Safe Work Method Statement

Fire Detection-Alarms Testing

Comprehensive Australian WHS Compliant SWMS

No credit card required • Instant access • 100% compliant in every Australian state

5 sec
Creation Time
100%
Compliant
2,000+
Companies
$3.6K
Fines Avoided

Avoid WHS penalties up to $3.6M—issue compliant SWMS to every crew before work starts.

Fire detection and alarm system testing is essential maintenance work verifying that fire protection systems function correctly and will provide adequate warning during actual fire emergencies. This work involves comprehensive testing procedures mandated by AS 1851 standards including functional testing of smoke and heat detectors, manual call point activation tests, alarm sounder verification, backup battery capacity checks, and system integration testing. Fire services technicians conduct both routine six-monthly maintenance testing and commissioning testing of newly installed systems, working with energised electrical equipment, testing aerosols, elevated access equipment, and coordinating with building occupants to prevent unnecessary evacuations. A comprehensive SWMS is essential for managing electrical hazards, fall risks, exposure to testing chemicals, and coordination challenges inherent in fire alarm testing work.

Unlimited drafts • Built-in WHS compliance • Works across every Australian state

Overview

What this SWMS covers

Fire detection and alarm system testing comprises routine maintenance testing required under AS 1851 and commissioning testing of newly installed or modified systems following AS 1670 standards. Australian regulations classify fire alarm systems as essential safety measures requiring regular testing and maintenance to ensure continued functionality. Testing procedures verify that smoke detectors respond appropriately to smoke aerosol test spray, heat detectors activate at correct temperature thresholds, manual call points trigger immediate alarm response, alarm sounders and visual alerting devices operate at specified intensity, fire indicator panels display correct zone information, backup battery systems provide adequate standby power, and system integration functions including building management system interface and emergency systems activation operate correctly. Testing work involves accessing elevated detector locations using ladders or elevated work platforms, activating devices using specialized test equipment including smoke aerosol canisters, heat sources, and electrical test instruments, monitoring fire alarm panel responses, and documenting test results on standardized testing forms. Technicians test smoke detectors by applying smoke aerosol directly to detector chambers causing alarm activation, verify correct zone indication on fire panels, and confirm alarm sounders activate throughout the building. Heat detector testing involves applying controlled heat sources or using specialized heat detector test units. Manual call point testing requires breaking seal elements and activating switches to simulate emergency activation.

Fully editable, audit-ready, and aligned to Australian WHS standards.

Why this SWMS matters

Fire alarm testing is high-risk work under the Work Health and Safety Act 2011 combining electrical hazards from energised fire alarm systems, fall risks when accessing elevated detectors, chemical exposure from testing aerosols, and coordination challenges that can result in inappropriate emergency response if not properly managed. Without comprehensive risk controls documented in a SWMS, technicians face electrocution from live alarm circuits, falls from ladders during detector testing, respiratory irritation from testing chemicals, heat stress during testing work, and incidents arising from poor coordination including building evacuations, emergency service callouts, and conflicts with building operations. Fire alarm systems remain energised during testing creating genuine electrical hazards. Testing procedures activate alarm circuits, sounders, and panel electronics requiring technicians to work with live electrical equipment. Detector testing at ceiling height requires ladder work or elevated platform use presenting fall hazards. Testing aerosols contain chemicals causing eye and respiratory irritation if used in confined spaces without ventilation. AS 1851 establishes specific testing procedures ensuring systems remain functional, and comprehensive SWMS documentation ensures technicians follow these procedures whilst maintaining their own safety.

Reinforce licensing, insurance, and regulator expectations for Fire Detection-Alarms Testing crews before they mobilise.

Hazard identification

Surface the critical risks tied to this work scope and communicate them to every worker.

Risk register

Electrical hazards from energised fire alarm systems during testing

high

Fire alarm testing requires systems to remain energised and operational throughout testing procedures, creating electrical hazards for technicians working with fire indicator panels, detector circuits, and power supplies. Testing involves manipulating control panel electronics, measuring circuit voltages and currents, activating detection zones, and working near backup battery systems that can deliver high currents. Panel testing requires accessing internal electronics while circuits are live to verify correct operation. Detector circuit testing involves checking continuity and voltage on energised detector loops. Battery systems store significant electrical energy and can deliver dangerous currents if short-circuited. Working near fire alarm panels positioned in electrical rooms increases exposure to other building electrical systems. Without appropriate electrical safety training, use of insulated tools, voltage testing before work, and proper procedures when working on or near energised equipment, technicians can suffer electric shock, burns, arc flash injuries, or cardiac arrest from contact with live circuits.

Consequence: Electric shock, burns, cardiac arrest, arc flash injuries, or fatality

Falls from heights during ceiling detector testing

high

Testing smoke detectors and heat detectors mounted on ceilings requires technicians to work at heights using ladders or elevated work platforms. Typical commercial building ceiling heights of 3-4 metres require extension ladders or platform ladders. Industrial buildings and warehouses have detector heights exceeding 6 metres requiring scissor lifts or boom platforms. Testing procedures require technicians to position aerosol test spray directly into detector chambers or apply heat sources to heat detectors whilst working from elevated positions. This involves reaching overhead, releasing one hand from the ladder to operate test equipment, and maintaining position for 30-60 seconds while detector response is verified. Ladder instability, overreaching to test multiple adjacent detectors without repositioning, loss of balance whilst operating test equipment, or fatigue during testing programs involving hundreds of detectors can cause falls. Working from elevated work platforms presents risks from platform tip-overs, workers leaning beyond guardrails to reach detectors, or travelling with boom extended over obstacles.

