concrete slump from each truck delivery conducting slump tests where concrete appearance suggests variation from specification - reject non-conforming concrete 6. Coordinate with batch plant dispatcher if concrete workability is inadequate requesting mix adjustments for subsequent trucks rather than continuing with unsuitable concrete 7. Implement cold weather procedures when ambient temperature drops below 10°C including concrete heating, pipeline insulation, and reduced time between trucks preventing premature stiffening 8. Flush pipelines with water immediately upon completing pour or if blockage develops that cannot be cleared, preventing concrete hardening requiring pipeline disassembly 9. Establish emergency blockage clearance procedures documented in pump operator manual including reducing pump pressure, reversing pump direction if capable, and compressed air pulse methods 10. Prohibit striking pipelines with hammers or sledges to clear blockages - this creates pipeline damage and injury risk from burst without reliably clearing blockage 11. Prohibit excessive pump pressure to force blockages - maximum operating pressure typically 200-250 bar with blockage clearance pressure not exceeding this limit 12. Establish exclusion zones around pipelines during blockage clearance preventing personnel adjacent to pipeline sections where burst may occur 13. Wear appropriate PPE during blockage clearance including full face shields, chemical-resistant gloves, and protective clothing preventing injuries from concrete discharge 14. Disconnect pipeline sections progressively from discharge end working back toward pump if blockage cannot be cleared by pumping or flushing methods 15. Document blockage incidents including cause determination, clearance method used, time lost, and preventive measures for future pours in incident register 16. Maintain spare pipeline sections and couplings on site enabling replacement of damaged or blocked sections without extended delays

Personal protective equipment

Requirement: Type 1 hard hats to AS/NZS 1801 with secure chin straps mandatory

When: Required at all times during concrete pumping operations for pump operators, concrete placement crews, spotters, and all personnel within exclusion zones. Critical protection against struck-by hazards from boom movements, falling tools, and overhead hazards

Requirement: Class D day/night high-visibility vests or shirts with reflective tape

When: Mandatory for all personnel in concrete pumping areas enabling spotters and operators to identify workers and preventing struck-by incidents. Particularly critical in early morning or evening pours with reduced visibility

Requirement: Lace-up boots with steel toe protection, ankle support, chemical-resistant materials, and slip-resistant soles

When: Required continuously during concrete pumping protecting against crush injuries from concrete hoses, dropped equipment, and moving machinery. Chemical-resistant materials prevent cement burns from concrete contact

Requirement: PVC or nitrile-coated gloves providing cement chemical protection and grip

When: Mandatory when handling concrete hoses, during pump hopper operations, and all activities involving concrete contact. Prevents cement chemical burns and improves grip on wet concrete-contaminated surfaces

Requirement: Clear impact-resistant glasses with side protection, full face shields for pump hopper operations

When: Required during all concrete pumping activities protecting against concrete splash from pump hopper, hose connections, and discharge operations. Face shields mandatory for operators at pump hopper during truck discharge

Requirement: Class 4-5 earplugs or Class 3-5 earmuffs providing minimum 25dB noise reduction

When: Mandatory for pump operators and personnel within 10 metres of operating pumps exceeding 85dB(A). Required for entire duration of pumping operations typically 6-12 hours for large pours

Requirement: Cotton or cotton-blend clothing covering arms and legs

When: Mandatory during concrete pumping operations preventing cement chemical burns from concrete splash. Clothing should be changed immediately if saturated with concrete to prevent prolonged skin contact

Requirement: Heavy-duty PVC or rubber aprons and leg chaps

When: Required for pump hopper operators during concrete discharge from mixer trucks and during pipeline disconnection operations exposing personnel to concrete spillage and splash

