Comprehensive SWMS for Construction Hoist Operations and Vertical Transport

Hoist Personnel and Materials Safe Work Method Statement

2,000+ Australian Businesses Trust OneClickSWMS

No credit card required • Instant access • 100% compliant in every Australian state

5 sec
Creation Time
100%
Compliant
2,000+
Companies
$3.6K
Fines Avoided

Avoid WHS penalties up to $3.6M—issue compliant SWMS to every crew before work starts.

Personnel and materials hoists provide vertical transportation of workers, tools, and construction materials on multi-storey building sites, allowing efficient access to elevated work levels without reliance on stairs or ladders. These temporary lifting installations feature guided platforms travelling vertically along mast structures attached to building frames, powered by electric motors operating wire rope or rack-and-pinion drive systems. This SWMS addresses comprehensive safety requirements for hoist operations in accordance with Australian WHS legislation, AS 1418.18 hoist standards, and high-risk work licensing requirements, providing detailed hazard controls, inspection procedures, emergency protocols, and operational safety procedures essential for protecting hoist operators, passengers, and ground personnel throughout the hoist operational period on construction projects.

Unlimited drafts • Built-in WHS compliance • Works across every Australian state

Overview

What this SWMS covers

Personnel and materials hoists are temporary vertical transportation systems installed on construction sites to move workers, equipment, tools, and building materials between ground level and elevated work platforms throughout building construction projects. These installations consist of a vertical mast structure fixed to the building frame, one or two enclosed platforms (cages) that travel up and down the mast on guide rails, electric motor drive systems, wire rope or rack-and-pinion lifting mechanisms, and comprehensive safety systems including overload protection, overspeed governors, door interlocks, and emergency braking. Hoists operate continuously throughout construction phases, often for months or years on large projects, providing essential vertical access as stairways and permanent lifts are not yet available. Hoist installations vary in capacity, speed, and configuration based on project requirements. Single-platform hoists provide capacity typically ranging from 1000kg to 2000kg for combined personnel and materials transport, suitable for low to mid-rise construction up to 20 storeys. Dual-platform hoists feature two independent cages operating on the same mast structure, allowing simultaneous upward and downward travel doubling vertical transport efficiency on large projects. High-capacity hoists rated to 3000kg or more handle heavy materials including concrete buckets, steel beams, and mechanical plant. Travel speeds range from 20 metres per minute for lower-capacity units to 60 metres per minute for express passenger hoists on tall buildings. Platform dimensions typically provide 2 to 3 square metres of floor area accommodating 10-15 persons or equivalent material loads. Hoist operation requires licensed operators holding high-risk work licences for construction hoist operation issued under WHS Regulations. Operators control platform movement using controls located inside platforms or at fixed control stations on each building level. Modern hoists feature variable speed controls, precise floor-level positioning, automatic door operation, and load monitoring systems. Safety systems prevent operation with doors open, cease movement if overload detected, prevent platform overshooting end limits, and activate emergency braking if travel speed exceeds design parameters. Communication systems including intercoms or radios connect hoist operators with ground personnel and building floor coordinators managing platform dispatching. Hoist lifecycle on construction projects encompasses erection, commissioning, operational period, height modifications, and eventual dismantling. Erection occurs early in construction, typically after building structure reaches 4-6 storeys providing adequate height for initial productivity gains. Specialised hoist erection crews install foundation anchors, assemble initial mast sections, position platforms and drive machinery, and conduct commissioning testing and certification. As building height increases, hoist masts are extended by adding sections, requiring temporary shutdown periods and re-certification after modifications. At project completion, hoists are progressively dismantled as building systems become operational and site access requirements diminish. Throughout operational periods, daily pre-start inspections, weekly documented inspections, monthly major inspections, and annual statutory inspections by competent persons maintain hoist safety and serviceability.

Fully editable, audit-ready, and aligned to Australian WHS standards.

Why this SWMS matters

Personnel and materials hoists present high-consequence hazards resulting in numerous fatalities and serious injuries in Australian construction. Platform falls from height caused by door failures, structural collapses, or platform overshooting terminal limits have resulted in deaths of multiple workers in single incidents. Catastrophic failures typically result from inadequate maintenance, structural defects developing during operation, or operation beyond design capacity limits. Safe Work Australia data indicates hoist-related incidents consistently feature in annual serious injury and fatality statistics, with common scenarios including platform collapse from overloading, workers falling through inadequately maintained doors, and crushing injuries when platforms fail to stop at floor levels. Overloading of hoist platforms remains a persistent hazard despite clearly marked load limits and operator oversight. Construction crews under production pressure may exceed capacity by carrying excessive material loads, overloading with personnel beyond platform rating, or combining heavy materials with multiple workers approaching or exceeding total capacity. Overload conditions stress structural components, drive systems, and suspension ropes beyond design limits. Suspension rope failures from overload or inadequate maintenance cause immediate platform falls. Even when primary rope systems incorporate redundancy with multiple independent ropes, simultaneous failure of multiple ropes during overload conditions removes all redundancy protections. Load monitoring systems prevent operation when overload is detected, but can be defeated or ignored by operators facing schedule pressures. Structural attachment failures between hoist masts and building structures have caused complete hoist collapses on construction sites. Hoist masts must resist substantial lateral loads from wind, eccentric loading during operation, and accidental impact from materials handling. Attachment tie points connecting masts to building structures at regular vertical intervals provide lateral restraint preventing mast buckling or overturning. Inadequate attachment quantities, incorrect spacing, insufficient anchor strength, or attachment to inadequately strong building elements can result in progressive attachment failures leading to mast collapse. Building structures themselves may not yet have achieved design strength when hoist ties are installed, particularly at upper levels where concrete may not be fully cured. Engineering assessment of tie positions, quantities, and attachment methods is essential throughout hoist operational periods and must be re-verified after each mast height increase. Personnel becoming trapped in hoists during mechanical or electrical failures creates emergency response challenges particularly on tall buildings. Power failures immobilise platforms between floors, potentially for extended periods until power restoration or manual lowering procedures are implemented. Passengers may include workers with medical conditions, claustrophobia, or heat stress susceptibility during entrapment in enclosed platforms. Emergency rescue procedures must address platform lowering using manual overrides, emergency escape hatches in platform roofs for evacuation to building floors when trapped between levels, and communication with trapped personnel maintaining calm during extended entrapment. Comprehensive SWMS implementation includes emergency procedures, rescue equipment positioning, and coordination with emergency services for scenarios exceeding site emergency response capabilities. Documentation creates clarity for all site personnel on actions required during hoist failures, reducing confusion during actual emergency scenarios when rapid, coordinated response is essential.