Consequence: Serious injuries including head trauma, spinal injuries, fractures, permanent disability, or death

Exposure to testing aerosols and chemical irritants

medium

Smoke detector testing uses specialized aerosol products containing chemicals that simulate smoke particles, triggering detector optical chambers or ionisation sensors. Testing aerosols typically contain propellant gases and particulate matter designed to create detector response. When used in confined ceiling spaces or areas with poor ventilation, testing aerosol accumulation can cause eye irritation, respiratory irritation, headaches, dizziness, and allergic reactions in sensitive individuals. Testing hundreds of detectors throughout large buildings creates cumulative exposure to testing chemicals. Some older testing products contain solvents or chemicals with safety data sheets warning against prolonged inhalation. Working in ceiling cavities during testing exposes technicians to concentrated aerosol in enclosed spaces. Building occupants may also be exposed if testing aerosol migrates through ceiling air circulation. Heat detector testing using chemical heat sources can produce fumes requiring ventilation. Without adequate ventilation, use of testing products in well-ventilated areas, respiratory protection where required, and adherence to product safety data sheet recommendations, testing technicians can develop acute respiratory symptoms or chronic sensitisation to testing chemicals.

Consequence: Respiratory irritation, eye damage, headaches, allergic sensitisation, or chronic respiratory problems

Noise-induced hearing damage from alarm sounders during testing

medium

Fire alarm system testing requires activation of all alarm sounders and visual alerting devices to verify correct operation and adequate sound pressure levels throughout the building. Fire alarm sounders are specifically designed to produce loud, attention-getting sounds typically exceeding 85dB(A) and often reaching 100dB(A) or higher when measured close to the sounder location. Testing procedures require technicians to verify each sounder operates correctly, often positioning themselves near sounders during activation. Testing large buildings with dozens of sounders means exposure to multiple high-intensity alarm activations throughout the testing session. Cumulative exposure over testing sessions conducted weekly or monthly creates genuine hearing damage risk. Sounder testing in confined areas such as stairwells, corridors, or small rooms creates additional sound reverberation amplifying noise levels. Some alarm sounders use high-frequency tones specifically designed to penetrate through background noise, creating particular hearing damage risk. Without appropriate hearing protection during sounder testing, maintaining distance from sounders during activation, and limiting testing duration, technicians can suffer temporary threshold shift (temporary hearing loss) progressing to permanent noise-induced hearing loss with cumulative exposure.

Consequence: Temporary hearing loss, tinnitus, permanent noise-induced hearing loss, or permanent disability

Manual handling strain during testing equipment transport and ladder positioning

medium

Fire alarm testing requires technicians to transport testing equipment including extension ladders, platform ladders, elevated work platforms, testing aerosol supplies, tool kits, testing instruments, and documentation throughout buildings. Testing large commercial or industrial sites may involve testing hundreds of detectors across multiple floors and building areas requiring extensive equipment movement. Extension ladders weighing 20-30 kilograms must be carried, positioned, climbed, repositioned dozens of times during testing sessions. Platform ladders are heavier but require less repositioning. Elevated work platform use involves pushing or driving equipment through buildings, negotiating doorways, ramps, and obstacles. Testing equipment bags containing aerosols, heat sources, multimeters, and documentation add to manual handling load. Repetitive ladder climbing during detector testing creates cumulative physical fatigue particularly to legs and cardiovascular system. Setting up and repositioning ladders involves bending, lifting, and overhead positioning creating back and shoulder strain. Without mechanical aids such as trolleys for equipment transport, team lifting for heavy ladders, regular breaks, and task rotation, fire alarm testing technicians commonly develop musculoskeletal injuries including chronic back pain, shoulder injuries, and repetitive strain.

Consequence: Back injuries, shoulder strains, knee problems, chronic musculoskeletal disorders, or physical incapacity

Coordination failures causing building evacuations or emergency service callouts

medium

Fire alarm testing creates risk of inappropriate building evacuations or emergency service responses if coordination procedures fail. Fire alarm systems in commercial buildings are often connected to security monitoring companies who automatically dispatch fire brigade upon alarm activation. Occupied buildings will evacuate when alarms activate unless building management has properly communicated that testing is occurring. Testing coordination requires notifying building occupants, security monitoring companies, fire brigade communications, and building management well in advance of testing. However, communication failures occur when notifications don't reach all stakeholders, testing extends beyond notified periods, systems aren't properly isolated from monitoring, or building occupants aren't adequately informed. Inappropriate evacuations disrupt businesses, cause productivity loss, create evacuation risks for building occupants particularly those with mobility limitations, and generate complaints and conflicts. False fire brigade callouts waste emergency resources, may incur significant false alarm fees (often $1000-$2000 per callout), and create liability issues. Testing in critical facilities such as hospitals, aged care facilities, or industrial sites with hazardous materials creates particular coordination challenges where inappropriate evacuations could endanger vulnerable occupants or disrupt safety-critical operations.

Consequence: Building evacuations, emergency service false callouts, building operation disruption, regulatory penalties, or conflicts

Control measures

Deploy layered controls aligned to the hierarchy of hazard management.

Implementation guide

Comprehensive Pre-Testing Notification and Coordination Procedures

Administrative

Implement comprehensive notification procedures before commencing any fire alarm testing to prevent inappropriate building evacuations and emergency service responses. Establish formal notification protocols ensuring all relevant stakeholders receive advance notice including building owners or managers, building occupants and tenants, security monitoring companies, fire brigade communications centres, building maintenance staff, and facility management. Notifications must specify exact testing dates, times, expected duration, areas affected, and contact details for the testing technician. For routine testing, provide notification minimum 48 hours in advance. For large scale testing requiring extended duration, provide one week advance notice. Coordinate testing schedules with building operations avoiding critical business periods, peak occupancy times, or when building systems cannot be temporarily interrupted.