Inspections & checks

Before work starts

  • Verify pump operator holds current CN (Concrete Placing) high-risk work license, checking photo identification and license expiry date
  • Conduct thorough pre-operational inspection of pump equipment checking hydraulic systems, boom articulation, outriggers, hopper, pipelines, and safety devices functionality
  • Inspect pipeline sections for damage, wear, cracks, or deterioration replacing any defective sections before pumping commences
  • Test boom control systems including remote control functionality, emergency stop buttons, and boom movement smoothness without binding or hesitation
  • Verify ground conditions at pump setup location checking for adequate bearing capacity, level surface, absence of services or voids, and clearance from excavations
  • Position and secure outrigger pads ensuring full outrigger extension, even pad bearing, and adequate pad dimensions for ground conditions
  • Conduct electrical hazard assessment identifying all overhead powerlines within 50 metres, determining voltage, calculating required clearances, and implementing control measures
  • Install and test boom limiters or electrical proximity warning devices where overhead conductors are within boom operating envelope, verifying alarm functionality
  • Establish physical exclusion zones with barriers, fencing, and signage around pump operating radius, chassis area, and concrete discharge zone
  • Appoint and brief spotters on responsibilities, communication protocols, radio usage, and emergency stop authority, providing high-visibility identification
  • Brief all site personnel on concrete pumping operations, exclusion zones, communication methods, and emergency procedures in morning pre-start meeting
  • Verify concrete mix design is suitable for pumping confirming slump, aggregate size, and mix specifications with batch plant and obtaining mix design documentation
  • Confirm concrete delivery schedule with batch plant dispatcher reviewing truck intervals, total quantity, any special requirements, and contact numbers
  • Check weather forecast for pour day ensuring conditions suitable for concrete placement and pump operation with contingency plans for adverse weather
  • Verify first aid facilities and emergency equipment available with first aid trained personnel on site and emergency contact numbers clearly displayed

During work

  • Monitor boom position continuously relative to overhead electrical conductors maintaining required clearances with spotter observation and proximity warning devices
  • Inspect exclusion zone barriers and signage remaining in place with spotters actively enforcing zones and preventing unauthorized access
  • Verify effective communication maintained between pump operator, placement crews, and site coordinator with radio checks if communication quality degrades
  • Monitor ground conditions beneath pump watching for settlement, movement, water accumulation, or any signs of ground distress indicating instability risk
  • Check concrete consistency from each truck delivery assessing slump, workability, and uniformity rejecting non-conforming concrete before pumping
  • Observe concrete flow through pipelines and discharge hose watching for flow rate changes, pressure fluctuations, or signs of potential blockages developing
  • Monitor pump operating pressures and hydraulic systems checking gauges, listening for unusual sounds, and watching for hydraulic leaks or overheating
  • Verify workers maintain safe distances from concrete hoses during discharge operations with adequate personnel for safe hose handling without overexertion
  • Inspect PPE compliance ensuring all personnel wearing hard hats, high-visibility clothing, safety glasses, chemical-resistant gloves, and hearing protection
  • Monitor personnel for fatigue particularly during extended pours implementing scheduled breaks and relief personnel for pump operators and placement crews
  • Check housekeeping around pump and placement area managing concrete spillage, keeping walkways clear, and maintaining safe access routes
  • Observe weather conditions monitoring for high winds affecting boom stability, rainfall affecting concrete placement, or temperature extremes requiring mix adjustments
  • Maintain continuous coordination with concrete supplier managing truck delivery timing to match placement rate without excessive delays between trucks
  • Monitor placement crew productivity ensuring concrete placed and finished before initial set occurs with pumping rate adjusted to crew capacity

After work

  • Flush all pipelines immediately after completing pour using water pumped through system until discharge runs clear preventing concrete hardening in lines
  • Clean pump hopper, pipelines, and discharge hose removing concrete residue before material hardens requiring mechanical cleaning
  • Inspect boom sections, hydraulic cylinders, and articulation points checking for concrete accumulation, hydraulic leaks, or damage from operation
  • Stow boom following manufacturer procedures ensuring boom properly secured for transport and outriggers fully retracted before moving pump
  • Maintain clear exclusion zones during pump pack-down and movement preventing personnel struck-by hazards from boom stowage movements
  • Document pump performance during pour including any issues, blockages, equipment problems, or near-miss incidents in pump operation log
  • Conduct post-pour debrief with pump operator, placement crews, and site coordinator identifying successes and improvements for future pours
  • Remove temporary exclusion zone barriers, signage, and boom limiters storing equipment appropriately for future use
  • Complete daily maintenance procedures per manufacturer specifications including lubrication, filter checks, and visual inspections
  • Report any equipment damage, malfunction, or defects to pump owner/supervisor tagging equipment out of service if defects affect safety or operation
  • Review concrete delivery documentation checking actual quantity delivered matches order, recording any rejected loads, and noting mix variations
  • Verify site restored to safe condition with concrete spillage cleaned, temporary barriers removed, and access routes clear for other trades

Step-by-step work procedure

Give supervisors and crews a clear, auditable sequence for the task.

