Comprehensive SWMS for installing vertical plumbing services in multi-storey buildings

Risers Working In Safe Work Method Statement

2,000+ Australian Businesses Trust OneClickSWMS

No credit card required • Instant access • 100% compliant in every Australian state

5 sec
Creation Time
100%
Compliant
2,000+
Companies
$3.6K
Fines Avoided

Avoid WHS penalties up to $3.6M—issue compliant SWMS to every crew before work starts.

Riser installation involves installing vertical plumbing services through multiple floors of multi-storey buildings including water supply risers, drainage stacks, fire protection risers, and mechanical services. Work occurs in dedicated service shafts, riser cupboards, or external building faces requiring working at heights, confined space work in riser shafts, and coordination between multiple floor levels. This Safe Work Method Statement addresses the unique hazards of vertical services installation including fall risks through floor penetrations, working in vertical shafts with limited access, fire separation requirements, and precise vertical alignment of services over multiple floors.

Unlimited drafts • Built-in WHS compliance • Works across every Australian state

Overview

What this SWMS covers

Riser installation forms the backbone of multi-storey building plumbing systems, providing vertical distribution of water supply, drainage, fire protection, and mechanical services connecting basement plant rooms to upper floor levels and ultimately to rooftop equipment. These vertical service routes typically run through purpose-designed service shafts or riser cupboards strategically positioned in building cores, restroom areas, or external walls. In high-rise residential buildings, commercial offices, hotels, hospitals, and mixed-use developments, risers enable centralized services to reach all floors efficiently while concentrating service routes in defined zones facilitating maintenance access and minimizing interference with occupied spaces. Typical riser installations include cold water supply risers delivering potable water from ground-level water mains or basement storage tanks to all floors, hot water return and flow risers in buildings with centralized hot water systems, drainage stacks collecting wastewater from multiple floor levels and conveying to ground-level drainage systems, vent stacks providing drainage system ventilation preventing trap seal loss, fire hydrant and hose reel risers supplying fire-fighting water to all floors, sprinkler system risers distributing fire protection water to sprinkler zone piping, and mechanical services risers including heating water, chilled water, or gas services in buildings with central plant. These services may run in dedicated shafts containing only plumbing services, or in shared service shafts accommodating electrical risers, communications cabling, and HVAC services requiring careful coordination and clearance management. Riser shafts typically consist of vertical penetrations through floor slabs at each level with surrounding walls creating enclosed shaft space. Shaft dimensions vary from compact 600x600mm shafts in residential buildings serving single bathroom groups, through to large 2-3 metre shafts in commercial buildings accommodating multiple service risers, electrical switchboards, and access space. Access to riser shafts occurs through access doors at each floor level opening into riser cupboards, or in some designs through removable wall panels. Shaft design must incorporate fire separation between floors using fire collars on pipes penetrating floors, fire-rated shaft walls and doors maintaining building fire compartmentation, and smoke sealing preventing smoke spread through shafts during fires. Installation methodology varies with building height and riser configuration. For buildings under construction with floor slabs progressively poured, risers install floor-by-floor as building rises with pipe sections installed from each level threading through penetrations to level above and supported at each floor. For taller buildings or post-construction installations, sections may be prefabricated at ground level and crane-lifted into position through shaft, or in some cases pipes are fed from top level down through shaft with installers working at multiple levels simultaneously. Vertical alignment is critical - a 2mm deviation per floor accumulates to substantial misalignment over 20 floors requiring careful setting-out and verification. Support brackets install at each floor supporting pipe weight and accommodating thermal expansion through sliding supports or spring hangers. Work hazards include falls through floor penetrations created for riser installation typically 150-300mm diameter holes through which workers or materials can fall, confined space conditions in narrow riser shafts with limited natural ventilation and restricted entry/egress, working at heights when accessing riser shafts on upper floors or working from access platforms within shafts, manual handling of heavy pipe sections in confined vertical shafts with limited maneuvering space, dropped object risk with tools or pipe sections falling down vertical shafts potentially striking workers on lower levels, and fire separation compliance requiring proper installation of fire collars and penetration seals. Coordination between workers on different floors requires clear communication preventing incidents from simultaneous work at different levels of same shaft. This SWMS provides systematic controls for safely installing vertical services in multi-storey buildings addressing these specific riser installation hazards.

Fully editable, audit-ready, and aligned to Australian WHS standards.

Why this SWMS matters

Riser installation in multi-storey buildings creates compounded safety risks combining working at heights, confined spaces, and coordination across multiple floor levels. Falls through unprotected floor penetrations created for riser installation represent a critical hazard - these penetrations typically range 150-300mm diameter for single risers to 1 metre or larger for multiple service shafts, creating openings through which workers can fall to lower levels potentially dropping multiple floors if penetrations align vertically. Fatal falls have occurred when workers step into unprotected riser penetrations while walking backward pulling pipes or carrying materials with obstructed vision. Floor penetrations often remain open during extended construction periods serving as service routes requiring protection throughout this period not just during active riser work. Under WHS Regulations, floor openings and penetrations exceeding 200mm in any dimension must be protected by covers capable of supporting anticipated loads, or by guardrails if covers are not practicable. For riser penetrations used for passing pipes and materials, covers are typically removed during active work but must be replaced when work ceases and must be clearly marked "FLOOR OPENING" or "HOLE" when in place preventing inadvertent stepping onto covers assuming solid floor. Guardrails around larger penetrations must be minimum 900mm high with mid-rails and toe boards. Recent prosecutions have resulted from workers falling through unprotected riser penetrations with companies fined over $150,000 and individuals including supervisors receiving personal fines for failing to ensure floor openings were protected. Confined space hazards in riser shafts require careful assessment. Many riser shafts meet confined space definitions being enclosed spaces not designed for continuous human occupancy with restricted entry/egress through small access doors, limited natural ventilation creating potential for atmospheric hazards, and difficulty conducting emergency rescue if workers are injured within shafts. Vertical configuration of riser shafts creates particular rescue challenges - a worker who becomes unconscious in shaft cannot be easily retrieved without specialized rescue equipment and training. Atmospheric hazards in riser shafts can include oxygen depletion from displacement by heavier-than-air gases, buildup of welding fumes or solvent vapors from pipe jointing work, or carbon monoxide from combustion equipment operated in shafts. Some riser shaft designs include vertical ladder access requiring workers to climb multiple floors to access work areas, creating fall hazards and fatigue issues. Where riser shafts are classified as confined spaces, formal entry procedures are mandatory under WHS Regulations including atmospheric testing before entry measuring oxygen levels (must be 19.5-23%), flammable gases (below 5% LEL), and toxic gases, continuous atmospheric monitoring during work or periodic re-testing if continuous monitoring is not practicable, standby person positioned outside shaft maintaining contact with workers inside and capable of initiating rescue, and rescue procedures and equipment appropriate to shaft configuration. For vertical shafts, rescue may require harnesses with retrieval lines allowing vertical extraction, or alternative access routes allowing rescue team entry. Confined space entry permits document these controls and verification of atmospheric testing results before workers enter shafts. Fire separation integrity in multi-storey buildings depends heavily on proper installation of fire penetration seals around riser pipes passing through floors and fire-rated walls. Building Code of Australia requires fire-rated penetration seals maintaining fire resistance level of the floor or wall penetrated - typically 60 to 120 minute fire resistance level for multi-storey construction. Improper sealing allows fire and smoke spread between floors potentially allowing ground floor fires to spread throughout building via riser shafts creating untenable conditions in upper levels and compromising evacuation. Fire safety engineering assessments and post-construction fire safety certification rely on penetration seals being installed correctly. Building surveyors conduct inspections before sealing occurs verifying services are correctly positioned, then after sealing verifying approved products are used and installed per manufacturer specifications. Failure to install compliant fire seals can result in building occupancy delays pending rectification, orders to expose and reinspect sealed penetrations at contractor expense if compliance cannot be verified, and in serious cases requirement to remove non-compliant services and reinstall properly. Fire seal manufacturers provide detailed installation instructions and approved installer programs - use of unapproved installers or incorrect installation voids product certifications. Recent building fire incidents have highlighted consequences of poor fire seal installation with fire spreading through unsealed service penetrations contributing to rapid fire spread and casualties. Regulatory focus on combustible cladding and fire safety has increased scrutiny of all fire safety systems including penetration seals. Coordination between workers on different floor levels during riser installation requires robust communication systems. Workers on different floors cannot see each other creating risk of simultaneous activities causing injuries - for example, worker on upper floor feeding pipe down shaft while worker below is positioning at penetration creates crush risk if upper worker releases pipe unexpectedly. Dropped tools from upper levels strike workers below. Lifting pipe sections from lower levels requires coordination ensuring upper level workers are clear of lifting zone. Two-way radio communication between floor levels is essential providing real-time coordination, but procedures must account for radio failures or misunderstood communications. Visual confirmation where possible using cameras or direct line-of-sight through shaft provides additional safety layer. Documented lifting procedures with clear signals and acknowledgments prevent simultaneous conflicting actions. This systematic coordination prevents struck-by incidents and crushing injuries that have occurred on riser installation projects where coordination was informal or inadequate.