Reinforce licensing, insurance, and regulator expectations for Hoist Personnel and Materials Safe Work Method Statement crews before they mobilise.

Hazard identification

Surface the critical risks tied to this work scope and communicate them to every worker.

Risk register

Platform Fall from Height Due to Structural or Mechanical Failure

High

Personnel and materials hoist platforms suspended at heights up to 100+ metres can fall catastrophically if suspension systems fail, structural components break, or drive mechanisms malfunction. Wire rope suspension failures from broken ropes, inadequate rope condition, or overload create immediate fall scenarios. Platform guide system failures allowing platforms to derail from mast guide rails can cause platforms to tip or fall. Brake system failures preventing platforms from stopping at terminal limits result in platform overshooting and crashing into overhead structures or falling down shafts. Structural failures of platform floor structures from overload or fatigue cause partial or complete collapse. Each scenario presents immediate life-threatening falls for all platform occupants.

Consequence: Multiple fatalities from platform falls from extreme heights. Serious injuries including fractures, spinal injuries, and head trauma to survivors. Platform debris falling onto ground personnel causing secondary injuries. Complete work stoppage on construction site pending investigation. Criminal prosecution of responsible parties for WHS Act breaches. Multi-million dollar damages claims from injured workers and families. Project delays extending months during investigation and equipment replacement.

Platform Overloading Exceeding Rated Capacity

High

Hoist platforms have specific load ratings accounting for combined weight of passengers, materials, and equipment not to be exceeded. Construction crews may overload platforms by carrying excessive material quantities, loading bulk materials exceeding capacity, or combining materials with maximum personnel numbers approaching total weight limit. Overload conditions stress suspension ropes, structural members, drive motors, and brake systems beyond design parameters. Load monitoring systems typically prevent operation when overload detected, but operators may bypass protections or incrementally load platform to slightly below alarm thresholds repeatedly, creating cumulative stress fatigue in structural components. Dynamic loading from platform starts and stops increases actual loading beyond static platform weight.

Consequence: Suspension rope failure from overload stresses causing immediate platform fall and multiple fatalities. Structural component failure including platform floor beams or suspension connection points. Motor or brake system failure from excessive torque requirements. Platform damage requiring extensive repairs and work stoppages. Accumulated fatigue damage from repeated overload shortening equipment life. Regulatory prosecution for operating equipment beyond rated capacity. Loss of passenger and worker confidence in hoist safety.

Mast Structure Collapse from Inadequate Building Tie Connections

High

Hoist masts extending vertically for multiple storeys require lateral restraint connections (ties) to building structures preventing buckling, overturning, or lateral deflection. Inadequate tie quantities, incorrect vertical spacing, insufficient anchor strength, or attachment to structurally inadequate building elements creates instability. Wind loads on tall masts create substantial lateral forces requiring multiple tie points with adequate capacity. Building structures at upper levels may not have achieved full concrete strength when ties are installed. Ties can loosen over time from vibration and repeated loading. Construction activities including concrete pours or steel erection create impact loads that can damage ties. Progressive tie failures allow mast deflection increasing stress on remaining ties leading to cascading failures and complete mast collapse.

Consequence: Catastrophic mast collapse causing death or serious injury to hoist occupants and ground personnel in collapse zone. Major property damage to building structures, adjacent equipment, and site facilities. Extended project delays during incident investigation and hoist replacement. Substantial fines and potential criminal prosecution for structural inadequacy. Multi-million dollar civil liability claims. Industry reputation damage affecting future project opportunities.

Personnel Falling Through Open Platform Doors or Access Gates

High

Hoist platform doors and access gates at building floor levels must remain closed and secured during platform travel. Door interlock systems prevent platform movement when doors are open, but interlock failures, deliberate bypassing, or door latch failures can allow operation with doors open. Passengers may lean against doors expecting them to be secured, falling through if doors open unexpectedly. Loading operations at floor levels involve workers reaching in or out of platforms through open doors creating fall risks if platform moves unexpectedly. Gate hinges, latches, or bottom door seals can fail from repeated use, impact damage, or inadequate maintenance creating gaps large enough for personnel or materials to fall through. Workers becoming impatient with delayed platform arrival may attempt to manually open floor-level access doors or gates and fall down shafts.

Consequence: Fatal falls from height when workers fall through open doors or gates into shafts. Serious injuries from partial falls where workers catch themselves but sustain traumatic injuries. Materials falling down shafts striking personnel at lower levels. Panic and chaos on site following fall incidents. Permanent site access issues if personnel become reluctant to use hoists after serious incidents. Regulatory investigation and potential prosecution for inadequate safety system maintenance.

Crushing Injuries at Platform Floor Interfaces

Medium

Crushing hazards exist where moving hoist platforms meet fixed building floor levels. Workers loading or unloading platforms can become caught between platform edges and floor slabs if platforms continue moving during loading activities. Feet, hands, or legs positioned across platform thresholds create crushing risk if platform descends unexpectedly. Material handling equipment including wheelbarrows, trolleys, or hand trucks can jam between platforms and floors if platforms move during loading transitions. Some workers may attempt to board moving platforms rather than waiting for complete stops, creating trapping hazards. Communication failures between hoist operators and floor-level workers result in platforms moving when personnel are in threshold zones.