Field ready
1

Pre-Pour Planning and Site Assessment

Comprehensive planning and site assessment prevents most concrete pumping incidents by identifying hazards and implementing controls before pump arrival. Conduct site meetings minimum one week before pour with all stakeholders including pump operator, concrete supplier, placement contractor, and principal contractor representatives. Review architectural and structural drawings identifying exact placement locations, access routes, and concrete specifications. Calculate concrete quantities and pumping time based on placement area dimensions and pour rates typically 30-60 cubic metres per hour. Identify overhead electrical conductors within 100 metres of site using service location plans and visual inspection, determining voltage through utility authority contact. Calculate required boom reach from probable pump position to furthest placement location accounting for obstacles and access limitations. Assess ground conditions at potential pump setup locations evaluating bearing capacity, levelness, proximity to excavations, and underground services. Specify outrigger pad requirements based on ground conditions typically 600mm minimum for competent natural ground. Develop pour sequence and placement strategy ensuring continuous concrete supply without delays causing pipeline blockages. Confirm concrete mix design suitability for pumping including slump targets, aggregate sizing, and admixtures. Schedule concrete deliveries at intervals matching placement capacity typically 15-20 minutes between trucks. Brief all personnel on pour day arrangements, safety procedures, exclusion zones, and emergency protocols. Document planning outcomes in pour plan distributed to all parties before pour date.

Safety considerations

Inadequate planning causes rushed setup on pour day increasing electrical contact risk from insufficient clearance assessment. Poor ground assessment causes pump instability. Incorrect concrete specification creates blockage risks. Communication breakdown between parties creates coordination failures and incidents. All major concrete pumping incidents trace back to inadequate planning and site assessment.

2

Pump Setup and Stabilization

Position concrete pump at planned location optimizing boom reach to placement areas while maintaining overhead clearances and ground stability. Approach setup area slowly watching for overhead powerlines, soft ground, underground services, and obstructions. Position pump with boom articulation centered on primary placement area minimizing boom extension required. Before extending outriggers, verify pump is on level ground checking chassis spirit levels - relocate if ground slope exceeds manufacturer limits typically 3 degrees. Extend outriggers symmetrically to full extension providing maximum stability footprint. Position outrigger pads beneath outrigger feet distributing ground bearing pressure - pad dimensions match ground assessment requirements determined during planning. Verify all outriggers bearing evenly on pads with pump chassis clear of ground. Connect remote control unit to pump hydraulic system testing all control functions before boom extension. Extend boom slowly section by section watching overhead clearances and maintaining visual or radio contact with spotters. Position boom over placement area ready for concrete delivery. Install boom limiters if required preventing boom movements breaching electrical clearances. Activate electrical proximity warning devices and verify alarm functionality by approaching electrical conductors from safe distance. Connect rigid pipeline sections from pump discharge to required locations for line pump operations, supporting pipeline adequately on formwork or ground. Establish exclusion zones with physical barriers around pump operating radius and access controls. Position spotters at strategic locations with clear visibility of boom, electrical hazards, and site personnel. Conduct final pre-operational checks before authorizing concrete delivery.

Safety considerations

Electrical contact risk is highest during boom extension when operators are focused on positioning rather than overhead clearances. Ground failure occurs during setup if bearing assessment was inadequate. Boom instability from uneven outrigger support causes overturn. Rushed setup to meet concrete delivery schedules increases error risk. Never compromise setup procedures due to time pressure - delays setup costs far less than incident consequences.