Reinforce licensing, insurance, and regulator expectations for Risers Working In Safe Work Method Statement crews before they mobilise.

Hazard identification

Surface the critical risks tied to this work scope and communicate them to every worker.

Risk register

Falls Through Unprotected Floor Penetrations for Risers

High

Riser installation requires penetrations through floor slabs at each level creating fall hazards. Penetrations typically range 150-300mm diameter for single service risers to over 1 metre for large service shafts. These openings extend through full floor slab thickness (typically 150-300mm) creating fall paths to floor below or through multiple aligned penetrations potentially allowing falls through several floors. Penetrations remain open during pipe installation work allowing pipes to pass between levels. Workers moving backward while pulling pipes, carrying materials with obstructed vision, or working in poor lighting may not see penetrations. Temporary penetration covers may be displaced by pipe passing or removed for work access. Multiple penetrations in riser cupboards create complex fall hazard with limited safe walking areas. Congestion in riser areas during simultaneous work by multiple trades increases inadvertent approach to penetrations. Night work or work in unlit areas reduces visibility of penetrations.

Confined Space Hazards in Riser Shafts

High

Riser shafts are enclosed vertical spaces often meeting confined space definition with restricted entry through small access doors typically 600-900mm wide, limited natural ventilation particularly in internal building core shafts, restricted egress requiring backing out through access doors or climbing vertical ladders, and difficulty conducting emergency rescue in vertical shaft configuration. Atmospheric hazards can develop including oxygen depletion from displacement by heavier-than-air gases or consumption by oxidation processes, accumulation of welding fumes or solvent vapors from pipe jointing work sinking to shaft bottom in stagnant air, or carbon monoxide from any combustion equipment operated in shaft. Temperature extremes develop with excessive heat in summer from solar gain on external shafts or inadequate ventilation, hypothermia risk in winter in unheated shafts. Psychological stress from claustrophobic conditions affects some workers. Vertical ladder access creates additional fall risk and physical demands climbing multiple floors. Emergency rescue is complicated by vertical shaft configuration and restricted access.

Working at Heights Accessing Riser Shafts and Platforms

High

Riser work in multi-storey buildings occurs at elevated positions accessed via building stairs, temporary construction hoists, or ladders within riser shafts. Working within shafts may require step ladders or temporary platforms providing access to pipe support brackets at ceiling level. External risers on building facades involve working from scaffolding or abseil access at significant heights. Accessing riser cupboards on upper floors requires safe access to those levels. Pipe lifting operations position workers at edge of floor openings managing cranes or manual hauling systems. Working on platforms within shafts provides limited working space affecting stability. Tools and materials stored in confined shaft spaces create trip hazards. Poor lighting in shafts reduces visibility of fall hazards.

Manual Handling of Heavy Pipes in Vertical Shafts

High

Riser installation requires manual handling of substantial pipe sections in confined vertical shaft spaces with limited maneuvering room. Steel fire service risers commonly 100-150mm diameter weigh 30-50kg per 3-metre section requiring team lifting in spaces often less than 1 metre wide. Copper water supply risers while lighter still require awkward positioning threading through floor penetrations. Vertical orientation requires lifting pipes overhead to position through upper floor penetrations or lowering through penetrations to lower floors. Confined shaft dimensions prevent proper lifting posture forcing twisted spine positions and bent postures. Shaft access through small doors requires maneuvering pipes through doorways at awkward angles. Vertical ladder access means pipes must be hauled up shafts using rope systems or carried while climbing ladders. Installation of pipe support brackets requires overhead reaching in confined spaces. Repetitive lifting during progressive floor-by-floor installation creates cumulative strain.

Dropped Objects Down Vertical Shafts

High

Vertical riser shafts create extreme dropped object hazard with tools, pipe fittings, or equipment dropped from upper floors falling down shaft potentially striking workers on lower levels. Free-fall acceleration means items falling from upper floors of multi-storey buildings strike with extreme force. Pipe wrenches, cutting tools, fittings, and fasteners used during riser installation can be inadvertently dropped. Passing tools between workers at different levels creates transfer point dropping risk. Working on platforms or ladders within shafts positions workers at different vertical levels with workers below at risk from anything dropped by workers above. Aligned floor penetrations create vertical shaft effect allowing objects to fall multiple floors. Temporary materials storage on platforms within shafts can be displaced. Lack of visual contact between workers at different levels means workers below may not be aware of overhead work creating dropping risk.

Fire Separation Compliance and Penetration Sealing

Medium

Maintaining fire separation integrity in multi-storey buildings requires proper installation of fire-rated penetration seals around all pipes passing through fire-rated floors and walls. Failure to install compliant seals compromises building fire safety allowing fire and smoke spread between floors via riser shafts. Sealing products must be compatible with pipe materials (different products for steel, copper, PVC pipes), installed per manufacturer specifications including correct annular gap dimensions and seal thickness, and certified for required fire resistance level matching floor or wall rating. Installation timing is critical - seals install after pipe positioning is finalized but before builders seal shaft walls preventing future access. Incorrect seal installation including incomplete filling of annular gaps, use of incorrect products, or installation by non-approved installers voids product certifications. Building certifier inspections verify seal compliance before concealment.

Control measures

Deploy layered controls aligned to the hierarchy of hazard management.