Implementation

1. Identify all stakeholders requiring notification for each testing location 2. Prepare written notification templates specifying testing dates, times, areas, and contact details 3. Email notifications to building management minimum 48 hours before testing 4. Contact security monitoring companies requesting system isolation or monitoring suspension during testing 5. Notify fire brigade communications centres where systems have direct fire brigade connection 6. Coordinate with building management to notify all tenants and occupants 7. Install physical signage at building entries and fire indicator panels stating testing is in progress 8. Place fire indicator panels in test mode or isolate from remote monitoring 9. Provide mobile phone contact details for building management to reach testing technician 10. Notify all parties immediately after testing completion that systems have been restored to normal operation

Electrical Safety Procedures for Energised System Testing

Administrative

Implement electrical safety procedures for working on or near energised fire alarm systems during testing. While complete electrical isolation is not possible during functional testing, specific controls reduce electrical hazards. Ensure only appropriately trained and licensed electrical workers conduct testing involving fire alarm panel internal access or electrical measurements. Establish procedures prohibiting access to fire alarm panel internals unless absolutely necessary for troubleshooting. When panel access is required, use insulated tools rated for electrical work, wear appropriate PPE including insulated gloves, and use voltage testers to verify voltages before contact. Position battery systems within panels to prevent inadvertent contact with terminals. Establish one-person-working rules prohibiting solo access to fire panels - always have spotter present when panel access is required. Train technicians to recognise electrical hazards including battery systems capable of delivering high currents, backup power supplies, and main power connections to panels.

Implementation

1. Verify all testing technicians hold appropriate electrical qualifications or work under licensed supervision 2. Provide insulated tools rated for electrical work including insulated screwdrivers, pliers, and multimeter leads 3. Supply insulated gloves meeting AS/NZS 2225 for panel internal access work 4. Use voltage-rated multimeters and test equipment calibrated within manufacturer specifications 5. Establish protocols prohibiting fire panel internal access unless necessary for fault finding 6. Test circuits using external test points where available rather than accessing internals 7. Verify battery terminals are protected against short-circuit contact 8. Maintain two-person rule for any panel internal access work 9. Ensure adequate lighting in panel locations for safe work 10. Train technicians in basic electrical hazard recognition and emergency response

Height Safety Systems for Detector Testing

Engineering

Provide appropriate height access equipment and fall protection for fire alarm detector testing work. Select height access equipment appropriate to detector heights and quantity of detectors being tested. For routine testing with ceiling heights under 3.5 metres, provide industrial-grade platform ladders with stability features and handrails. For buildings with higher ceilings or large testing programs, provide mobile elevated work platforms (scissor lifts) allowing technicians to position at detector height without climbing. Inspect all height access equipment before each use. Ensure ladders are industrial-rated, free from damage, equipped with stability bars, and positioned on level ground. For elevated work platforms, conduct pre-start checks including hydraulic systems, platform controls, emergency lowering, and guardrail integrity. Implement ladder safety procedures including three-point contact, prohibition of overreaching, and frequent repositioning rather than stretching to reach detectors. Provide extension poles with aerosol spray adapters allowing detector testing from ground level where practical.

Implementation

1. Assess detector heights and testing program scope to select appropriate equipment 2. Provide platform ladders with minimum 1.8 metre platform height and stability bars 3. Supply mobile elevated work platforms for ceiling heights exceeding 4 metres 4. Conduct daily pre-start inspections of all ladders and elevated equipment 5. Position ladders on level, stable ground free from trip hazards 6. Secure ladder feet using anti-slip mats on smooth floors 7. Maintain three-point contact when ascending, descending, and working from ladders 8. Prohibit overreaching - reposition ladder frequently to maintain central position 9. Use two persons for ladder setup in congested areas or on stairs 10. Provide extension poles allowing detector testing from ground level where practical

Respiratory Protection and Ventilation for Testing Aerosol Use

PPE

Implement respiratory protection and ventilation controls for testing aerosol exposure during detector testing. Review testing aerosol product Safety Data Sheets to understand chemical composition and exposure hazards. Conduct testing in well-ventilated areas with adequate natural air movement or mechanical ventilation. Avoid testing in confined ceiling spaces or areas with poor ventilation unless forced ventilation is implemented. Provide respiratory protection where testing involves extended aerosol use in confined areas. Use testing aerosol products designed for low toxicity and minimal irritation. Allow aerosol to dissipate before conducting testing on adjacent detectors in confined areas. Provide eye protection preventing aerosol contact with eyes. Implement work practices minimising unnecessary aerosol release including precise aerosol spray direction and appropriate spray duration. Monitor technicians for adverse reactions to testing aerosols including respiratory irritation, headaches, or allergic symptoms and modify procedures if reactions occur.

Implementation

1. Obtain Safety Data Sheets for all testing aerosol products used 2. Review SDS information with technicians covering chemical composition and safe use 3. Conduct detector testing in well-ventilated open areas where possible 4. Open ceiling access panels in adjacent areas to improve ventilation during ceiling testing 5. Provide portable ventilation fans for use in confined testing areas 6. Supply P1 or P2 disposable respirators for extended testing in confined spaces 7. Provide safety glasses with side shields preventing aerosol eye contact 8. Train technicians in precise aerosol application using short bursts directed into detectors 9. Allow 2-3 minutes between testing adjacent detectors for aerosol dissipation 10. Monitor technicians for adverse reactions and provide fresh air breaks if symptoms develop

Hearing Protection During Alarm Sounder Testing

PPE

Provide hearing protection and implement procedures reducing noise exposure during alarm sounder testing. Supply noise-attenuating earplugs or earmuffs rated for minimum 25dB noise reduction for use during sounder testing. Establish procedures requiring hearing protection be worn before activating alarm sounders for testing. Implement testing procedures that minimise technician proximity to sounders during activation - activate sounders from fire panel location rather than standing near sounders where possible. Test sounders individually or in small groups rather than activating entire building alarms to reduce overall noise exposure. Limit sounder activation duration to minimum required for functional verification, typically 30-60 seconds per activation. Provide warning to other building occupants before sounder testing. Position technicians in quieter locations during testing - conduct sounder inspection before testing then move to quieter area before activation. Monitor cumulative noise exposure during testing sessions and implement rest breaks in quiet areas to allow hearing recovery. Train technicians in proper hearing protection use including insertion technique for earplugs and positioning for earmuffs.