3

Pipeline Priming and System Testing

Before structural concrete pumping, prime pipelines and system test preventing blockages and verifying equipment functionality. Mix cement-water grout batch approximately 50-80 litres using cement and water only in bucket or mixer, achieving thick consistency. Alternatively mix sand-cement mortar using 3:1 sand:cement ratio without coarse aggregate. Load priming material into pump hopper starting with small quantity. Engage pump at low speed pumping priming material through pipeline system lubricating internal surfaces. Observe priming material discharge from boom or line pump outlet verifying smooth flow through entire system. Discharge priming material away from placement area into waste area or formwork that will be covered. Flush pipeline with small concrete batch if priming material appears excessively watery. With priming complete and first concrete truck arriving, direct truck to position at pump hopper. Direct truck driver to raise truck mixer at appropriate speed for controlled concrete discharge - rapid discharge overwhelms hopper creating spillage. Position hopper discharge chute into pump hopper preventing concrete bounce-out. Watch initial concrete flow into hopper for segregation, inappropriate slump, or visible defects - reject defective concrete immediately before pumping. Once hopper contains adequate concrete level covering pump inlet, engage pump at low speed initially. Observe concrete entering pipeline watching for smooth flow without air pockets or surging. Gradually increase pump speed to operational rate typically 30-60 cubic metres per hour. Communicate with placement crew watching for concrete arrival at discharge point. Adjust pump speed matching placement crew capacity. Establish steady pumping rhythm coordinating truck discharge rate with pump speed maintaining adequate hopper level.

Safety considerations

Pumping without priming creates blockage risk from dry pipeline friction. Segregated concrete entering system creates blockage risk requiring dangerous high-pressure clearance. Rapid pump startup can cause pipeline separation from pressure surge. Inadequate hopper concrete level causes air entry creating pressure spikes and blockage risk. Effective priming and controlled startup are critical blockage prevention measures.

4

Concrete Pumping Operations and Boom Control

Maintain continuous concrete pumping coordinating delivery, pumping, and placement activities through effective communication. Pump operator maintains position at remote control station with clear visibility of boom tip and surrounding area, or relies on spotter communications if direct visibility is obstructed. Monitor hydraulic pressure gauges watching for pressure increases indicating developing blockages or inappropriate concrete consistency - normal operating pressure typically 100-150 bar for good concrete. Respond to placement crew directions for boom movements using radio communications or hand signals, moving boom smoothly without sudden jerky movements. When moving boom, scan full operating radius watching for personnel, structures, and overhead hazards before initiating movement. Announce boom movements via radio warning personnel of intended direction allowing workers to clear movement path. Use boom limiters and proximity warning systems preventing electrical contact during all boom repositioning. Maintain exclusion zones throughout pumping with spotters preventing unauthorized access and monitoring all personnel locations. As each truck completes discharge, signal next truck to approach pump positioning at hopper while previous truck departs. Maintain continuous pumping without extended interruptions - if delays occur between trucks pulse pump periodically preventing concrete stiffening in pipelines. Monitor concrete quality from each truck watching for slump variations, segregation, or contamination - reject non-conforming loads immediately. Communicate with batch plant dispatcher if concrete quality issues develop requesting mix adjustments for subsequent trucks. Adjust pumping rate if placement crew falls behind preventing concrete accumulation exceeding finishing capacity. Monitor weather conditions watching for rainfall, high winds, or temperature extremes requiring operational adjustments. Document concrete receipt including truck numbers, quantities, arrival times, and any quality issues in pour log. Brief relief operators during crew changeovers for extended pours ensuring continuity and hazard awareness.

Safety considerations

Most struck-by incidents occur during boom movements when operators or spotters fail to identify personnel in movement path. Electrical contact occurs from inattention or wind-induced boom movement. Pressure spikes from blockages cause pipeline bursts injuring workers. Communication breakdown between operator and placement crews creates coordination failures and incidents. Continuous vigilance and effective communication are essential throughout pumping operations.