Implementation guide

Floor Penetration Protection and Marking

Engineering

Protecting all floor penetrations with covers or guardrails prevents fall-through incidents. This engineering control creates physical barrier preventing workers falling through riser penetrations whether work is active or shafts are temporarily unattended. Proper marking and securing of covers ensures protection remains effective throughout construction period.

Implementation

1. Install penetration covers over all riser openings when not actively in use for pipe passing, using covers capable of supporting minimum 200kg point load (equivalent to worker plus tools) 2. Fabricate covers from substantial material including minimum 12mm plywood or steel plate with cleats preventing displacement, sized to overlap penetration by minimum 150mm all sides 3. Mark all penetration covers clearly with high-visibility paint and text "FLOOR OPENING" or "HOLE" preventing workers assuming cover is solid floor and stepping onto covered openings 4. Secure covers preventing unauthorized removal using bolts, clips, or weighted placement ensuring covers cannot be accidentally displaced 5. For large service shaft openings where covers are impractical due to size or frequent access requirements, install temporary guardrails minimum 900mm high with mid-rails and toe boards around full perimeter of penetration 6. Implement cover replacement protocol requiring covers to be replaced immediately when pipe passing work ceases, with daily inspection verifying all penetrations are protected overnight 7. Paint high-visibility marking (typically yellow and black diagonal stripes) around floor area adjacent to penetrations providing additional visual warning of hazard location 8. Establish exclusion zones around large unprotected penetrations during active pipe passing operations using temporary barriers preventing inadvertent approach by workers not directly involved in riser work 9. Provide adequate lighting in riser cupboard areas ensuring penetrations are clearly visible in all working conditions including emergency lighting for power failure situations 10. Brief all workers accessing riser areas on penetration locations and protection requirements prohibiting removal of covers except when necessary for pipe passing work

Confined Space Assessment and Entry Procedures for Shafts

Administrative

Conducting formal confined space assessment of riser shafts and implementing entry procedures where classification applies ensures atmospheric hazards and emergency rescue arrangements are addressed. This administrative control establishes verification that shafts are safe to enter and rescue arrangements are adequate before workers access shaft spaces.

Implementation

1. Assess each riser shaft against confined space criteria considering enclosure level, entry/exit restrictions through small access doors, potential for atmospheric hazards, and emergency rescue difficulty in vertical shaft configuration 2. For shafts meeting confined space definition, implement formal confined space entry procedures including written confined space entry plan, atmospheric testing before each entry measuring oxygen levels (19.5-23%), flammable gases (below 5% LEL), and toxic gases including carbon monoxide and solvent vapors, continuous atmospheric monitoring using fixed monitors or periodic re-testing every 2 hours during work 3. Install continuous forced ventilation in confined space shafts using portable fans with flexible ducting extending into shaft creating air exchange, positioning fan at shaft base drawing fresh air down from top or at top extracting contaminated air depending on contamination type 4. Establish standby person system with trained standby positioned outside shaft access door maintaining constant communication with workers in shaft using two-way radios or voice contact, with standby person briefed on emergency procedures and prohibited from entering shaft to attempt rescue without proper rescue equipment and backup 5. Develop shaft-specific rescue procedures accounting for vertical configuration potentially requiring harnesses with vertical retrieval systems, alternative access points allowing rescue team entry, or fire brigade notification for specialized rescue capability 6. Provide rescue equipment appropriate to shaft configuration including tripods with mechanical lifting systems for vertical extraction if shaft allows positioning over access point, full-body harnesses with retrieval lines for workers in vertical shafts, and emergency breathing apparatus if atmospheric contamination risk exists 7. Implement confined space entry permits for each entry period documenting atmospheric test results, workers entered, standby person details, and completion sign-off before workers exit 8. Brief all workers on confined space hazards specific to riser shafts including atmospheric hazards from welding fumes or solvent vapors sinking to bottom of vertical shafts, emergency signals and evacuation procedures, and prohibition of solo shaft entry 9. Prohibit use of combustion equipment including petrol-powered tools within confined space shafts due to carbon monoxide generation 10. Establish maximum work duration limits for confined space shaft work with scheduled breaks requiring workers to exit shaft for rest and recovery

Mechanical Pipe Lifting Systems for Vertical Installation

Engineering

Using mechanical lifting systems for moving pipes vertically through riser shafts eliminates sustained manual lifting and reduces manual handling injuries. This engineering control includes crane lifting for external risers, rope and pulley systems within shafts, and specialized riser installation equipment providing mechanical advantage for vertical pipe movement.

Implementation

1. For external building risers accessible to cranes, use crane lifting to position prefabricated riser sections up to full building height where practical, securing sections at each floor as installation progresses vertically 2. Install temporary rope and pulley systems within riser shafts allowing controlled raising or lowering of pipe sections, using mechanical advantage to reduce manual force required for vertical movement 3. Use portable winches or lifting hoists positioned at upper floors capable of hauling pipe sections vertically through shaft with workers guiding pipes without supporting full weight 4. Pre-fabricate pipe assemblies at ground level or at convenient floor levels including multiple joints in each assembly, lifting completed assemblies reducing number of individual lifts and amount of work in confined shafts 5. Implement team lifting protocols for pipe sections requiring manual lifting within shafts ensuring minimum two workers for any pipe exceeding 15kg, with workers positioned to maintain balanced load 6. Use pipe support cradles or slings that distribute pipe weight evenly during lifting preventing point loading on workers' hands and backs 7. Position temporary platforms or supports within shafts at intermediate heights allowing pipes to be rested during multi-floor lifts providing recovery periods for workers 8. Establish communication protocols between workers at different floor levels during lifting operations using two-way radios with standard signals for start lifting, stop, hold position ensuring coordinated lifting without simultaneous conflicting actions 9. Brief workers on proper lifting technique adapted to confined shaft work including maintaining straight back despite space constraints, using legs for lifting force, and avoiding twisted spine positions 10. Monitor workers for fatigue during repetitive lifting operations implementing task rotation and scheduled breaks reducing cumulative strain

Dropped Object Prevention in Vertical Shafts

Engineering/Administrative

Implementing systematic dropped object prevention prevents tools and materials falling down vertical riser shafts potentially striking workers on lower levels. This control combines physical barriers with work procedures establishing multi-level protection against dropped object incidents.

Implementation

1. Install temporary horizontal barriers (safety mesh or solid sheeting) at regular vertical intervals within riser shafts creating intermediate protection levels preventing objects falling more than one or two floors even if dropped from upper levels 2. Implement tool lanyard requirements for all hand tools used within riser shafts with lanyards attached to worker belts or secured to structure preventing tools falling if dropped from hands 3. Use tool buckets or bags with secure closures for transporting tools vertically through shafts keeping tools contained during movement between floors 4. Establish exclusion protocols prohibiting workers from being positioned directly below other workers in vertical shafts, requiring staggered positioning so workers at different levels are offset horizontally within shaft space 5. Implement material passing procedures for transferring items between floor levels requiring verbal communication and acknowledgment before items are released, with receiving worker confirming ready to receive and positioned to accept transfer 6. Install shaft bottom protection using solid boarding or mesh covering shaft base preventing access to space directly below active work areas 7. Provide adequate storage for tools and materials within shafts using secured shelving or containers with raised edges preventing materials rolling or being knocked off storage surfaces 8. Brief workers on immediate area clearing protocols if items are dropped requiring loud verbal warning "BELOW" or similar and verification that dropped items have not struck workers before resuming work 9. Establish regular housekeeping procedures removing waste materials, off-cuts, and debris from shaft work areas that could be inadvertently displaced and fall 10. Use visual communication systems where possible installing cameras or mirrors allowing workers at different levels to verify positioning before commencing activities that create dropped object risk

Fire Penetration Seal Installation Compliance

Administrative

Ensuring fire penetration seals are installed by approved installers using certified products complying with building fire safety requirements maintains fire separation integrity. This administrative control establishes verification procedures confirming seal compliance and documentation for building certification.