Consequence: Severe crushing injuries to extremities requiring surgical intervention or amputation. Fractures to feet or legs from compression loading. Soft tissue damage requiring long recovery periods. Permanent disability affecting manual dexterity or mobility. Psychological trauma from witnessing or experiencing crushing incidents. Lost time injuries affecting site productivity and workers compensation costs.

Personnel Entrapment During Power Failure or Mechanical Breakdown

Medium

Electrical power failures, motor malfunctions, or control system failures can immobilise hoist platforms between floors for extended periods. Trapped personnel may include multiple workers in confined platform spaces for hours awaiting rescue or power restoration. Platform environmental conditions deteriorate during entrapment in hot weather causing heat stress. Passengers with medical conditions, claustrophobia, anxiety, or physical disabilities face increased risks during extended confinement. Emergency communication systems may fail preventing trapped personnel contacting site management. Rescue procedures requiring manual platform lowering or evacuation through roof hatches present additional risks. Platforms stopped at mid-floor positions prevent direct floor access requiring complex rescue procedures.

Consequence: Heat stress or medical emergencies in trapped personnel during extended entrapment. Panic and anxiety reactions in confined spaces. Injuries during emergency evacuation procedures through roof hatches. Project delays from extended hoist outages on sites dependent on hoists for access. Emergency services involvement requiring specialised rescue capabilities. Regulatory investigation of emergency preparedness and response procedures. Lost worker confidence in hoist reliability affecting site morale and productivity.

Suspended Platform Swinging or Impacting Building Structure

Medium

Wind loading on hoist platforms and masts during high wind conditions can cause platform swing within guide clearances. Inadequately maintained guide rollers or worn guide rail surfaces allow excessive platform movement during travel. Unbalanced loading with material concentrated on one side of platforms creates eccentric loading causing platforms to travel at angles contacting guide rails. Impact between platforms and building structures during loading/unloading operations from rapid platform approaches or misjudged floor positioning damages platform doors, building edges, or structural elements. Repeated impacts loosen structural connections and damage guide rail alignments. Workers standing near platform edges during travel face impact hazards if platforms contact structures.

Consequence: Personnel injuries from being thrown or impacted against platform walls during sudden movements. Structural damage to platform cages, doors, or corner posts requiring repairs. Damage to building floor edges, columns, or slabs from platform impact. Guide rail misalignment causing increasing vibration and wear. Suspension component fatigue from repeated impact loading. Work stoppages while damage is assessed and repaired. Increased maintenance costs from accelerated wear.

Manual Handling Injuries During Materials Loading and Unloading

Medium

Workers loading and unloading materials at ground level and building floors repeatedly lift, carry, and manoeuvre construction materials, tools, and equipment. Heavy items including concrete vibrators, compactors, power tools, formwork components, and packaged materials may weigh 20-50kg or more. Awkward platform access requiring lifting over platform thresholds or through narrow doorways compounds manual handling strain. Time pressure to maximise hoist utilisation encourages rapid loading cycles without adequate breaks. Working on uneven ground at loading areas or rough concrete floors at building levels affects body positioning during manual handling. Repetitive lifting throughout shifts creates cumulative musculoskeletal loading. Cold weather reduces muscle flexibility and warm-up increases injury susceptibility.

Consequence: Acute lower back strain and disc injuries from improper lifting techniques. Shoulder and arm injuries from repetitive overhead lifting loading upper platform areas. Knee and leg injuries from poor squatting technique during ground-level loading. Chronic musculoskeletal disorders developing from cumulative exposure. Reduced workforce capacity from injured workers requiring light duties. Increased workers compensation costs and insurance premiums. Reduced productivity from manual handling injuries affecting experienced workers.

Control measures

Deploy layered controls aligned to the hierarchy of hazard management.

Implementation guide

Comprehensive Daily Pre-Start Inspection by Licensed Operators

Administrative Control

Implement mandatory documented pre-start inspections before commencing hoist operations each day. Licensed hoist operators systematically examine structural components, suspension ropes, drive systems, safety devices, and door interlocks verifying serviceability. Inspections detect developing defects before they progress to failures during operation. Documented inspection creates accountability and provides maintenance records showing equipment history. Failed inspections prevent unsafe equipment entering service until defects are rectified. This administrative control establishes daily verification that critical safety systems function correctly before personnel are exposed to hoist operation hazards.

Implementation

1. Require licensed hoist operator to complete documented pre-start checklist before first platform movement each day 2. Inspect suspension wire ropes across visible lengths checking for broken wires, kinking, crushing, corrosion, or reduced diameter indicating wear 3. Test all door interlock systems by attempting platform movement with doors open; interlocks must prevent operation 4. Verify overspeed governor and emergency brake systems are correctly reset and not showing any alarm or fault indications 5. Check overload monitoring system by loading platform to capacity limit and verifying load indication displays correctly 6. Test emergency communication systems including intercoms and emergency phones connecting platforms to ground control 7. Inspect platform floor surface for any deterioration, missing panels, or structural damage that could create fall hazards 8. Verify emergency stop buttons at operator controls and platform locations function correctly by testing activation 9. Check that capacity load plates are displayed inside platforms and at loading zones showing maximum load limits 10. Document inspection completion in daily log book including date, operator name, any defects found, and rectification actions taken 11. Tag hoists with "DO NOT OPERATE - DEFECTIVE" signage if any critical safety system fails inspection; notify maintenance immediately 12. Retain inspection records for minimum 5 years for regulatory compliance and maintenance planning purposes

Strict Load Capacity Monitoring and Enforcement

Engineering Control

Install and maintain load monitoring systems that continuously weigh platform loads and prevent operation when rated capacity is exceeded. Load cells or pressure sensors integrated into suspension systems measure actual platform weight including passengers, materials, and equipment. Visual and audible alarms activate when loads approach capacity limits providing warning to operators and passengers. Interlocks prevent platform movement when overload conditions exist, eliminating possibility of operating beyond design capacity. This engineering control creates automatic prevention of overload conditions regardless of operator behaviour or production pressures. Combined with clearly displayed load limits at loading points, this control ensures capacity limits are respected throughout operations.