Implementation

1. Provide Class 4 or Class 5 hearing protection rated for minimum 25dB noise reduction 2. Establish mandatory hearing protection policy during all sounder testing 3. Train technicians in correct earplug insertion achieving proper seal 4. Test sounders from fire panel location rather than standing near sounders 5. Activate sounders individually or in small groups rather than building-wide activation 6. Limit activation duration to 30-60 seconds per sounder test 7. Conduct visual sounder inspection before testing then move away before activation 8. Implement rest breaks in quiet areas every 60 minutes during extended testing 9. Warn building occupants before sounder testing in occupied areas 10. Document cumulative noise exposure and rotate testing tasks among team members

Equipment Transport Aids and Manual Handling Procedures

Engineering

Provide manual handling aids and equipment transport solutions reducing physical strain during fire alarm testing. Supply equipment trolleys allowing technicians to wheel testing equipment, ladders, and supplies rather than manual carrying throughout buildings. Provide lightweight aluminium platform ladders where appropriate rather than heavier steel models. Use collapsible or telescoping ladders for transport through narrow corridors or elevators. Establish team lifting procedures for heavy extension ladders requiring minimum two persons. Position testing equipment and supplies strategically throughout large buildings using multiple equipment stations reducing need to carry supplies long distances. Use building lifts for vertical equipment transport rather than stair climbing. Implement task rotation among testing team members alternating between ladder climbing and ground-level documentation tasks. Schedule regular rest breaks and stretching exercises during extended testing sessions. Provide hydration and seating allowing recovery between testing zones.

Implementation

1. Provide four-wheel platform trolleys with adequate capacity for testing equipment transport 2. Use lightweight aluminium platform ladders rather than steel where practical 3. Supply telescoping ladders collapsing for transport through narrow spaces 4. Establish mandatory two-person team lifting for extension ladders 5. Pre-position testing equipment on multiple floors in large buildings 6. Use building elevators for ladder and equipment vertical transport 7. Rotate testing tasks with one technician conducting overhead tests while another documents results 8. Implement 10-minute rest breaks every 60 minutes during extended testing sessions 9. Provide water bottles and seating in testing areas for regular hydration and rest 10. Conduct pre-work stretching exercises focusing on back, shoulders, and legs

Personal protective equipment

Hearing protection - earplugs or earmuffs

Requirement: Class 4 or 5 hearing protection rated minimum 25dB noise reduction complying with AS/NZS 1270

When: Required during all alarm sounder activation testing and recommended throughout extended testing sessions with multiple sounder activations

Safety glasses with side shields

Requirement: Impact-rated safety glasses meeting AS/NZS 1337 with side protection preventing aerosol contact

When: Required during all testing aerosol use for detector testing and when working near fire alarm panels

Disposable P1 or P2 respirator

Requirement: P1 or P2 disposable respirator for testing aerosol protection in confined areas

When: Required when testing multiple detectors in confined ceiling spaces or poorly ventilated areas with testing aerosol accumulation

Insulated gloves for electrical work

Requirement: Class 0 insulated gloves rated to 1000V AC complying with AS/NZS 2225

When: Required when accessing fire alarm panel internals for troubleshooting or electrical measurements

Steel-capped safety boots

Requirement: Steel-capped boots meeting AS/NZS 2210.3 with slip-resistant soles

When: Required at all times during fire alarm testing work particularly when transporting equipment and ladders

Hard hat

Requirement: Type 1 hard hat meeting AS/NZS 1801

When: Required when testing in active construction sites or areas with overhead hazards

High-visibility clothing

Requirement: Class D day/night high-visibility vest meeting AS/NZS 1906.4

When: Required in active construction areas, near roadways, or where other trades are working simultaneously

Inspections & checks

Before work starts

  • Verify all required notifications have been completed including building management, security monitoring, and building occupants
  • Confirm fire alarm panel is in test mode or monitoring has been isolated to prevent false emergency response
  • Inspect ladders for damage, stability features, and correct industrial rating before use
  • Check elevated work platforms for hydraulic leaks, platform damage, guardrail integrity, and emergency controls
  • Verify testing aerosol products are within expiry date and safety data sheets are available
  • Check testing equipment batteries, calibration dates, and functional operation
  • Verify hearing protection is available and in good condition for sounder testing
  • Confirm emergency contact details and building access arrangements with building management

During work

  • Monitor fire alarm panel displays for correct zone indication during detector testing
  • Verify alarm sounder activation occurs appropriately for each detector test
  • Check for testing aerosol accumulation in confined areas and implement ventilation breaks
  • Monitor for signs of electrical faults including unusual smells, sounds, or panel error messages
  • Verify ladder stability before each repositioning and maintain three-point contact
  • Document test results immediately for each device tested including any failures or anomalies
  • Monitor technicians for heat stress, fatigue, or adverse reactions to testing aerosols
  • Verify systems remain in test mode and monitoring isolation remains active throughout testing

After work

  • Restore fire alarm panel to normal operational mode and verify monitoring reconnection
  • Notify all stakeholders that testing is complete and systems are restored to normal operation
  • Remove all testing signage from building entries and fire panel locations
  • Document all test results, system faults identified, and recommendations for rectification work
  • Verify all detectors tested are restored to normal operation without test locks engaged
  • Clean up any residue from testing aerosols if visible on detectors or surfaces
  • Report any defects identified requiring urgent attention to building management immediately
  • Provide testing certification documentation to building management for essential safety measure records

Step-by-step work procedure

Give supervisors and crews a clear, auditable sequence for the task.