Implementation

1. Engage fire seal installers holding manufacturer approval for specified penetration seal products ensuring installer competency and product warranty compliance 2. Use fire penetration seal products with current CodeMark certification or other approved certification demonstrating compliance with Building Code fire resistance requirements for floor or wall being penetrated 3. Verify seal product selection is appropriate for pipe material and diameter - manufacturers specify different products for steel, copper, PVC, or composite pipes and different products for different pipe diameter ranges 4. Install seals per manufacturer specifications including correct annular gap between pipe and penetration (typically 10-25mm depending on product), seal thickness achieving required fire resistance level, and installation technique such as packing density for intumescent materials 5. Coordinate installation timing with building construction ensuring seals install after final pipe positioning but before shaft walls are closed allowing building certifier inspection before concealment 6. Document each penetration seal installation with photographs showing seal before, during, and after installation, product identification labels, installer details, and date of installation 7. Provide seal installation documentation to building certifier including penetration schedule listing each penetration location, pipe type and diameter, seal product used, and confirmation of compliant installation 8. Arrange building certifier inspection of penetration seals at holding point before concealment allowing verification of compliant installation and correction of any deficiencies before sealing 9. Maintain seal manufacturer warranties requiring use of approved installers and installation per specifications, with warranty documentation provided to building owner 10. Brief plumbing workers on importance of fire seal integrity and prohibition of penetrating fire seals after installation for additional pipes or modifications requiring new seals using approved products and installers

Multi-Level Work Coordination and Communication

Administrative

Implementing robust communication and coordination procedures between workers on different floor levels prevents struck-by incidents and crushing injuries from simultaneous uncoordinated work. This administrative control establishes clear protocols for communication, work sequencing, and verification before activities affecting other floor levels.

Implementation

1. Provide two-way radio communication equipment to all workers involved in riser installation with dedicated radio channel for riser work team preventing interference from other site communications 2. Establish standard communication protocols using clear verbal signals and acknowledgments before any vertical material movement including "Ready to lift" requiring "Ready" acknowledgment from all levels before lifting commences, "Lifting now" as lift begins, "Stop" for immediate cessation of movement, and "Set down" when item is in position 3. Implement work zone designation within vertical shafts preventing workers being positioned directly below active work areas, with workers at lower levels offset horizontally from upper level work or excluded from shaft during overhead work 4. Use visual confirmation systems where practical including shaft cameras, lights signaling ready status, or direct line-of-sight through shaft openings allowing workers to verify other workers' positions before commencing activities 5. Develop job-specific work procedures for complex riser installation tasks documenting step-by-step sequence, communication requirements at each step, and designated positions for workers at different levels ensuring consistent safe work approach 6. Conduct pre-start meetings each day involving all workers participating in riser installation reviewing day's work plan, communication protocols, potential hazards, and emergency procedures 7. Establish backup communication methods for radio failure situations using agreed whistle signals or physical signals visible between levels, with procedure to cease work if communication capability is lost until restored 8. Implement verification protocols requiring receiving worker to visually verify item secured or positioned correctly and communicate completion before sending worker releases or commences next activity 9. Brief workers on prohibition of solo work in multi-level riser installations requiring minimum two workers to maintain communication and respond to emergencies 10. Document near-miss incidents where communication failures nearly resulted in incidents conducting lessons-learned analysis and implementing corrective actions improving communication protocols

Personal protective equipment

Requirement: Safety helmet to AS/NZS 1801 Type 1 with secure chin strap

When: Mandatory during all riser installation work protecting from dropped objects falling down vertical shafts, striking head on shaft structures in confined spaces, and head protection during falls. Chin strap prevents helmet displacement in confined shaft work.

Requirement: Full-body harness to AS/NZS 1891.1 with dorsal D-ring for vertical fall arrest

When: Required when working on upper floors accessing riser shafts if edge protection is not provided, when working from platforms or ladders within shafts at heights exceeding 2 metres, or when working from external scaffolding on building facade risers. Must be connected to certified anchor points via energy-absorbing lanyards.

Requirement: Lace-up boots with steel toe caps, ankle support, slip-resistant soles

When: Required continuously during riser installation providing protection from crush injuries from dropped pipes and fittings, ankle support for stability on ladders and platforms in shafts, penetration protection from fasteners and sharp edges.

Requirement: Impact-resistant safety glasses to AS/NZS 1337.1 with side shields

When: Mandatory during all work in riser shafts protecting from debris falling from upper levels, metal filings from drilling and cutting operations, and impacts from pipe handling. Side shields provide peripheral protection in confined shaft spaces.

Requirement: Heavy-duty work gloves with grip enhancement and abrasion resistance

When: Required during all pipe handling providing protection from sharp edges on cut pipes, improved grip for pipe manipulation in confined spaces, and protection from pinch points when maneuvering pipes through penetrations.

Requirement: Class 4-5 earplugs or earmuffs to AS/NZS 1270

When: Required during power tool operation including grinders, drills, and reciprocating saws, particularly in enclosed riser shafts where sound reflects and intensifies. Threading machines and impact tools also generate hazardous noise levels.

Requirement: P2 particulate respirator to AS/NZS 1716 for dust, supplied air for welding in shafts

When: Required when cutting pipes generating metal dust, during welding or brazing in confined riser shafts, or when working in dusty shaft environments. Higher protection required for extended welding in confined vertical shafts with limited ventilation.

Inspections & checks

Before work starts

  • Verify all workers hold current Construction Induction White Cards and appropriate plumbing qualifications
  • Confirm floor penetrations for risers have been created per specifications with proper fire-rated penetration dimensions
  • Check all floor penetrations are protected with secure covers or guardrails when not in active use
  • Conduct confined space assessment of riser shafts determining if formal entry procedures required
  • If confined space classification applies, verify atmospheric testing equipment available, calibrated, and functional
  • Confirm ventilation equipment for shafts is operational including portable fans and ducting
  • Check communication equipment including two-way radios are functional and batteries charged
  • Verify mechanical lifting equipment including pulleys, ropes, and winches are in good condition and load rated
  • Confirm first aid equipment is accessible and first aid trained personnel are on site
  • Check emergency contact numbers are displayed and emergency procedures understood
  • Verify access to all floor levels is safe with construction stairs or hoists operational
  • Confirm fire penetration seal products and approved installers are arranged and available