5

Blockage Recognition and Emergency Response

Pipeline blockages develop from inappropriate concrete consistency, aggregate bridging in bends, or concrete stiffening during delays requiring immediate response preventing high-pressure burst incidents. Recognize blockage indicators including sudden pressure increase on pump gauges typically exceeding 200 bar, reduced or stopped concrete flow from discharge point, unusual pump sounds, or pump stalling. Immediately reduce pump pressure to minimum or stop pumping when blockage indicators appear - never increase pressure attempting to force blockage. Communicate blockage situation to all personnel via radio establishing exclusion zones around pipeline preventing workers adjacent to potential burst locations. Reverse pump direction if pump is capable of reversing attempting to draw blockage back to hopper - many modern pumps incorporate reverse function. If reverse successful, discharge affected concrete from hopper inspecting for foreign objects or segregated material causing blockage. Attempt compressed air pulse method if reverse ineffective - carefully introduce compressed air into pipeline using appropriate fittings and pressure regulation maximum 100 psi. Monitor pipeline during compressed air pulse watching and listening for blockage movement - cease immediately if no progress within 30 seconds. If blockage cannot be cleared by pressure reduction, reverse, or compressed air, implement pipeline disassembly from discharge end. Establish exclusion zones around pipeline sections being disassembled preventing injuries from sudden concrete discharge. Disconnect pipeline couplings progressively working from discharge end toward pump, inspecting each section for blockage location. Once blockage located, clear manually using appropriate tools and dispose of affected concrete. Flush pipeline thoroughly with water before reassembling ensuring all concrete residue removed. Document blockage incident including suspected cause, clearance method, time lost, and preventive measures for future pours. Analyze concrete samples from batch causing blockage conducting slump tests and visual inspection identifying root cause - communicate findings to batch plant for corrective action.

Safety considerations

High-pressure blockage clearance has caused catastrophic injuries from pipeline burst discharging concrete at extreme pressure. Never strike pipelines with hammers - this increases burst risk without reliably clearing blockage. Never exceed maximum pump pressure specifications during blockage clearance. Establish exclusion zones during clearance preventing personnel exposure to burst hazard. Most blockages are preventable through correct concrete specification and continuous pumping operations.

6

Pour Completion and Pipeline Flushing

As concrete placement nears completion with final truck contents in hopper, coordinate with placement crews confirming quantity remaining is adequate for placement area avoiding excess concrete or shortfall. Pump remaining concrete maintaining steady flow until hopper nearly empty. Before hopper completely empties, commence pipeline flushing procedure preventing concrete hardening in pipelines requiring costly mechanical cleaning or pipeline replacement. Prepare pipeline flushing equipment including high-volume water supply connected to hopper, sponge ball or pig slightly smaller than pipeline internal diameter, and discharge area for concrete-contaminated flush water. Insert sponge ball into hopper on top of remaining concrete - ball follows behind last concrete preventing water and concrete mixing. Connect water supply to hopper filling with clean water. Engage pump at low speed pumping water and sponge ball through pipeline pushing concrete ahead. Observe discharge watching for sponge ball emergence indicating pipeline cleared. Continue water pumping until discharge runs clear without concrete contamination. Collect concrete-contaminated flush water in settlement tank or containment area preventing environmental discharge - dispose of settled concrete in accordance with waste regulations. For line pumps with accessible pipelines, disconnect sections after flushing cleaning internal surfaces with water spray before concrete hardens. Clean pump hopper, valves, and pipelines with water hose and scraper removing all concrete residue. Inspect pipeline sections for wear, damage, or deterioration replacing sections exceeding wear limits or showing cracks. Store clean pipeline sections in protected area preventing moisture ingress causing internal corrosion. Document concrete quantities placed, pumping duration, equipment performance, and any issues encountered in pour completion log. Clean pump chassis and boom sections removing concrete accumulation before material hardens. Conduct post-pour equipment inspection checking hydraulic systems, structural components, and operational systems identifying any maintenance requirements.

Safety considerations

Delayed pipeline flushing allows concrete hardening requiring dangerous mechanical cleaning or pipeline replacement. Concrete-contaminated water discharged to stormwater creates environmental harm and potential prosecution. Hardened concrete in pipelines reduces internal diameter increasing blockage risk in future pours. Inadequate cleaning of equipment accelerates wear and maintenance costs. Proper completion procedures prevent subsequent equipment failures and operational issues.