Field ready
1

Pre-Testing Coordination and Notification

Contact building management minimum 48 hours before planned testing date to confirm testing schedule and coordinate building access. Provide written notification specifying testing date, start time, expected duration, areas to be tested, and technician contact details. Request building management notify all tenants and occupants that fire alarm testing will occur and that alarm activation during the specified period is testing only and does not require evacuation. Contact security monitoring company providing fire alarm monitoring services and request monitoring isolation or system placed in test mode for duration of testing. Provide monitoring company with specific times and contact details. For systems with direct fire brigade connection, notify fire communications centre of testing schedule. Coordinate with building operations staff to avoid testing during critical business periods, building events, or when occupancy will be at peak levels. Arrange building access including keys or swipe cards for equipment transport and detector access.

Safety considerations

Ensure all notifications include emergency contact details for testing technician. Verify building management understands testing will activate alarm sounders. Confirm arrangements for lifting or propping doors open to facilitate equipment transport preventing strain injuries from repeated door operation.

2

Fire Alarm Panel Test Mode Setup

Locate fire indicator panel and verify correct building and system before commencing work. Install physical signage at panel location and building entrances stating 'Fire Alarm Testing In Progress - Alarms Are Testing Only'. Place fire alarm panel in test mode following manufacturer procedures, typically by entering engineer access code and selecting test mode from panel menu. Verify that test mode is active by checking panel display shows 'TEST MODE' or similar indication. For monitored systems, verify panel shows disconnection from remote monitoring or that monitoring company has confirmed isolation. Test panel functionality by conducting minor function test such as lamp test verifying panel responds correctly. Document panel model, software version, and testing commencement time. Review recent fault logs for any pre-existing system faults that may affect testing. Verify backup battery voltage is adequate for testing activities.

Safety considerations

Do not access panel internals unless absolutely necessary for test mode setup. Verify voltages using non-contact voltage tester if panel access is required. Ensure adequate lighting in panel area for safe work. Position trolleys with testing equipment nearby to minimise manual carrying.

3

Smoke Detector Testing Procedure

Select first smoke detector to be tested using building fire system drawings or sequential approach by zone. Position appropriate height access equipment beneath detector ensuring stable, level positioning. Ascend ladder or elevated work platform wearing hearing protection in case alarm activation startles during testing. Apply smoke detector test aerosol according to product instructions, typically holding aerosol can 150-300mm from detector and applying short 2-3 second burst directed into detector chamber air intake slots. Observe detector LED should activate indicating smoke detection. Wait for fire alarm panel to register detection - typical response time 10-30 seconds. Verify correct zone indication on fire alarm panel matches detector being tested. Verify alarm sounders activate throughout building or zone being tested. If sounders do not activate, check panel programming and alarm output functions. Document test result including detector location, zone number, panel response time, and pass/fail result. If detector fails to respond, re-test with longer aerosol application. If repeated failure occurs, flag detector for replacement or maintenance. Move to next detector and repeat procedure.

Safety considerations

Maintain three-point contact on ladders during aerosol application. Use short aerosol bursts in well-ventilated areas to prevent accumulation. Allow aerosol to dissipate before testing adjacent detectors in confined spaces. Implement ventilation breaks after testing 10-15 detectors in confined areas. Use hearing protection before alarm activation to prevent acoustic shock.

4

Heat Detector Testing Procedure

Locate heat detectors throughout building using fire system drawings. Position height access equipment beneath heat detector. For rate-of-rise heat detectors, apply controlled heat source such as heat detector test unit or heat gun maintaining safe distance from detector (typically 300-500mm) to avoid damage. Apply heat for duration specified by detector manufacturer, typically 10-30 seconds until detector LED activates. For fixed temperature heat detectors, use manufacturer-specific heat detector testing equipment that surrounds detector with controlled heated air chamber bringing detector to activation temperature without damaging sensor. Monitor fire alarm panel for zone activation corresponding to heat detector location. Verify alarm response including sounder activation. Document test results including detector type (rate-of-rise or fixed temperature), location, response time, and pass/fail outcome. For heat detectors that cannot be tested using heat application (such as those in hazardous atmospheres), conduct electrical continuity test only and document limitation. Test heat detector reset by allowing detector to cool and verify panel returns to normal. Flag any heat detectors requiring replacement if they fail to respond to appropriate heat application.

Safety considerations

Do not overheat detectors which can cause permanent damage. Maintain safe distance from heat sources. Use heat testing tools designed specifically for detector testing rather than improvised heat sources. Verify detectors cool and reset properly before concluding test. Be aware heat application may trigger sprinkler activation if testing near sprinkler heads.

5

Manual Call Point Testing

Locate all manual call points (break-glass alarm activation devices) positioned throughout building, typically near exit doors. Manual call points require seal break or key operation to test. For break-glass call points, remove test key from holder (typically attached to call point by cord). Insert test key into call point test position and rotate to simulate activation without breaking seal element. This should trigger immediate fire alarm activation. Verify fire alarm panel registers correct zone. Verify alarm sounders activate throughout building. Document test result with call point location, zone, and pass/fail result. Reset call point following manufacturer procedures, typically returning test key to normal position and verifying panel shows normal status. For call points requiring seal break for activation, coordinate with building management as seals will need replacement after testing. After testing in break-glass mode, replace any seals broken during testing with new elements. Verify call point cover closes properly and test key is secured to prevent loss.

Safety considerations

Manual call point testing causes full building alarm activation. Ensure all notifications are complete before testing. Warn nearby building occupants immediately before test to prevent alarm startle. Be prepared for loud alarm sounder activation - use hearing protection. Reset call points promptly after testing to restore system to normal.