During work

  • Monitor all floor penetrations remain protected when not in active use with covers replaced immediately after pipe passing
  • If confined space procedures apply, verify atmospheric testing is conducted before shaft entry and monitoring continues during work
  • Check ventilation equipment in shafts continues operating effectively throughout work periods
  • Monitor workers are using proper communication protocols before any vertical material movement
  • Verify no workers are positioned directly below other workers in vertical shaft spaces
  • Check tool lanyards are being used for all hand tools preventing dropped object hazards
  • Monitor manual handling practices ensuring mechanical aids and team lifting are used for heavy pipes
  • Verify workers maintain stable footing on ladders or platforms within shafts without overreaching
  • Check adequate lighting is maintained in shaft spaces as work progresses
  • Monitor workers for signs of heat stress or claustrophobia in confined shaft spaces
  • Verify housekeeping in shafts with debris and off-cuts removed preventing trip and dropped object hazards
  • Check standby person remains in position during confined space shaft entry if formal procedures apply

After work

  • Verify all workers have exited riser shafts accounting for all personnel who entered during shift
  • Confirm all floor penetrations are protected with covers or guardrails for overnight security
  • Check tools and equipment are removed from shafts or secured preventing dropped object hazards after hours
  • If confined space work occurred, complete entry permit documentation with atmospheric test results and sign-off
  • Document fire penetration seals installed during shift with photographs and product details
  • Verify riser cupboard access doors are closed and secured preventing unauthorized access
  • Record any near-miss incidents or hazards identified during shift for continuous improvement
  • Report any injuries immediately with incident documentation and medical assessment
  • Clean work areas in riser cupboards removing waste materials to designated bins
  • Brief following shift workers on installation progress, remaining hazards, and shaft access status

Step-by-step work procedure

Give supervisors and crews a clear, auditable sequence for the task.

Field ready
1

Riser Shaft Assessment and Preparation

Commence riser installation with assessment of shaft configuration, access arrangements, and hazard identification. Review architectural drawings identifying riser shaft locations, dimensions, floor penetration sizes, and access door positions at each floor level. Verify floor penetrations have been created during concrete pour or core-drilled post-construction matching riser pipe diameters with adequate clearance (typically 50-75mm annular gap for fire seal installation). Assess shaft dimensions determining whether confined space classification applies considering enclosure level, entry/exit restrictions through access doors typically 600-900mm wide, natural ventilation availability, and emergency rescue difficulty. For confined space shafts, develop confined space entry plan including atmospheric testing requirements, ventilation provisions, standby person arrangements, and rescue procedures specific to vertical shaft configuration. Check access to floor levels verifying stairs or construction hoists provide safe access for workers and materials. Identify electrical and lighting availability in shaft spaces installing temporary lighting if permanent lighting not yet commissioned. Verify adequate working space within shaft allowing pipe installation without excessive awkward positions. Plan pipe support bracket locations at each floor level ensuring structural fixings align with appropriate substrate (concrete slab, structural steel beams). Coordinate with other trades identifying any shared service shafts requiring coordination with electrical or HVAC installations. Document shaft assessment with photographs showing shaft configuration, access arrangements, and floor penetrations.

Safety considerations

Confined space assessment before work commences ensures appropriate controls are established if shafts meet confined space criteria. Verification of penetration sizes ensures pipes will fit through penetrations without forcing or enlargement that could compromise structural integrity. Access assessment ensures safe routes for workers and materials preventing improvised unsafe access. Lighting assessment ensures adequate visibility preventing trips and falls in shaft spaces.

2

Floor Penetration Protection Installation

Install protection for all floor penetrations preventing fall-through incidents before commencing riser installation work. Fabricate penetration covers for each opening using substantial material - minimum 12mm plywood or steel plate sized to overlap penetration by minimum 150mm all sides providing bearing on solid floor. Construct covers with cleats or framing preventing warping and providing rigidity. Paint covers with high-visibility colors (typically yellow and black diagonal stripes) with large text "FLOOR OPENING" or "HOLE" clearly marked. Install covers over all penetrations securing against displacement using bolts, clips, or weighted placement. For large service shaft openings where covers are impractical, install temporary guardrails around full perimeter using scaffolding components or purpose-built guardrails minimum 900mm high with mid-rails and toe boards. Paint floor area around penetrations with high-visibility marking providing additional visual warning of hazard location. Implement cover management system designating responsibility for cover replacement after pipe passing work with daily inspection verifying all penetrations are protected overnight and when work is not active. Brief all workers who will access riser areas on penetration locations and protection requirements prohibiting cover removal except when necessary for specific pipe passing activities. Document penetration protection with photographs showing covered penetrations and installed guardrails. Provide adequate lighting in all riser cupboard areas ensuring penetrations and covers are clearly visible.

Safety considerations

Physical barriers preventing access to penetrations eliminate primary fall hazard. Secure covers prevent inadvertent displacement that could expose openings unexpectedly. High-visibility marking ensures workers see protected penetrations rather than assuming all floor areas are solid. Systematic cover replacement procedures ensure protection is maintained throughout construction period not just during active riser work.

3

Vertical Alignment and Support Bracket Installation

Establish vertical alignment for risers ensuring pipes install truly vertical over multiple floors without cumulative deviation. Use laser level or plumb bob to establish vertical reference line through shaft from base to top floor. Mark pipe centerline at each floor level on floor slab adjacent to penetration providing reference for pipe positioning. Install pipe support brackets at each floor level before pipe installation creating support infrastructure. Support bracket type depends on pipe material and configuration - typically clevis hangers for steel pipes with U-bolts securing pipe in hanger, pipe clamps with support rods extending to structural ceiling for copper pipes, or trapeze hangers supporting multiple parallel pipes in congested shafts. Fix brackets to structural elements using appropriate anchoring - expansion anchors drilled into concrete slabs, beam clamps on structural steel, or through-bolting where access permits from both sides. Position brackets to align with vertical reference line ensuring pipes will install vertically. For multi-pipe risers, maintain adequate spacing between pipes typically minimum 50mm clear between pipes and greater spacing where thermal insulation will be applied. Install brackets at correct heights accounting for thermal expansion - fixed brackets at mid-height of riser with sliding or spring hangers at intervals above and below allowing thermal movement without stressing pipes. For fire service risers subject to high loads when charged with water, install reinforced brackets with higher load ratings. Verify bracket installation is secure capable of supporting full pipe weight when filled with water plus dynamic loads from water hammer effects.

Safety considerations

Vertical alignment before pipe installation prevents cumulative deviation eliminating rework from misaligned risers. Pre-installation of brackets provides secure support preventing temporary propping of heavy pipes during installation. Proper anchoring ensures brackets support pipe loads without failure. Working from stable platforms or step ladders during bracket installation prevents falls. Overhead drilling requires eye protection and stable working positions.