7

Pump Stowage and Site Demobilization

After pipeline flushing and equipment cleaning, commence pump stowage and site demobilization ensuring continued safety during pack-down activities. Maintain exclusion zones and spotter positions during boom stowage operations - boom movements during stowage present identical struck-by hazards as operational movements. Retract boom progressively from extended position articulating sections in reverse sequence to extension, watching overhead clearances throughout retraction. Monitor boom stability during retraction ensuring hydraulic systems operate smoothly without jerky movements indicating hydraulic issues. Stow boom in transport configuration per manufacturer procedures securing all sections with transport locks. Remove boom limiters and proximity warning devices storing equipment appropriately. Retract outriggers symmetrically preventing vehicle tipping during retraction. Remove outrigger pads stacking for transport or storage. Conduct post-operational inspection of pump documenting equipment condition, hours operated, fuel used, and maintenance items required. Complete operator log sheets recording pour details, concrete quantity pumped, operational issues, and equipment performance. Remove temporary exclusion zone barriers, signage, and access controls storing equipment for future use. Conduct site cleanup removing any concrete spillage from pump location, access routes, or surrounding areas. Ensure site left in safe condition for subsequent trades with access routes clear and no trip hazards from pipeline sections or equipment. Hold post-pour debrief meeting with pump operator, placement crews, site coordinator, and supervisor reviewing pour outcomes, safety performance, issues encountered, and improvements for future operations. Document debrief outcomes including concrete quality assessment, equipment performance, safety observations, and lessons learned. File pour documentation including operator logs, concrete delivery dockets, inspection records, and incident reports in project quality and safety files. Communicate any equipment defects or maintenance requirements to pump owner ensuring repairs completed before next deployment.

Safety considerations

Struck-by incidents during pack-down occur from relaxed safety discipline after pour completion. Ground beneath outriggers may have softened during pumping increasing instability during retraction. Boom movements during stowage can contact electrical conductors if clearance awareness lapses. Proper pack-down procedures with maintained exclusion zones ensure safety through all phases of pumping operations.

Frequently asked questions

What license is required to operate a concrete boom pump in Australia?

Boom-type concrete pump operators must hold a current CN (Concrete Placing) high-risk work license issued under the Work Health and Safety Regulations 2011. This license requires completion of approved training with both theoretical knowledge assessment and practical skills evaluation covering pump setup, stabilization, boom operation, and emergency procedures. The licensing course typically requires 3-5 days training followed by assessment. License holders must be at least 18 years old and licenses remain current for 5 years requiring renewal before expiry. Line pump operation does not require statutory licensing but operators must demonstrate competency through documented training and supervision. Operating boom pumps without appropriate licensing constitutes a serious breach attracting penalties up to $10,000 for individuals and $50,000 for companies, plus potential prosecution following incidents. Always verify operator licensing before permitting pump operation, and maintain license copies in project files providing compliance evidence.

What clearance distance is required from overhead powerlines during concrete pumping?

Minimum clearance distances from overhead electrical conductors depend on conductor voltage as specified in AS/NZS 3000 Electrical Installations standard. For low-voltage lines up to 1000V (typically residential and light commercial), minimum clearance is 3 metres between any part of the boom and conductors. For high-voltage lines 1000-33,000V (most urban distribution), minimum clearance is 3-6 metres depending on specific voltage with 6 metres conservative safe distance. For extra-high-voltage transmission lines exceeding 33,000V, minimum clearance extends to 8 metres. These clearances apply to the boom structure itself plus any movement from wind, equipment sway, or operator error, typically requiring 3 metre buffer beyond actual boom position. Never assume conductor voltage from appearance - always contact electrical utility authority to determine actual voltage for specific lines. If required clearances cannot be maintained, the boom pump cannot operate safely in that location - alternative controls include temporary electrical disconnection and conductor removal, physical boom limiters preventing boom movement into clearance zones, or relocating pump position to achieve clearances. Most concrete pumping fatalities result from electrical contact demonstrating the absolute criticality of clearance compliance.