6

Alarm Sounder and Visual Alert Device Testing

Verify alarm sounders and visual alerting devices operate correctly during detector and manual call point testing. After confirming activation from detector tests, conduct dedicated sounder and visual device testing to verify coverage. Activate fire alarm from panel control using sounder test function allowing testing without detector activation. Walk through all areas of building verifying alarm sounders are audible at minimum 65dB(A) above ambient noise levels. Use sound level meter to verify sound pressure levels in quiet areas, busy areas, and any areas with high ambient noise. Document sounder locations and measured sound levels. Verify visual alerting devices (strobe lights) operate and are visible throughout protected spaces. Check synchronisation of sounders and visual devices - they should activate simultaneously, not sequentially. Verify alarm duration continues for appropriate period (typically until manual reset). Test different alarm patterns if system has multiple alarm tones for different emergency types. Document any sounders that fail to activate, have inadequate volume, or show synchronisation issues requiring rectification.

Safety considerations

Use hearing protection during sounder testing. Maintain distance from sounders during activation - conduct testing from remote location rather than standing near sounders. Limit test duration to minimum required. Warn building occupants before testing. Be aware extended alarm exposure causes hearing fatigue - take breaks in quiet areas.

7

System Integration and Final Testing

Test fire alarm system integration with other building systems. Verify that fire alarm activation triggers appropriate responses including building management system (BMS) interface showing fire alarm status, emergency lighting systems activating if integrated with fire alarm, HVAC systems shutting down air handling units to prevent smoke spread if programmed, elevator recall to ground floor if fire service mode is integrated, electromagnetic door holders releasing fire doors to closed position, and emergency warning intercommunication systems (EWIS) activating voice evacuation messages if installed. Document each integration function and verify correct operation. Test backup battery system by disconnecting mains power supply and operating system on battery backup for minimum 30 minutes during annual testing (monthly tests verify battery voltage only). Verify all system functions operate normally on battery power. Reconnect mains power and verify changeover occurs correctly. Conduct final walk-through of all tested areas confirming detectors are reset, testing aerosol residue is minimal, access panels are closed, and areas are returned to normal condition.

Safety considerations

Coordinate integration testing with building management as it may affect building operations. Ensure appropriate personnel are present when testing elevator recall to prevent trapping occupants. Do not conduct extended battery testing during building occupied periods. Verify mains power restoration is successful before leaving site.

8

Documentation and System Restoration

Complete comprehensive testing documentation recording all devices tested, test results, any failures or defects identified, and rectification recommendations. Document should include building name and address, testing date and time, technician name and qualifications, fire alarm panel details, total number of detectors tested by type (smoke, heat, manual call points), sounder testing results, integration function tests, battery test results if conducted, list of any devices that failed testing and require replacement or repair, and certification statement confirming testing conducted in accordance with AS 1851. Remove fire alarm panel from test mode and restore to normal operational status. Verify panel shows normal operational mode without any fault indications. Reconnect system to remote monitoring by contacting security monitoring company and requesting monitoring restoration. Verify monitoring company confirms normal signal reception. Remove all physical testing signage from building entrances and fire panel locations. Notify building management that testing is complete and systems are restored to normal. Provide copy of testing documentation to building management for essential safety measure compliance records. Report any critical defects requiring urgent attention separately and recommend appropriate follow-up actions. Schedule any required rectification work for identified defects.

Safety considerations

Verify panel is fully restored to normal operation before leaving site. Confirm monitoring restoration with security company. Ensure building management understands any defects identified and urgency of rectification. Do not leave systems in test mode overnight or over weekends.

Frequently asked questions

How frequently must fire alarm systems be tested under AS 1851 and who can conduct the testing?

AS 1851 establishes mandatory testing frequencies for fire alarm systems classified as essential safety measures. Routine testing frequency depends on system type and building occupancy class. Most commercial fire alarm systems require six-monthly testing of all detectors, manual call points, and alarm devices. Critical facilities including hospitals, aged care, and high-rise residential buildings require more frequent testing, typically quarterly or monthly for some components. Annual testing requires extended duration battery capacity tests (typically discharge to 80% over 24 hours) and comprehensive system functional testing. Testing must be conducted by competent persons who understand AS 1851 procedures, fire alarm system operation, and testing equipment use. While formal qualifications are not mandated for routine testing, best practice recommends technicians hold industry certifications through organisations such as Fire Protection Association Australia. For electrical aspects of testing, appropriate electrical licenses may be required. Building owners must maintain records of all testing including dates, results, and defects identified, with records kept for minimum five years to demonstrate compliance with essential safety measure requirements.

What procedures prevent fire brigade false alarm callouts during routine fire alarm testing?

Preventing false fire brigade callouts requires comprehensive coordination before testing commences. First, identify whether the fire alarm system is monitored by a security monitoring company with automatic fire brigade dispatch capability. Contact the monitoring company minimum 24 hours before testing providing specific testing date, start time, end time, and contact details. Request monitoring isolation or test mode for the duration of testing. Many modern systems allow remote test mode activation by monitoring companies. For older systems, monitoring company may provide instructions for on-site isolation. For fire alarm systems with direct connection to fire brigade (less common in modern systems), notify fire communications centre directly providing same testing details. Always place the fire indicator panel in test mode which typically disables monitoring signal transmission. Install clear signage at building entrance and panel locations stating testing is in progress. Provide mobile phone contact to building management so they can reach testing technician if alarm activates unexpectedly. After testing completion, notify monitoring company immediately requesting restoration of monitoring. Verify monitoring company confirms normal signal reception before leaving site. Document all notification times and confirmations. Most jurisdictions impose significant false alarm fees (typically $1000-$2000 per callout) making proper procedures critical to avoid unnecessary costs.

What should be done if smoke detectors fail to respond during testing and how do you determine if replacement is required?