Implementation

1. Verify load monitoring systems are installed, calibrated, and functioning on all hoist platforms per manufacturer specifications 2. Conduct load monitoring calibration annually by certified technicians using known weights verifying accuracy within ±5% of rated capacity 3. Test load alarm systems monthly by loading platforms incrementally and verifying alarms activate at 90% of rated capacity 4. Display load capacity plates prominently inside platforms and at all loading levels showing maximum load in kilograms and maximum passenger numbers 5. Post illustrated loading guides showing space required for common materials including pallet loads, wheelbarrows, and equipment 6. Train all operators and frequent hoist users on capacity limits and consequences of overload conditions 7. Assign ground-level hoist coordinators to monitor loading operations and prevent overload attempts 8. Implement policy that intentional overload or tampering with load monitoring systems constitutes serious misconduct grounds for site removal 9. Review load monitoring system data logs weekly identifying any attempts to operate at or above capacity requiring retraining 10. Install backup mechanical overload prevention devices that physically prevent platforms lifting excessive loads if electronic systems fail 11. Conduct spot checks of loaded platforms using portable scales or load cells verifying actual loads match operator estimates 12. Document any overload alarm activations in daily logs investigating causes and implementing corrective actions preventing recurrence

Engineered Mast Tie Design and Regular Tie Inspection

Engineering Control

Require qualified structural engineers to design hoist mast tie connections to building structures accounting for wind loads, operational loads, and building construction sequence. Engineered tie designs specify tie locations, quantities, anchor systems, and attachment methods ensuring adequate lateral restraint throughout hoist operational period. Regular documented inspections of ties during operations detect loosening, corrosion, or damage requiring rectification. This engineering control ensures mast structural stability through professionally designed connections verified throughout the equipment lifecycle. Re-engineering of tie systems occurs when mast heights are increased or building structural conditions change.

Implementation

1. Engage qualified structural engineer to design mast tie connections before initial hoist erection providing sealed drawings and calculations 2. Specify tie locations, quantities, anchor bolt sizes, connection details, and maximum vertical spacing in engineering documentation 3. Verify building structural elements receiving tie connections have adequate strength to resist tie forces considering concrete age and curing 4. Install ties exactly per engineered design without substitutions or modifications unless approved by engineer through formal variation 5. Conduct visual inspection of all tie connections weekly by competent person checking for loosening, missing components, or visible damage 6. Torque-check all tie anchor bolts monthly using calibrated torque wrenches verifying connections maintain specified preload 7. Document all tie inspections in dedicated register recording date, inspector, tie locations checked, and any defects requiring attention 8. Re-engage structural engineer to reassess tie adequacy whenever mast height is increased providing new calculations and drawings for modified configuration 9. Monitor building structures for any cracking, spalling, or distress at tie locations indicating overstress or inadequate anchorage 10. Prohibit hoist operation during high wind conditions exceeding design wind speeds specified in structural engineering documentation 11. Review and update tie inspection frequency if adverse conditions develop including repeated loosening, building structure changes, or weather damage observed 12. Maintain engineering drawings, calculations, inspection records, and correspondence as permanent documentation demonstrating structural due diligence

Platform Door Interlock Systems and Daily Functional Testing

Engineering Control

Install and maintain comprehensive door interlock systems preventing platform movement whenever platform doors or building floor access gates are not fully closed and secured. Electrical interlocks use sensors detecting door position; mechanical interlocks physically prevent movement until doors engage locking mechanisms. Redundant interlock systems using both electrical and mechanical means provide backup protection if primary systems fail. Daily functional testing verifies interlocks operate correctly. This engineering control eliminates reliance on operator vigilance or procedural compliance by providing automatic prevention of movement with doors open.

Implementation

1. Verify all platform doors and floor-level access gates have functioning interlock systems preventing operation when doors not fully closed 2. Test door interlocks daily before first platform use by attempting movement with each door open individually; platform must not move 3. Inspect door locking mechanisms including latches, strikers, and sensors for damage, wear, or misalignment affecting operation 4. Adjust door sensors or mechanical interlocks if excessive clearances develop that could allow bypass of interlock systems 5. Implement policy prohibiting any tampering, bypassing, or deliberate defeat of door interlock systems treating violations as serious misconduct 6. Install tamper-evident seals or covers on interlock electrical connections preventing unauthorised modifications 7. Replace worn door hinges, rollers, or guide systems that prevent doors closing fully or affect door alignment 8. Verify door bottom seals and edge guards are intact preventing material or personnel fall hazards through gaps 9. Test emergency door release systems allowing trapped personnel to open doors for evacuation if platform stops between floors 10. Label all doors with "DOORS MUST BE CLOSED BEFORE PLATFORM MOVEMENT" signage and operating instructions 11. Include door interlock functionality in monthly major inspections by competent persons documenting test results 12. Maintain spare door interlock components on site allowing immediate replacement if failures detected during daily testing

Emergency Rescue Procedures and Equipment Readiness

Administrative Control

Develop comprehensive emergency response procedures for scenarios including power failures immobilising platforms, mechanical breakdowns, medical emergencies in trapped personnel, and evacuation requirements. Procedures specify communication protocols, manual platform lowering techniques, roof hatch evacuation methods, and emergency services coordination. Emergency equipment including manual lowering handles, rescue harnesses, emergency lighting, and communication devices must be readily accessible and maintained. Regular emergency drills test procedures and familiarise personnel with emergency responses. This administrative control ensures coordinated, effective responses during actual emergencies minimising harm to trapped personnel.