4

Pipe Section Installation with Mechanical Assistance

Install riser pipe sections working floor-by-floor with mechanical lifting assistance reducing manual handling strain. For bottom-up installation starting at lowest level, position first pipe section threading through floor penetration to next level above with approximately half pipe length protruding through penetration. From upper level, workers guide protruding pipe section securing in support bracket. Install joining coupling or weld joint connecting next pipe section to installed section. Remove penetration cover at next level threading pipe through to level above. Continue progressive installation working up building with pipe sections installed sequentially at each floor. For top-down installation in some configurations, position first pipe section at top floor feeding down through penetrations to lower levels with workers at lower levels guiding pipe into brackets. Use mechanical lifting aids including temporary rope and pulley systems allowing controlled raising or lowering of pipe sections, portable winches positioned at strategic floors capable of hauling pipes vertically, or crane lifting for external risers accessible from building exterior. Implement team communication protocols using two-way radios with workers at each level communicating before any pipe movement - standard signals include "Ready to lift," "Lifting now," "Stop," and "Set down." Ensure receiving worker at destination level confirms ready to receive and is positioned safely before lifting worker releases pipe section. For heavy steel fire service risers, use minimum two workers per level for pipe handling. Pre-fabricate pipe assemblies where practical joining multiple pipe lengths at ground level lifting completed multi-floor assemblies reducing individual lifts and work in confined shafts. Join pipe sections using methods appropriate to material - threading and couplings for steel pipes, brazing or mechanical couplings for copper pipes. Test each joint section before proceeding.

Safety considerations

Mechanical lifting systems reduce manual forces required for vertical pipe movement preventing musculoskeletal injuries. Team communication prevents simultaneous uncoordinated actions that could cause crushing injuries. Pre-fabrication reduces work in confined shafts and number of individual lifts. Systematic work progression reduces complexity preventing errors. Sequential testing identifies joint failures before entire riser is complete.

5

Fire Penetration Seal Installation and Testing

Install fire penetration seals around all pipes passing through fire-rated floors and walls maintaining building fire separation integrity. Coordinate seal installation timing with building construction ensuring seals install after pipes are in final position but before shaft walls are closed allowing building certifier inspection. Engage fire seal installers holding manufacturer approval for specified seal products. Verify seal product selection is appropriate for pipe material (steel, copper, PVC) and diameter with current CodeMark or equivalent certification. Clean penetration annular gap removing construction debris, dust, and oil ensuring seal materials bond to substrate. Install seals per manufacturer specifications packing intumescent materials to specified density, achieving specified thickness, and filling entire annular gap without voids. For multi-pipe penetrations, install individual seals around each pipe. Install identification tags on seals documenting seal product, date of installation, and installer details. Photograph each seal after installation providing documentation for building certifier. Conduct visual inspection of installed seals verifying complete gap filling and proper installation technique. Arrange building certifier holding point inspection of seals before shaft walls close allowing verification of compliant installation. Document any deficiencies identified by certifier and rectify using approved installers and products. Provide seal installation documentation to building certifier including penetration schedule listing each seal location, pipe details, seal product used, and certification of compliant installation. Brief workers on prohibition of penetrating fire seals after installation - any future service additions require new seals installed by approved installers. Pressure test riser after seal installation verifying seals do not leak and pipe system integrity is maintained.

Safety considerations

Fire seal integrity is critical building fire safety requirement preventing fire and smoke spread between floors. Use of approved installers and certified products ensures compliance. Building certifier inspection before concealment verifies compliance preventing later requirement to expose seals for inspection. Documentation provides building certification records and demonstrates compliance. Prohibition of seal penetration after installation maintains integrity.

Frequently asked questions

When do riser shafts require confined space entry procedures versus being treated as normal work areas?

Confined space classification for riser shafts depends on specific characteristics assessed against confined space definition in WHS Regulations. A confined space is an enclosed or partially enclosed space not designed or intended primarily for human occupancy, where there is risk of one or more of: harmful airborne contaminants, oxygen deficiency or enrichment, flammable atmosphere, or engulfment. Additionally, confined spaces typically have restricted entry and exit, and present difficulty for emergency rescue. Many riser shafts meet these criteria requiring formal confined space procedures, while some larger shafts with good access and ventilation may not require confined space classification. Indicators suggesting confined space classification include shaft access through small doors typically 600-900mm wide creating restricted entry/egress, vertical shaft configuration with limited natural ventilation particularly in internal building core locations, potential for atmospheric hazards from welding fumes, solvent vapors from pipe jointing work, or oxygen displacement by heavier-than-air gases, shaft dimensions less than 2 metres wide and of substantial vertical height creating enclosed feeling, and difficulty conducting emergency rescue particularly in vertical shafts requiring specialized retrieval equipment. Where any doubt exists, treat shaft as confined space implementing formal entry procedures rather than assuming it is safe. For shafts classified as confined spaces, implement comprehensive entry procedures including written confined space entry plan specific to shaft configuration, atmospheric testing before each entry measuring oxygen (19.5-23%), combustible gases (below 5% LEL), and toxic gases including carbon monoxide from any combustion equipment and volatile organic compounds from solvent-based joining materials, continuous forced ventilation using portable fans with ducting creating air exchange throughout shaft, continuous atmospheric monitoring using fixed gas monitors or periodic re-testing minimum every 2 hours during extended work, standby person stationed outside shaft access maintaining constant contact with workers inside via two-way radio or voice communication, written entry permit system documenting atmospheric test results, workers entered, standby person details, and completion sign-off, and emergency rescue procedures and equipment appropriate to vertical shaft configuration potentially including tripods with mechanical retrieval systems, full-body harnesses with vertical retrieval lines, or fire brigade notification for specialized confined space rescue capability. Brief all workers on confined space hazards, entry procedures, emergency signals, and prohibition of solo entry. Never enter shaft to attempt rescue without proper equipment and backup as secondary casualties commonly occur in confined space rescue attempts. For larger riser rooms or service areas with good access doors, adequate natural or mechanical ventilation, and no specific atmospheric hazards, confined space classification may not apply but general height safety and other hazard controls still apply. Document confined space assessment rationale whether classifying as confined space or determining it does not meet criteria, as this demonstrates due diligence in hazard assessment.

What are the specific requirements for protecting floor penetrations created for riser installation?

Floor penetrations for risers create serious fall hazards requiring protection under WHS Regulations which specify that floor openings exceeding 200mm in any dimension must be protected by covers capable of supporting anticipated loads, or by guardrails where covers are not practicable. For riser installations, protection requirements depend on penetration size and use frequency. For individual pipe penetrations typically 150-300mm diameter, fabricated covers provide most practical protection using minimum 12mm plywood or steel plate sized to overlap penetration minimum 150mm all sides providing adequate bearing on solid floor around opening. Covers must be capable of supporting minimum 200kg point load accounting for possibility of workers stepping onto covered opening unaware it is not solid floor. Install cleats or framing under cover preventing warping and ensuring rigidity. Mark covers prominently with high-visibility paint (typically yellow and black diagonal stripes) and large text "FLOOR OPENING" or "HOLE" clearly visible ensuring workers recognize covered opening rather than assuming solid floor. Secure covers preventing displacement using bolts through pre-drilled holes into floor, weighted placement using concrete blocks or steel sections on cover surface, or clips engaging floor or penetration edge. Covers must be in place whenever penetration is not in active use - for riser work requiring frequent pipe passing through penetrations, covers remove during active work but must be replaced immediately when work ceases including lunch breaks, shift end, and any period when workers are not actively using penetration. Daily site inspections must verify all penetrations are protected overnight. For large service shaft openings exceeding 1 metre in any dimension where covers are impractical due to size, weight, or frequent access requirements, install temporary guardrails around full penetration perimeter using scaffolding components or purpose-built guardrail systems. Guardrails must be minimum 900mm high with mid-rail approximately 450-500mm height and toe boards minimum 150mm high preventing materials rolling into opening. Guardrails must be fixed securely to floor or structural elements capable of resisting horizontal force of minimum 200N applied at top rail. For penetrations that are actively used for material passing with covers removed, establish exclusion zones using temporary barriers positioned back from penetration preventing inadvertent approach by workers not directly involved in pipe passing work. Paint high-visibility markings on floor surface around penetrations providing additional visual warning of hazard location visible when covers are temporarily removed. Implement cover management protocols designating responsibility for cover replacement - typically the last worker to use penetration is responsible for replacing cover before leaving area, with supervisor conducting verification checks. Brief all workers who access riser areas on penetration locations, protection requirements, and prohibition of removing covers except when specifically necessary for pipe work. Document penetration protection with site plans showing penetration locations, photographs of protected penetrations, and inspection records verifying ongoing protection compliance. For construction projects under principal contractor control, principal contractor typically establishes site-wide floor penetration protection standards that riser installation must comply with including cover specifications, marking requirements, and inspection schedules. Remember that falls through floor penetrations have caused fatalities and serious injuries on construction sites - consistent rigorous protection of all penetrations throughout construction period is critical safety requirement not optional administrative detail.