When smoke detectors fail to respond to testing aerosol application, follow systematic troubleshooting to determine cause. First, verify testing aerosol is being applied correctly - aerosol should be directed into detector air intake slots with 2-3 second application 150-300mm from detector. Try extended application up to 10 seconds if initial brief application doesn't trigger response. Check detector LED - if LED doesn't illuminate during aerosol application, detector likely has internal fault. Verify detector receives power by checking voltage at detector base using multimeter - should show appropriate circuit voltage (typically 15-30VDC depending on system). Check for corrosion on detector base terminals preventing electrical contact. Remove detector from base and inspect optical chamber for contamination - heavy dust, insects, or moisture can prevent smoke detection. Many photoelectric smoke detectors have cleanable optical chambers - compressed air can remove loose contamination. However, extensive contamination or deteriorated sensors require detector replacement. If detector has been in service more than 10 years, automatic replacement is recommended regardless of apparent function as detector sensitivity degrades over time. Document failed detectors with location, zone, and failure mode. Recommend replacement to building owner with urgency based on fire protection criticality. Some jurisdictions prohibit buildings operating with non-functional detection devices as essential safety measure breach. Failed detectors should be replaced within 48 hours in critical areas, within one week in general areas. Never leave building with significant proportion of detectors non-functional without explicit building owner acknowledgment and acceptance of increased fire risk.

How should technicians protect hearing during fire alarm sounder testing and what are the long-term hearing risks?

Fire alarm sounders are specifically designed to produce high-intensity sound pressure levels typically 85-100dB(A) or higher, creating genuine hearing damage risk for testing technicians with regular exposure. Hearing protection is essential for all sounder testing work. Provide Class 4 or Class 5 hearing protection (earplugs or earmuffs) rated for minimum 25dB noise reduction. Train technicians in correct earplug insertion technique achieving proper seal - poorly inserted earplugs provide inadequate protection. Establish policy requiring hearing protection be donned before activating sounders for testing. Implement testing procedures minimising noise exposure duration - activate sounders for only 30-60 seconds required to verify operation rather than extended activations. Test sounders from fire alarm panel location rather than standing directly beneath sounders during activation. Conduct physical sounder inspection before testing then move to quieter location before activation. Implement rest breaks in quiet areas every 60 minutes during extended testing sessions allowing temporary threshold shift recovery. Rotate testing responsibilities among team members so no individual receives excessive cumulative exposure. Monitor technicians for hearing problems including tinnitus (ringing in ears), temporary hearing loss after work, or difficulty understanding speech in noisy environments - these symptoms indicate hearing damage is occurring. Provide annual audiometric hearing testing for technicians conducting regular fire alarm testing work. Long-term hearing damage from occupational noise exposure is permanent and irreversible, making prevention through hearing protection and exposure control critical for protecting technicians throughout their careers.

What electrical safety precautions are necessary when testing fire alarm systems that remain energised during testing?

Fire alarm testing presents electrical hazards because systems remain energised and operational throughout testing procedures. Implement multiple safety precautions to protect technicians. Ensure testing is performed only by competent persons with electrical safety training and understanding of fire alarm system operation. For work involving fire indicator panel internal access (required for some troubleshooting), require appropriate electrical qualifications or licensed supervision. Use insulated tools rated for electrical work including insulated screwdrivers, pliers, and voltage-rated multimeter leads. Wear appropriate PPE when accessing panel internals including insulated gloves rated Class 0 (1000V) and safety glasses. Establish procedures prohibiting unnecessary panel internal access - conduct all possible testing using external test points and visual panel displays. When panel access is essential, establish two-person working requiring spotter present. Verify voltages using non-contact voltage tester before any contact with electrical components. Be aware fire alarm systems contain backup battery systems capable of delivering high currents if short-circuited - treat battery terminals with same precautions as mains voltage. Avoid testing during wet conditions or when hands are wet as moisture increases electrical shock risk. Position testing equipment to prevent water or liquids contacting electrical components. Ensure adequate lighting when accessing panel locations - poor lighting increases risk of inadvertent contact with live parts. Immediately report any electrical faults, damaged insulation, exposed terminals, or electrical odours to building management as these represent serious hazards requiring urgent rectification. Never bypass electrical safety features or disable panel protection devices to conduct testing. Maintain electrical testing equipment in good condition with regular calibration and inspection for damage.

Related SWMS documents

Browse all documents

fire-services

Fire Alarm System Installation Safe Work Method Statement

Comprehensive SWMS covering preparation, cable installation, device mounting, control panel configuration, functional testing, and commissioning of automatic fire alarm systems in accordance with AS 1670 and WHS legislation.

View document

fire-services

Fire Door Installation Safe Work Method Statement

Comprehensive SWMS covering preparation, frame fixing, leaf hanging, hardware installation, fire sealing, and certification of fire-rated doorsets in accordance with NCC and AS 1905.1.

View document

fire-services

Fire Extinguisher Installation and Maintenance Safe Work Method Statement

Comprehensive SWMS detailing preparation, mounting, recharge, hydrostatic testing, compliance inspection, and documentation for portable fire extinguishers and hose reels in line with AS 2444 and AS 1851.

View document

fire-services

Fire Sprinkler System Installation Safe Work Method Statement

End-to-end SWMS for fire sprinkler system prefabrication, mounting, hydraulic testing, and commissioning aligned with AS 2118 and WHS legislative requirements.

View document

fire-services

Portable Hydrants, Hose Reels & Extinguishers Inspection Safe Work Method Statement

SWMS outlining routine service, flow testing, recharge, and documentation for portable hydrants, hose reels, and fire extinguishers under AS 1851.

View document

fire-services

Prescribed Burns Safe Work Method Statement

SWMS covering planning, ignition, control, and mop-up of prescribed burns and hazard reduction works in compliance with Australian fire management guidelines.