Implementation

1. Document detailed emergency procedures covering power failures, mechanical breakdowns, medical emergencies, fire, and evacuation scenarios 2. Assign emergency coordinator role to senior site personnel responsible for directing emergency responses and coordinating with emergency services 3. Position emergency manual lowering equipment including hand cranks, wrenches, and procedure placards at hoist motor rooms 4. Provide emergency communication equipment including two-way radios, megaphones, or hard-wired emergency phones for trapped personnel contact 5. Install emergency lighting inside platforms providing illumination during power failures allowing occupants to see and access emergency equipment 6. Position emergency escape equipment including harnesses, descent devices, and rescue ropes at upper hoist terminations for roof hatch evacuations 7. Train all hoist operators and site supervisors in emergency procedures including manual lowering techniques and evacuation coordination 8. Conduct emergency drills quarterly simulating entrapment scenarios and testing communication, manual lowering, and evacuation procedures 9. Establish arrangements with emergency services including fire brigade and ambulance for responses requiring their specialised rescue capabilities 10. Maintain emergency contact lists at hoist control stations listing key personnel, emergency services, hoist maintenance contractors, and manufacturers 11. Brief all site personnel during site inductions on hoist emergency procedures and actions required if they observe emergencies 12. Review and update emergency procedures following any actual incidents or changes to site conditions, hoist configuration, or personnel

Traffic Management at Ground Level Loading Zones

Engineering Control

Establish controlled loading zones at ground level separated from general site traffic, pedestrian routes, and overhead work areas. Physical barriers including fencing, bollards, and marked exclusion zones prevent unauthorised access to hoist operating areas. Designated pathways direct pedestrians around loading zones rather than through hoist operation areas. Overhead protection prevents materials falling from elevated levels striking personnel at ground loading points. This engineering control segregates hoist operation hazards from other site activities through physical barriers and controlled access.

Implementation

1. Define exclusive hoist loading zone extending minimum 3 metres radius around hoist base on all open sides 2. Erect physical barriers using temporary fencing, safety barriers, or bollards preventing vehicle or pedestrian entry to loading zones 3. Install overhead protection structures above ground loading areas where work proceeds at elevated levels directly above 4. Mark loading zones using high-visibility painted lines, signage, and safety bunting ensuring clear boundaries 5. Position signage stating "Hoist Loading Zone - Authorised Personnel Only - Hard Hats and High-Vis Mandatory" at access points 6. Create designated pedestrian routes with physical barriers directing foot traffic around rather than through loading zones 7. Implement vehicle exclusion from loading zones except during scheduled material deliveries coordinated with hoist operations 8. Assign ground level hoist coordinator responsible for managing loading zone access, material staging, and platform loading sequences 9. Prohibit materials storage within loading zones except items actively awaiting hoist transport; maintain clear access at all times 10. Install adequate lighting in loading zones for evening or night shift operations ensuring visibility of hazards and controls 11. Maintain level, compacted ground surfaces in loading zones preventing trip hazards and ensuring stable footing during manual handling 12. Review loading zone adequacy weekly checking barrier condition, signage visibility, and overhead protection integrity

Personal Protective Equipment for Hoist Operations

Personal Protective Equipment

Provide appropriate PPE for all personnel involved in hoist operations including operators, passengers, and loading personnel. PPE protects against struck-by hazards, falling objects, manual handling injuries, and visibility concerns in dynamic construction environments. While PPE represents the lowest control hierarchy level, it provides essential protection when exposure cannot be eliminated through higher controls. Task-specific PPE accounts for hoist-specific hazards while maintaining compatibility with general construction site PPE requirements.

Implementation

1. Require Class D hard hats (AS/NZS 1801) for all personnel in hoist loading areas and platform passengers protecting from falling objects 2. Provide high-visibility Day/Night Class D/N clothing (AS/NZS 4602.1) ensuring personnel are visible to operators and mobile plant 3. Mandate steel-capped safety boots (AS/NZS 2210.3) with 200 joule impact protection for all personnel loading platforms or handling materials 4. Issue close-fitting work gloves during materials handling protecting hands while maintaining dexterity for controls and door operation 5. Provide hearing protection (AS/NZS 1270) for personnel working extended periods near hoist motor rooms or hydraulic power units 6. Ensure all PPE is correctly fitted, maintained in serviceable condition, and replaced when damaged or worn 7. Brief all hoist users during inductions that appropriate PPE is mandatory for hoist area access; enforce compliance through site inspections

Personal protective equipment

Requirement: Type 1 impact protection per AS/NZS 1801

When: Mandatory for all personnel in hoist loading zones and all platform passengers protecting from falling objects from elevated levels

Requirement: Day/Night Class D/N per AS/NZS 4602.1

When: Throughout all hoist areas ensuring visibility to operators, mobile plant, and site traffic in busy construction environments

Requirement: 200 joule impact protection per AS/NZS 2210.3

When: For all personnel loading platforms, handling materials, or accessing hoist areas to protect from dropped loads and manual handling hazards

Requirement: Close-fitting leather or synthetic providing hand protection

When: During materials handling and loading operations to protect from sharp edges, splinters, and manual handling strain while maintaining dexterity

Requirement: Class 3 protection per AS/NZS 1270

When: For personnel working extended periods near hoist motor rooms or in high-noise areas of construction sites

Requirement: Medium impact rated per AS/NZS 1337

When: In dusty environments or when working beneath elevated activities where debris may fall toward hoist loading areas