How do I assess if ground conditions are adequate for pump setup?

Ground bearing capacity assessment involves both engineering calculations and physical inspection to verify the ground can support pump loads safely. Start with engineering assessment calculating maximum ground bearing pressure from pump specifications - total pump weight plus concrete weight in fully extended boom divided by outrigger pad area. Compare calculated pressure to soil allowable bearing capacity from geotechnical investigation or standard values for soil types: competent natural ground (clay, gravel) typically 100-150 kPa, disturbed or filled ground 50-75 kPa, soft or wet ground 25-50 kPa. If calculated pressure exceeds soil capacity, increase outrigger pad dimensions distributing load across larger area or improve ground through geotechnical methods. Physical inspection on pour day checks for surface water, soft spots, recent fill less than 2 weeks old, service trenches, or proximity to excavations within distance equal to excavation depth. Ground within 5 metres of excavations should be avoided as ground movement can affect pump stability. Use timber pads minimum 600x600mm and 50mm thick on competent ground, increasing to 1200x1200mm for marginal conditions, or steel plates 20mm thick for heavy loads. Level pads properly ensuring even bearing across full pad area. Verify pump is level within 3 degrees maximum after setup. Monitor ground conditions throughout pumping watching for settlement or movement indicating inadequate capacity. Document ground assessment in pre-start records providing evidence of due diligence. Ground failure causing pump overturn is preventable through proper assessment and pad sizing.

What should I do if a pipeline blockage occurs during pumping?

Pipeline blockage indicators include sudden pump pressure increase typically exceeding 200 bar, reduced or stopped concrete flow from discharge, unusual pump sounds, or pump stalling. Immediate response is critical preventing high-pressure burst causing serious injuries. First, immediately reduce pump pressure to minimum or stop pumping - never increase pressure attempting to force blockage as this dramatically increases burst risk. Communicate blockage to all personnel via radio and establish exclusion zones around pipelines preventing workers near potential burst locations. Attempt to reverse pump direction drawing blockage back to hopper if pump has reverse capability - many blockages clear through reversing. If reverse successful, discharge affected concrete and inspect for foreign objects or segregation. Second option is compressed air pulse method carefully introducing compressed air maximum 100 psi into pipeline using appropriate fittings and pressure regulation. Monitor pipeline during air pulse watching for blockage movement - cease after 30 seconds if unsuccessful. If blockage persists, implement pipeline disassembly from discharge end working toward pump. Disconnect couplings progressively with exclusion zones maintained, inspecting each section until blockage located. Clear blockage manually using appropriate tools. Critical safety measures: never strike pipelines with hammers, never exceed maximum pump pressure, never position personnel adjacent to pressurized pipelines, and never attempt to clear blockages by continuing pumping at high pressure. Most blockages are preventable through correct concrete specification, adequate slump, continuous pumping without extended delays, and proper pipeline priming before pumping structural concrete.

Can concrete pumping operations continue in windy conditions?

Concrete pumping operations are subject to wind speed limitations due to boom stability and electrical contact risks. Most pump manufacturers specify maximum operating wind speeds between 40-50 km/h (approximately 25-30 mph) measured at boom height. Wind affects boom stability through lateral forces on extended boom sections particularly when boom is at maximum reach, and can induce boom sway causing electrical contact with nearby conductors or striking structures. Additional wind considerations include concrete placement quality where high winds cause rapid moisture loss affecting finishing, and safety of workers on elevated slabs during placement operations. Monitor weather forecasts during pour planning watching for high wind warnings. On pour day, assess actual wind conditions at site noting wind speed can vary significantly from forecast particularly in exposed locations or afternoon conditions. If winds approach or exceed manufacturer limits, implement controls including: reducing boom extension minimizing wind loading, restricting boom movements to essential positioning only, increasing spotter vigilance monitoring boom position relative to electrical hazards, and considering pour postponement if winds continue increasing. For extended boom reaches near electrical conductors, consider implementing lower wind speed limits (30-35 km/h) providing additional safety margin. Wind-induced boom sway has contributed to electrical contact incidents demonstrating this is not theoretical concern. Document wind assessments and operational decisions in pour logs. Always err on conservative side - postponing pour due to excessive winds costs less than incident consequences from wind-affected boom contact or instability.