What fire penetration seal requirements apply to riser pipes passing through floors, and who can install these seals?

Fire penetration seals around riser pipes passing through fire-rated floors and walls are critical building fire safety elements regulated under Building Code of Australia (BCA) which requires fire-rated construction elements to maintain their fire resistance rating when penetrated by services. For multi-storey buildings, floor slabs typically have fire resistance level (FRL) ratings of 60/60/60 to 120/120/120 (structural adequacy/integrity/insulation in minutes), and penetrations through these floors must maintain equivalent fire resistance. Penetration seal systems comprise products installed in annular gap between pipe and penetration edge that expand when exposed to fire, sealing gap and preventing fire and smoke passage. BCA recognizes several evidence of suitability pathways for penetration seals with most common being products holding CodeMark certification demonstrating compliance through testing to AS 1530.4 or AS 4072.1, or products with assessment reports from accredited testing laboratories. Seal product selection must account for multiple factors including pipe material (different products for steel, copper, PVC, composite pipes as material behavior in fire differs substantially), pipe diameter (products specify maximum and minimum pipe diameters), floor or wall fire resistance level required (seal must achieve equal or greater FRL), and installation configuration (different products for floor versus wall penetrations, and whether single pipe or multiple pipes in one penetration). Installation must comply exactly with product manufacturer specifications including annular gap dimensions (typically 10-25mm but varies by product), seal thickness achieving required FRL, installation technique such as packing density for intumescent materials or spray application parameters for spray-applied products, and any additional components such as backing materials or surface treatments. Installer requirements vary by jurisdiction but increasingly building certifiers require installers to hold manufacturer approval or accreditation for specific products being installed, as this ensures installer competency and maintains product warranties and certifications. Some manufacturers operate formal approved installer programs providing training and certification with installation by non-approved installers potentially voiding product certification. For critical installations in large projects, consider engaging fire protection specialists holding specific fire penetration sealing credentials. Installation timing is important - seals must install after pipes are in final position as seal removal and reinstallation typically voids certification, but before building elements that would prevent future access are installed such as shaft wall lining. Building certifier inspection typically occurs at holding point after seal installation but before concealment allowing verification of compliant installation and opportunity to correct deficiencies. Documentation requirements include maintaining product data sheets and CodeMark certificates for all seal products used, photographs showing each penetration before, during, and after seal installation, penetration schedule listing every sealed penetration with location, pipe type and diameter, seal product used, installer details, and date of installation, installer declarations certifying installation per manufacturer specifications, and certifier sign-off after inspection confirming compliant installation. Provide complete seal documentation to building certifier for building certification file and to building owner for building operating manuals and future maintenance reference. Seal compliance failures can result in building occupancy delays pending rectification, certifier orders requiring exposure of sealed penetrations for inspection at contractor expense if compliance cannot otherwise be verified, requirement to remove non-compliant seals and reinstall using correct products and approved installers, and in worst cases removal of services and structural penetration modification if seal compliance cannot be achieved with existing penetration configuration. Prevention through careful product selection, use of approved installers, and building certifier engagement before concealment avoids costly rectification. Remember that fire seal integrity directly affects building occupant safety in fire events - unsealed or improperly sealed penetrations allow fire and smoke spread between floors potentially trapping occupants and causing casualties, making this not merely administrative compliance but critical life safety issue.

How should communication be managed between workers on different floor levels during riser installation to prevent incidents?

Effective communication between workers at different floor levels during riser installation is critical safety requirement preventing struck-by incidents, crushing injuries, and dropped object incidents that occur when workers perform uncoordinated simultaneous actions. Unlike normal work where workers can see each other and coordinate visually, multi-level riser work separates workers by floor slabs preventing visual contact and requiring deliberate communication systems. Implement comprehensive communication protocols beginning with providing two-way radio equipment to all workers involved in riser installation - specify dedicated radio channel for riser work team preventing interference from other site communications and ensuring clear reception. Establish standard verbal communication signals used consistently for all vertical material movements including "Ready to lift" requiring "Ready" acknowledgment from all workers at all levels involved before lifting commences, "Lifting now" announced by initiating worker as lift begins, "Stop" as immediate cessation command if any worker identifies hazard, "Set down" when item reaches destination and is positioned safely, and "Secure" confirmation from receiving worker that item is properly secured and lifting worker can release. Require positive acknowledgment of all communications - sending worker must receive verbal confirmation from all receiving workers before proceeding, not assumption of readiness from silence. Before any vertical material movement or activity affecting other levels, conduct verbal roll-call with workers at each level confirming position and readiness. Implement work zone designation within vertical shafts prohibiting workers from being positioned directly below active work - workers at lower levels must be offset horizontally within shaft space or excluded from shaft during overhead work creating dropped object risk. For complex multi-step operations such as installing and joining multi-section riser assemblies, develop job-specific work procedures documenting step-by-step sequence, required communication at each step, designated worker positions at each level, and verification requirements before proceeding to next step. Conduct pre-start meetings each day involving all workers participating in riser work reviewing day's work plan, communication protocols, specific hazards anticipated, and emergency procedures. Where shaft configuration allows, install visual communication aids such as shaft cameras allowing workers to verify others' positions, colored lights signaling ready status at different levels, or mirrors positioned allowing line-of-sight through shaft openings. Establish backup communication for radio failure situations using agreed physical signals such as whistle codes, tapping signals transmitted through pipes, or light signals visible between levels, with procedure to cease work if primary communication capability is lost until restored or backup method verified functional. For emergency situations, establish emergency signals understood by all workers such as continuous whistle blast or repeated "EMERGENCY" radio calls requiring immediate work cessation and implementation of emergency procedures. Brief workers on prohibition of solo work in multi-level installations requiring minimum two workers maintaining communication capability and emergency response capacity. Implement supervisor verification checking communication protocols are being followed through random observations of work and immediate correction if shortcuts or informal methods are observed. Document near-miss incidents where communication failures nearly resulted in incidents conducting formal lessons-learned analysis identifying root causes such as unclear communication, misunderstood signals, inadequate radio discipline, or assumption rather than verification, implementing corrective actions such as revised communication protocols, additional worker briefing, or enhanced supervision. Consider communication training for workers unfamiliar with radio use covering radio discipline (clear concise messages, proper procedure words, prohibition of casual conversation on work channels), signal protocols (standard phrases used consistently), and emergency communications. For particularly complex installations or high-risk operations, designate communication coordinator responsible for coordinating multi-level activities, ensuring all workers are aware of work plan, verifying readiness before activities commence, and monitoring for communication failures or coordination problems. Test communication systems before work begins each day verifying radios function throughout shaft depth, all workers understand signals, and backup methods are known. Remember that communication failures in multi-level work have caused serious incidents including workers crushed by pipes released unexpectedly from above, struck by dropped objects, or injured when receiving worker was not positioned properly because sending worker proceeded without confirmation - rigorous consistent communication discipline prevents these incidents making communication protocols not bureaucratic procedure but essential safety system.