Inspections & checks

Before work starts

  • Verify hoist operator holds current high-risk work licence for construction hoist operation issued by relevant state authority
  • Confirm hoist annual statutory inspection certification is current and displayed at hoist control station
  • Complete daily pre-start inspection checklist covering structural, mechanical, electrical, and safety systems
  • Test all door interlock systems by attempting platform movement with doors open; verify interlocks prevent operation
  • Inspect suspension wire ropes across visible lengths for broken wires, kinking, crushing, corrosion, or diameter reduction
  • Check overload monitoring system displays correctly and alarms activate when test weight approaches capacity limit
  • Test emergency communication systems including intercoms and emergency phones from platforms to ground control
  • Verify emergency stop buttons at operator positions and platforms function correctly when tested
  • Check platform floor surfaces for deterioration, missing panels, or structural damage creating fall hazards
  • Inspect building tie connections visible from platform positions checking for loosening or damage
  • Review weather conditions including wind forecasts; confirm operations are permitted within design wind limits
  • Verify adequate lighting exists at ground loading zones and building floor access points for safe loading operations
  • Check that load capacity plates are displayed prominently inside platforms and at loading zones
  • Confirm emergency manual lowering equipment is positioned accessibly at motor room locations

During work

  • Monitor platform loading operations ensuring capacity limits are not exceeded by materials or excessive personnel numbers
  • Watch loading operations at floor levels verifying personnel maintain clear of platform thresholds during platform movement
  • Check that platform doors and floor access gates are fully closed and secured before platform movement commences
  • Verify platform travels smoothly without excessive vibration, unusual noises, or impacts with guide rails
  • Confirm platform stops accurately at floor levels without overshoot requiring repositioning
  • Monitor for any alarms or warning indications on load monitoring systems, door interlocks, or safety devices
  • Check that unauthorised personnel do not enter hoist loading zones or attempt to access platforms mid-floor
  • Observe weather conditions for increasing winds or storms requiring suspension of operations
  • Verify communication between operators and loading personnel remains clear throughout operations
  • Monitor platform door condition during operations watching for any loose components or damage developing
  • Check that materials are positioned within platform footprint and secured against movement during travel
  • Verify emergency equipment including communication devices and manual lowering tools remain accessible

After work

  • Inspect platform and doors for any damage sustained during day's operations including impacts or excessive wear
  • Check suspension ropes for any new damage or abnormal wear patterns that developed during operations
  • Review load monitoring data if electronic logging available checking for any capacity exceedances during shifts
  • Test door interlocks again ensuring no deterioration in function occurred during day's operations
  • Clean platform floors removing debris, spilled materials, or contaminants that could create slip hazards
  • Verify emergency equipment remains in assigned locations and has not been removed or discharged
  • Document any unusual occurrences including near misses, equipment malfunctions, or safety concerns in daily log
  • Report any defects or developing problems to maintenance personnel for assessment and rectification
  • Secure hoist controls and disable platform movement using key locks or power isolation preventing unauthorised use
  • Review operations with loading personnel discussing any issues observed and improvements for future shifts
  • Check building tie connections accessible from platform positions for any loosening or damage requiring attention
  • Verify weather forecasts for overnight period checking for high winds or storms requiring additional securing

Step-by-step work procedure

Give supervisors and crews a clear, auditable sequence for the task.

Field ready

Pre-Start Inspection and System Verification

Begin each work period by conducting comprehensive pre-start inspection following documented checklist. Verify your high-risk work licence for construction hoist operation is current and accessible. Confirm annual statutory inspection certification is displayed and current. Inspect suspension wire ropes across all visible lengths checking for broken wires (maximum 6 broken wires in one lay), kinking, crushing, corrosion, or diameter reduction exceeding 7% of nominal rope size. Test door interlock systems by attempting platform movement with each door open individually - interlocks must prevent movement in all cases. Verify overload monitoring system displays zero load with empty platform and that load indication increases appropriately when test weight is added. Test emergency communication systems including platform intercoms and emergency phones ensuring clear communication to ground control. Check emergency stop buttons at operator controls and in platforms activate correctly and hold platform stopped when pressed. Inspect platform floor surface for any deterioration, missing panels, or structural damage that could create fall hazards. Review weather forecasts checking wind predictions remain within hoist design limits (typically 80-100 km/h depending on hoist model). Document inspection completion in daily log book including date, time, operator name, and any defects identified. Do not operate hoist if any critical safety system fails inspection until repairs are completed and verified.

Safety considerations

Never skip or abbreviate pre-start inspections regardless of time pressure. Structural or safety system failures cause catastrophic incidents with multiple fatalities. Failed inspections must result in immediate hoist shutdown until defects are rectified. Document all findings maintaining permanent inspection records.

Platform Call and Positioning at Loading Level

Call platform to ground loading level or building floor level using call buttons or radio communication with operator. Wait for platform to complete travel and stop at floor level before approaching or opening access doors. Verify platform has stopped completely with level floor aligned with building floor level. Open access gate or platform door ensuring door interlocks are functioning correctly. If door opens while platform is not level with floor, immediately close door and report interlock failure to maintenance. Check platform interior before entry ensuring no trip hazards, debris, or materials from previous loads remain. Verify load capacity plate is displayed showing maximum load in kilograms and maximum passenger numbers. If platform will carry materials, estimate total material weight including packaging, pallets, and equipment. Compare estimated weight against capacity limit allowing margin for additional passengers or unanticipated weight. If capacity may be exceeded, separate load into multiple trips rather than risking overload. Position materials within platform footprint with heavy items centered to avoid eccentric loading. Secure loose materials or tools in containers preventing items falling or shifting during travel.

Safety considerations

Never attempt to board platforms that are not fully level with floor positions. Verify doors will not open mid-floor indicating interlock failures. Do not estimate material weights casually - underestimation causes dangerous overload conditions. Exceed rated capacity under no circumstances regardless of production pressure.

Materials and Personnel Loading

Load materials into platform using proper manual handling techniques including knee bending, maintaining neutral spine position, and avoiding twisting while carrying loads. Use mechanical aids including trolleys, pallet jacks, or wheelbarrows for moving heavy or bulky items reducing manual handling strain. Position loads within platform footprint avoiding contact with doors, walls, or control panels. Distribute weight evenly across platform floor preventing eccentric loading that could affect platform balance or guide contact. Stack materials to stable height ensuring adequate clearance below platform ceiling. Secure items that could shift during travel using straps or blocking. Load passengers after materials allowing workers to position themselves in remaining space. Count passengers ensuring maximum passenger number marked on capacity plate is not exceeded. Brief passengers on safe riding position including standing clear of doors, maintaining clear of moving parts, keeping hands inside platform during travel, and not interfering with operator controls. Instruct passengers on emergency stop button location and procedures if emergency occurs. Verify total load including materials and passengers does not exceed capacity marked on load plate. Check load monitoring display if visible to passengers confirming indication is below maximum capacity. Ensure all personnel are completely inside platform with bodies clear of doorways before closing doors. Close and secure all doors verifying latches engage correctly and doors cannot be pushed open.