What maintenance and inspection is required for concrete pumps?

Concrete pump maintenance combines daily pre-operational inspections, regular preventive maintenance per manufacturer schedules, and prompt repair of identified defects. Daily pre-start inspections check: boom hydraulic cylinders for leaks, structural integrity of boom sections checking for cracks or damage, boom articulation points for excessive play or binding, outriggers extend and retract smoothly with even extension, pump control systems and emergency stops function correctly, pipeline sections are undamaged with serviceable gaskets and couplings, engine oil and coolant levels are adequate, hydraulic oil level and condition is acceptable, safety devices including boom limiters and proximity warnings function, and tires and wheels on truck-mounted units are in serviceable condition. Any defect affecting safety or operation requires equipment to be tagged out of service until repaired. Regular preventive maintenance per manufacturer specifications typically includes: hydraulic oil and filter changes every 500 hours, wear ring and valve replacement at specified intervals based on concrete volume pumped, boom lubrication of articulation points, hydraulic hose replacement before wear limits or 5 year maximum age, structural inspections for cracks or fatigue, and engine servicing per manufacturer schedules. Major services by qualified hydraulic technicians inspect: boom cylinder seals and bushes, structural weld integrity, hydraulic pump and valve condition, and computerized load monitoring systems. Maintain service records documenting all inspections, maintenance performed, defects identified, and repairs completed. Equipment owners are responsible for maintenance programs but operators conduct daily inspections and report defects immediately. Incidents often trace to deferred maintenance or inadequate inspections demonstrating the critical importance of rigorous maintenance compliance.

Related SWMS documents

Browse all documents

concreting

Concrete Chasing Safe Work Method Statement

Complete SWMS for concrete chase cutting operations with mandatory silica dust controls, service strike prevention, and equipment safety procedures for Australian construction.

View document

concreting

Concrete Foundations Excavating - Pouring Safe Work Method Statement

Complete SWMS for foundation excavation and concrete placement operations including trenching safety, underground service location, formwork installation, steel fixing, and concrete pouring procedures for Australian construction.

View document

concreting

Concrete Grinding and Polishing Safe Work Method Statement

Comprehensive SWMS for concrete surface preparation and polished concrete installation including silica dust controls, equipment operation procedures, and multi-stage polishing methods.

View document

concreting

Concrete Kibble Safe Work Method Statement

Comprehensive SWMS for concrete kibble operations including crane lifting, suspended load management, and concrete placement procedures for high-rise construction.

View document

concreting

Concrete Placement and Finishing Safe Work Method Statement

Complete SWMS for concrete placement operations including receiving, spreading, consolidating, screeding, floating, troweling, and curing procedures with manual handling and chemical hazard controls.

View document

concreting

Concrete Pool Construction Safe Work Method Statement

Complete SWMS for concrete swimming pool construction including excavation safety, shotcrete application, waterproofing, and finishing with service location and confined space controls.

View document
Trusted by 1,500+ Australian construction teams

Concrete Boom or Line Pumping SWMS Sample

Professional SWMS created in 5 seconds with OneClickSWMS

  • Instant PDF & shareable link
  • Auto-filled risk matrix
  • Editable Word download
  • State-specific compliance
  • Digital signature ready
  • Version history preserved
Manual creation2-3 hours
OneClickSWMS5 seconds
Save 99% of admin time and eliminate manual errors.

No credit card required • Instant access • Unlimited drafts included in every plan

PDF Sample

Risk Rating

BeforeHigh
After ControlsLow

Key Controls

  • • Pre-start briefing covering hazards
  • • PPE: hard hats, eye protection, gloves
  • • Emergency plan communicated to crew

Signature Ready

Capture digital signatures onsite and store revisions with automatic timestamps.

Continue exploring

Hand-picked SWMS resources

Ready to deliver professional SWMS in minutes?

OneClickSWMS powers thousands of compliant projects every week. Join them today.