What mechanical lifting systems are practical for moving pipes vertically through multi-storey riser shafts?

Mechanical lifting systems for vertical pipe movement in riser shafts provide substantial safety and efficiency benefits compared to manual lifting which creates extreme musculoskeletal strain in confined vertical spaces. System selection depends on building height, shaft configuration, pipe weight, and project duration. For low-rise installations up to 4-5 floors, portable rope and pulley systems provide practical solution using mechanical advantage reducing manual force required - typical 3:1 or 4:1 pulley systems allow one or two workers to raise pipes that would otherwise require 3-4 workers for manual lifting. Install temporary pulley assemblies at top of shaft secured to structural elements capable of supporting full pipe weight plus dynamic loads, with rope extending to ground level or working floor. Workers at base attach pipe to rope using secure sling, workers at top haul rope raising pipe with workers at intermediate levels guiding pipe preventing binding against shaft walls or structures. For medium-rise installations 5-10 floors, portable winches or hand-operated lever hoists provide greater mechanical advantage positioned at strategic floors - typically install winch at top floor or at intermediate floor aligned with shaft allowing controlled raising or lowering of pipes. Electric winches provide easier operation than manual winches for repetitive lifting but require electrical supply in shaft. Winch capacity must exceed maximum pipe section weight - typical plumbing riser pipe sections weigh 20-50kg requiring winch capacity 100-200kg accounting for safety factor. For tall buildings exceeding 10 floors or large-diameter heavy steel risers, purpose-built pipe installation equipment provides most efficient solution - some mechanical contractors use specialized riser installation rigs comprising powered winches with remote controls, guide systems maintaining pipe alignment during lifting, and automated feed systems. For external building risers accessible to cranes, crane lifting of pre-fabricated multi-floor riser sections provides maximum efficiency - fabricate complete riser sections at ground level including all joints, branches, and fittings, crane-lift complete assembly positioning at multiple floors simultaneously secured at each floor as lifting progresses. This approach minimizes work in confined shafts and reduces total installation time substantially. Lifting equipment safety requirements include securing lifting equipment to structural elements verified capable of supporting loads with appropriate safety factors (typically 5:1 for static loads), using certified lifting equipment with current inspection and load rating tags, implementing fall protection preventing workers falling down shaft while operating lifting equipment positioned near penetrations, establishing dropped object prevention ensuring pipes remain secured during lifting and tools cannot fall if dropped, providing worker training in lifting equipment operation including load limits, proper rigging techniques, and emergency procedures if equipment fails or pipe becomes jammed. For all mechanical lifting systems, implement systematic communication protocols between workers at different levels using two-way radios with standard signals before, during, and after each lift. Never rely on shouted voice communication between floor levels as this is unreliable and easily misunderstood. Consider pre-fabrication opportunities reducing number of individual lifts and amount of jointing work in confined shafts - joining multiple pipe sections at ground level or at convenient floor levels creating longer assemblies reduces total lifts required and associated manual handling. Brief workers that mechanical aids are mandatory for pipe lifting with manual lifting only permitted for light pipes (typically under 15kg) that one worker can safely control - never manually lift heavy pipes simply because mechanical equipment setup takes time, as this creates serious injury risk. Maintain lifting equipment throughout installation period with daily pre-use inspections checking wire ropes for damage, pulley wheels rotate freely, winch brakes function correctly, and securing points remain tight. Document lifting operations particularly for heavy or complex lifts with lift plans showing rigging arrangement, load weight, equipment capacity verification, and worker positions providing reference for similar future lifts. Remember that manual handling injuries dominate plumbing injury statistics with back injuries often causing permanent reduced work capacity - investment in mechanical lifting equipment provides both immediate project safety benefits and long-term worker health protection supporting sustainable plumbing careers rather than injuries forcing early retirement from physical inability to continue trade work.

Related SWMS documents

Browse all documents

plumbing

CCTV Drain Inspection Safe Work Method Statement

Comprehensive SWMS for CCTV drainage investigation including confined space entry, sewage exposure controls, camera equipment operation, and inspection reporting procedures.

View document

plumbing

Electric Fusion - Poly Pipe Butt Welding (PPW) Safe Work Method Statement

Comprehensive SWMS for electric fusion and butt fusion welding of polyethylene pipes including hot work controls, equipment operation, surface preparation, and pressure testing procedures.

View document

plumbing

Gas-Water Leak Detection Safe Work Method Statement

Comprehensive SWMS for gas and water leak detection including electronic detection equipment, acoustic listening, tracer gas methods, and emergency response procedures for gas and water system leaks.

View document

plumbing

Gross Pollutant Trap Cleaning Safe Work Method Statement

Comprehensive SWMS for gross pollutant trap cleaning including confined space entry, contaminated waste removal, vacuum equipment operation, and stormwater protection procedures.

View document

plumbing

Guided Boring Pipe Jacking Works Safe Work Method Statement

Comprehensive SWMS for guided boring and pipe jacking trenchless installation including service location, confined space entry, drilling equipment operation, and strike prevention procedures.

View document

plumbing

Medical Gas Pipe System Installation Safe Work Method Statement

Comprehensive SWMS for installing medical gas pipeline systems in healthcare facilities including oxygen, medical air, vacuum, and anaesthetic gas distribution with contamination prevention and pressure testing protocols.

View document
Trusted by 1,500+ Australian construction teams

Risers Working In SWMS Sample

Professional SWMS created in 5 seconds with OneClickSWMS

  • Instant PDF & shareable link
  • Auto-filled risk matrix
  • Editable Word download
  • State-specific compliance
  • Digital signature ready
  • Version history preserved
Manual creation2-3 hours
OneClickSWMS5 seconds
Save 99% of admin time and eliminate manual errors.

No credit card required • Instant access • Unlimited drafts included in every plan

PDF Sample

Risk Rating

BeforeHigh
After ControlsLow

Key Controls

  • • Pre-start briefing covering hazards
  • • PPE: hard hats, eye protection, gloves
  • • Emergency plan communicated to crew

Signature Ready

Capture digital signatures onsite and store revisions with automatic timestamps.

Continue exploring

Hand-picked SWMS resources

Ready to deliver professional SWMS in minutes?

OneClickSWMS powers thousands of compliant projects every week. Join them today.