Safety considerations

Apply proper manual handling techniques during loading preventing back and shoulder injuries. Never exceed maximum passenger numbers or load capacity. Ensure all passengers understand emergency procedures before travel. Verify doors are fully closed and latched before signaling operator to move.

Platform Travel and Passenger Safety During Movement

Signal operator platform is ready for travel using call button, radio communication, or established signal method. Stand in stable position holding handrails or maintaining balance as platform begins movement. Maintain awareness of other passengers and materials ensuring items do not shift during acceleration. Watch for any unusual vibration, noises, or jerking movements during travel indicating developing problems. Do not lean against doors or gates during travel as door failures could allow falls. Keep hands, tools, and clothing clear of gaps between platform walls and shaft structures. Brief conversations during travel to avoid distraction while monitoring for safety concerns. If emergency stop activation is required due to unsafe conditions, press emergency stop button immediately and inform operator of situation via communication system. Do not attempt to open doors or manually interfere with platform controls during travel. If platform travels past intended floor level overshooting stop position, inform operator immediately; wait for operator to reposition rather than attempting to exit mid-floor. If platform stops unexpectedly between floors, remain calm and use emergency communication system to contact ground control or operator. Do not attempt to force doors open or climb out through roof hatches unless directed by emergency coordinators. Wait for emergency procedures including manual lowering or rescue to be implemented by trained personnel.

Safety considerations

Remain alert during platform travel ready to use emergency stop if hazards develop. Never lean against doors or attempt to open doors during travel. If trapped between floors, remain calm and use communication systems - do not attempt self-rescue without coordination. Emergency evacuation via roof hatches requires trained rescue personnel for safety.

Arrival at Destination Floor and Unloading

As platform approaches destination floor, prepare for stop by ensuring balance, securing handholds, and checking materials are stable. Wait for platform to complete stop and settle at floor level before moving toward doors. Verify platform floor is level with building floor before opening access doors. If platform has not stopped at correct level, use communication system to request repositioning; do not attempt to step over height differences exceeding 50mm. Open access gate or platform door verifying door opens freely without binding. Check building floor area beyond platform for any hazards including open penetrations, materials stacked near platform, or mobile equipment operating nearby. Unload materials before passengers exit allowing clear egress route. Use trolleys, pallet jacks, or material carts when available reducing manual handling during unloading. Do not throw or drop materials from platform as this can damage items, create noise and debris, or strike workers at lower levels if materials enter penetrations. Maintain clear egress path through platform door allowing passengers to exit promptly. Exit platform walking carefully over threshold watching for any height differences or trip hazards. Do not run or rush when exiting as trips and falls occur frequently at platform transitions. Ensure all passengers, tools, and materials are removed before doors close for next call. Clear materials away from landing gate perimeter allowing subsequent loads to be unloaded without obstruction. Signal operator platform is clear and ready for next use.

Safety considerations

Wait for complete platform stop before opening doors. Verify platform level with floor before stepping over threshold to avoid trips and falls. Never attempt to exit platforms stopped mid-floor. Use mechanical handling aids during unloading preventing manual handling injuries. Clear materials promptly maintaining unobstructed access for subsequent platform calls.

Emergency Response to Platform Failures or Entrapment

If platform becomes immobilised between floors due to power failure, mechanical breakdown, or control system failure, immediately assess situation calmly. Use emergency communication system including intercom or emergency phone to contact ground control informing them of situation and platform position. Provide information on number of passengers, any injured personnel, and environmental conditions inside platform. Follow instructions from emergency coordinator or operators regarding actions to take. Do not attempt to force doors open or climb out through roof hatches unless specifically directed by trained emergency personnel. Conserve emergency lighting if platforms are equipped with battery backup lights. If heat stress is concern, encourage passengers to sit or rest minimising physical exertion. Monitor passengers for medical emergencies including chest pain, difficulty breathing, or anxiety reactions requiring urgent response. Provide first aid as needed using any first aid kits available on platform or accessing supplies through partially opened doors if platform is close to floor level. If manual lowering procedures are initiated by operators, remain seated or holding handrails as platforms may move suddenly or unevenly during manual operation. If evacuation through roof hatches is required, follow rescue personnel instructions explicitly. Trained rescuers will access platform from above, open roof hatch, secure fall protection for evacuees, and coordinate descent or egress. Never attempt roof hatch evacuation without rescue personnel present as falls from hatch openings cause serious injuries. After rescue or emergency resolution, participate in incident debriefing providing information about emergency sequence and effectiveness of response procedures.

Safety considerations

Remain calm during platform failures. Use emergency communication systems immediately informing operators of situation. Do not attempt self-rescue through forced door opening or roof hatch climbing without trained rescue personnel. Monitor passengers for medical emergencies requiring urgent intervention. Follow emergency coordinator instructions explicitly during rescue procedures.

Frequently asked questions

What qualifications are required to operate personnel and materials hoists in Australia?

Hoist operators must hold a high-risk work licence for construction hoist operation (CN - construction hoist) issued by their state or territory work health and safety regulator. Obtaining this licence requires completion of nationally recognised training unit CPCCLDG3001A - Licence to operate a construction hoist, and passing practical and theoretical assessments conducted by registered training organisations. Assessment covers hoist operation, emergency procedures, safety systems, load capacity limitations, and regulatory requirements. Licences are valid for 5 years and must be renewed by demonstrating continued competency. Operators must carry licences during hoist operation and produce them for inspection by workplace supervisors or WHS regulators. Some jurisdictions require separate licences for different hoist types including goods hoists versus personnel hoists. Hoist erection, modification, and major maintenance work requires additional specialist qualifications and is typically performed by manufacturer-trained technicians rather than general operators.