View document

Overview

Fire detection and alarm system testing comprises routine maintenance testing required under AS 1851 and commissioning testing of newly installed or modified systems following AS 1670 standards. Australian regulations classify fire alarm systems as essential safety measures requiring regular testing and maintenance to ensure continued functionality. Testing procedures verify that smoke detectors respond appropriately to smoke aerosol test spray, heat detectors activate at correct temperature thresholds, manual call points trigger immediate alarm response, alarm sounders and visual alerting devices operate at specified intensity, fire indicator panels display correct zone information, backup battery systems provide adequate standby power, and system integration functions including building management system interface and emergency systems activation operate correctly. Testing work involves accessing elevated detector locations using ladders or elevated work platforms, activating devices using specialized test equipment including smoke aerosol canisters, heat sources, and electrical test instruments, monitoring fire alarm panel responses, and documenting test results on standardized testing forms. Technicians test smoke detectors by applying smoke aerosol directly to detector chambers causing alarm activation, verify correct zone indication on fire panels, and confirm alarm sounders activate throughout the building. Heat detector testing involves applying controlled heat sources or using specialized heat detector test units. Manual call point testing requires breaking seal elements and activating switches to simulate emergency activation. System integration testing verifies that fire alarm activation triggers appropriate responses including elevator recall, air handling shutdown, electromagnetic door release, and emergency warning systems. The work requires coordination with building occupants, security monitoring companies, and potentially fire brigade communications centres to prevent inappropriate emergency response during routine testing. Technicians must manage energised electrical circuits during testing, work at heights to access ceiling-mounted detectors, use testing chemicals with safety requirements, and interpret complex system responses to identify faults requiring rectification. AS 1851 mandates testing frequencies ranging from monthly for critical systems to six-monthly for most commercial installations, with comprehensive annual testing including extended duration battery tests and full system functional verification. Testing must be documented with all device tests recorded, defects identified, and rectification work scheduled, providing building owners with evidence of compliance with essential safety measure requirements.

Why This SWMS Matters

Fire alarm testing is high-risk work under the Work Health and Safety Act 2011 combining electrical hazards from energised fire alarm systems, fall risks when accessing elevated detectors, chemical exposure from testing aerosols, and coordination challenges that can result in inappropriate emergency response if not properly managed. Without comprehensive risk controls documented in a SWMS, technicians face electrocution from live alarm circuits, falls from ladders during detector testing, respiratory irritation from testing chemicals, heat stress during testing work, and incidents arising from poor coordination including building evacuations, emergency service callouts, and conflicts with building operations. Fire alarm systems remain energised during testing creating genuine electrical hazards. Testing procedures activate alarm circuits, sounders, and panel electronics requiring technicians to work with live electrical equipment. Detector testing at ceiling height requires ladder work or elevated platform use presenting fall hazards. Testing aerosols contain chemicals causing eye and respiratory irritation if used in confined spaces without ventilation. Extended testing programs in large buildings can take hours, exposing technicians to cumulative chemical exposure and physical fatigue. Poor coordination can trigger building evacuations disrupting hundreds of occupants, generate false emergency service callouts wasting fire brigade resources, or create conflicts with critical building operations in hospitals, data centres, or industrial facilities. Beyond immediate safety, fire alarm testing quality directly impacts building life safety systems' reliability. Inadequate testing fails to identify system faults that could prevent proper fire alarm operation during actual emergencies, potentially resulting in loss of life. AS 1851 establishes specific testing procedures, frequencies, and documentation requirements ensuring systems remain functional throughout their service life. Testing must verify not just that devices operate, but that they respond at correct sensitivity thresholds, alarm throughout the building at adequate sound levels, and integrate correctly with other building systems. Comprehensive SWMS documentation ensures technicians follow Australian Standard testing procedures, use calibrated equipment, correctly interpret test results, and document findings appropriately. Australian building regulations require building owners to maintain fire alarm systems as essential safety measures with testing conducted by competent persons using appropriate procedures. Under the WHS Act, PCBUs must ensure testing work is planned and conducted safely with appropriate risk controls. This includes ensuring technicians are trained in testing procedures, building occupants are notified before testing, electrical safety procedures are followed, and appropriate personal protective equipment is provided. Failure to implement these controls can result in regulatory penalties, prohibition notices halting testing programs, and increased liability if system faults go undetected due to inadequate testing. The fire services industry has recorded incidents during testing work including technicians falling from ladders while testing ceiling detectors, electric shocks from fire alarm panels, respiratory problems from testing aerosol exposure in confined ceiling spaces, and noise-induced hearing damage from proximity to alarm sounders during activation testing. These incidents demonstrate genuine hazards requiring systematic management. A well-prepared SWMS addresses these risks through detailed hazard identification, control measure specification including electrical safety procedures, fall protection requirements, chemical handling protocols, and building coordination procedures. The document ensures testing quality whilst protecting technician safety and preventing disruption to building operations.

Trusted by 1,500+ Australian construction teams

Fire Detection-Alarms Testing SWMS Sample

Professional SWMS created in 5 seconds with OneClickSWMS

  • Instant PDF & shareable link
  • Auto-filled risk matrix
  • Editable Word download
  • State-specific compliance
  • Digital signature ready
  • Version history preserved
Manual creation2-3 hours
OneClickSWMS5 seconds
Save 99% of admin time and eliminate manual errors.

No credit card required • Instant access • Unlimited drafts included in every plan

PDF Sample

Risk Rating

BeforeHigh
After ControlsLow

Key Controls

  • • Pre-start briefing covering hazards
  • • PPE: hard hats, eye protection, gloves
  • • Emergency plan communicated to crew

Signature Ready

Capture digital signatures onsite and store revisions with automatic timestamps.

Continue exploring

Hand-picked SWMS resources

Ready to deliver professional SWMS in minutes?

OneClickSWMS powers thousands of compliant projects every week. Join them today.