How often must construction hoists be inspected and what inspection types are required?

Construction hoists require multiple inspection types at different frequencies. Daily pre-start inspections must be conducted by licensed operators before first use each day, covering all critical systems and documenting findings in daily log books. Weekly documented inspections by competent persons examine structural components, suspension systems, safety devices, and door interlocks in detail with findings recorded in inspection registers. Monthly major inspections by competent persons include thorough examination of all components with specific focus on high-wear items, including non-destructive testing of suspension ropes and structural connections. Annual statutory inspections must be conducted by qualified engineers or manufacturer-approved inspectors, including load testing to 125% of rated capacity and comprehensive examination of all systems resulting in statutory certification required for continued operation. Additional inspections are required after any modifications including height increases, after incidents or accidents, following severe weather events, and whenever abnormal operation or defects are observed. Inspection records must be maintained for minimum 5 years and be available for regulator review demonstrating ongoing compliance.

What is the maximum load capacity for construction hoists and how is it determined?

Hoist load capacities are determined by manufacturers during design and testing, accounting for structural capacity, suspension rope strength, drive motor power, brake capacity, and platform dimensions. Typical construction hoists have rated capacities ranging from 1000kg for smaller personnel hoists to 3000kg or more for heavy materials hoists. The rated capacity includes all loads on platform including passengers (estimated at 80-90kg per person), materials, equipment, tools, and containers. Load capacity plates displayed inside platforms and at loading zones show maximum load in kilograms and maximum passenger numbers. Operators must never exceed rated capacity regardless of circumstances. Many hoists feature load monitoring systems using load cells or pressure sensors that prevent operation when overload detected. When calculating loads, weight of all items must be added including pallets, packaging, concrete buckets, formwork, tools, and any liquids. If exact weight is unknown, err on conservative side using worst-case estimates. For materials where weight varies significantly, arrange weighing before platform loading or separate into multiple trips rather than risking overload. Dynamic loads from rapid starts or stops can exceed static loads by 10-30%, so rated capacity provides safety margin for operational dynamics.

What emergency procedures must be in place for personnel trapped in hoists between floors?

Comprehensive emergency procedures must address multiple entrapment scenarios. Primary procedures include manual platform lowering using emergency hand cranks or override controls located at motor rooms, allowing trained personnel to lower platforms to floor levels for passenger evacuation. Emergency communication systems including intercoms, emergency phones, or two-way radios must connect trapped passengers with ground emergency coordinators providing information and reassurance. If platforms cannot be lowered promptly, emergency evacuation may proceed through platform roof hatches using trained rescue personnel with fall protection equipment including harnesses and descent devices to evacuate passengers to building floors. Medical emergency protocols address situations where trapped passengers experience medical events including cardiac events, heat stress, or anxiety requiring urgent response. Emergency services liaison arrangements with fire brigade and ambulance services provide access to specialised rescue capabilities for complex scenarios. Site emergency coordinators must be trained in all procedures, know locations of emergency equipment, and maintain emergency contact lists. Emergency drills should be conducted quarterly simulating entrapment scenarios to verify procedures effectiveness and familiarise personnel with emergency equipment operation. All personnel using hoists should receive emergency briefings during inductions explaining procedures if they become trapped including staying calm, using communication systems, and awaiting trained rescue rather than attempting self-rescue.

What are the requirements for hoist mast tie connections to building structures?

Hoist mast ties must be designed by qualified structural engineers and installed per engineered drawings and specifications. Engineers calculate required tie quantities, locations, and anchor strengths based on hoist mast height, wind loads, operational loads, and building structural capacity. Typical requirements specify ties at vertical intervals not exceeding 6 metres with minimum two ties per level positioned at opposing sides of mast for bidirectional restraint. Ties connect to building structural elements with adequate capacity including concrete columns, beams, or slabs, ensuring concrete has achieved design strength before loading. Anchor systems including cast-in bolts, post-installed mechanical anchors, or chemical anchors must be rated for calculated tie forces with appropriate safety factors. Installation requires torque specifications and verification testing ensuring anchors achieve design capacity. Regular inspections check for loosening, corrosion, concrete cracking, or structural distress at tie locations requiring remedial action. When mast height is increased during construction, engineers reassess tie adequacy and may require additional ties or tie modifications. Ties must remain in place throughout hoist operational period and cannot be removed or relocated without engineer approval. Building construction sequence must coordinate with tie requirements ensuring structural elements receiving ties are constructed and cured before tie loading. Thorough documentation including engineering calculations, installation records, inspection results, and modification approvals demonstrates compliance and due diligence.

Related SWMS documents

Browse all documents
Trusted by 1,500+ Australian construction teams

Hoist Personnel and Materials SWMS Sample

Professional SWMS created in 5 seconds with OneClickSWMS

  • Instant PDF & shareable link
  • Auto-filled risk matrix
  • Editable Word download
  • State-specific compliance
  • Digital signature ready
  • Version history preserved
Manual creation2-3 hours
OneClickSWMS5 seconds
Save 99% of admin time and eliminate manual errors.

No credit card required • Instant access • Unlimited drafts included in every plan

PDF Sample

Risk Rating

BeforeHigh
After ControlsLow

Key Controls

  • • Pre-start briefing covering hazards
  • • PPE: hard hats, eye protection, gloves
  • • Emergency plan communicated to crew

Signature Ready

Capture digital signatures onsite and store revisions with automatic timestamps.

Continue exploring

Hand-picked SWMS resources

Ready to deliver professional SWMS in minutes?

OneClickSWMS powers thousands of compliant projects every week. Join them today.