Comprehensive SWMS for safe excavation and trenching for plumbing drainage and pipeline installations

Trench Excavation Safe Work Method Statement

2,000+ Australian Businesses Trust OneClickSWMS

No credit card required • Instant access • 100% compliant in every Australian state

5 sec
Creation Time
100%
Compliant
2,000+
Companies
$3.6K
Fines Avoided

Avoid WHS penalties up to $3.6M—issue compliant SWMS to every crew before work starts.

Trench excavation for plumbing drainage and pipeline installation involves creating linear excavations for installing underground pipes, conduits, and services. Work includes excavation for sewer lines, stormwater drainage, water mains, gas pipelines, and service connections from buildings to street mains. This Safe Work Method Statement addresses critical excavation hazards including trench collapse burying workers, striking underground services causing injuries and service disruption, falls into excavations, and environmental hazards from groundwater, contaminated soil, or unstable ground conditions.

Unlimited drafts • Built-in WHS compliance • Works across every Australian state

Overview

What this SWMS covers

Trench excavation for plumbing installations creates linear excavations ranging from shallow trenches under 0.5 metres depth for residential drainage connections through to deep excavations exceeding 3 metres for sewer mains, water mains, and deep service installations. These trenches allow installation of underground pipework connecting buildings to street infrastructure, installing drainage systems collecting stormwater and sewage, and establishing service corridors for multiple utilities. The linear nature of trenches with length significantly exceeding width distinguishes trench excavation from general excavations or basements, creating specific stability and access challenges requiring specialized controls. Typical plumbing trench excavations include sewer connections from building drainage to street sewer main typically 1.5-2.5 metres deep depending on street main depth and site levels, stormwater drainage trenches collecting roof and surface water conveying to street drainage or on-site absorption systems typically 0.5-1.5 metres deep, water service connections from street water main to building meter position typically 0.5-1.0 metres deep, gas service trenches for natural gas or LPG connections typically 0.6-1.0 metres deep, and combined service trenches accommodating multiple services in single excavation. Trench widths typically range from 400-600mm for single pipe installations providing adequate working space for pipe laying and jointing, through to 1.5-2.0 metres for larger diameter pipes or multiple services requiring additional working room. Excavation methodology varies with depth, soil conditions, and site constraints. Shallow trenches under 1.5 metres in stable soil may be excavated with near-vertical sides if workers do not enter trench for extended periods, with pipes installed by workers standing outside trench reaching in, or by brief entry for pipe connection work. Deeper trenches or any depth in unstable soil require protective systems including shoring using mechanical shields or hydraulic shoring systems, benching excavation sides creating stepped configuration reducing wall height, or battering excavation sides at safe angle typically 1:1.5 (horizontal:vertical) eliminating collapse risk but requiring substantial excavation width. Modern plumbing excavations increasingly use trench shields - pre-fabricated aluminum or steel box structures lowered into excavation as work progresses providing immediate protection from collapse while allowing efficient work progress. Work sequencing typically involves service location using Dial Before You Dig enquiry and electromagnetic location equipment identifying existing underground services, marking proposed trench alignment on ground surface, establishing exclusion zones and barricades preventing unauthorized access, excavating using excavator or backhoe maintaining safe distances from identified services with final exposure by hand tools, installing shoring, benching, or battering as excavation progresses based on depth and soil conditions, laying pipes in excavated trench with workers protected from collapse hazards, testing installed pipes before backfilling verifying integrity, backfilling trench progressively from pipe foundation layer through selected fill to surface with adequate compaction, and reinstating surface to match existing conditions with pavement, grass, or landscaping replacement. Critical hazards requiring comprehensive controls include trench collapse and engulfment where soil walls fail burying workers potentially causing fatal asphyxiation within minutes as collapse weight prevents chest expansion and buries airways, striking underground services during excavation including water mains under pressure creating high-pressure water jet hazards, gas mains creating explosion risk from gas release, electrical cables causing electrocution particularly in wet excavations, and telecommunications cables causing service disruption, falls into excavations by workers or public approaching unbarricaded trenches, groundwater ingress flooding excavations creating drowning risk and undermining trench stability, contaminated soil exposure from previous industrial use or naturally occurring contaminants, confined space hazards in deep trenches with limited air circulation, and mobile plant hazards from excavators and trucks operating near trench edges potentially causing collapse from loading or falling into trenches. This SWMS addresses these hazards through systematic controls ensuring safe trench excavation for plumbing installations complying with Australian WHS legislation and AS 2601 Demolition of Structures standard which also covers excavation safety principles.

Fully editable, audit-ready, and aligned to Australian WHS standards.

Why this SWMS matters

Trench excavation represents one of the highest-risk construction activities with excavation fatalities occurring regularly in Australian construction. Trench collapse incidents cause rapid burial with soil weight preventing breathing, creating fatal asphyxiation within 3-5 minutes. Unlike other construction fatalities where victims may survive initial incident if rapid medical response occurs, trench collapse victims frequently die before rescue can occur due to rapid asphyxiation and the substantial time required to excavate collapsed soil to reach buried workers. The particularly tragic nature of excavation fatalities where victims are buried alive and workmates witness helplessly has prompted regulatory focus on excavation safety making this one of the most scrutinized construction activities. Under WHS Regulations, excavation work exceeding 1.5 metres depth or any depth creating potential for collapse or engulfment is classified as high-risk construction work requiring Safe Work Method Statement to be prepared before work commences. The SWMS must identify excavation hazards including potential for collapse based on soil type and groundwater conditions, specify control measures following hierarchy of control with preference for protective systems like shoring over reliance on soil stability, describe emergency procedures for trench collapse including rescue equipment and trained personnel, and be reviewed by workers before excavation commences. Excavation PCBUs must ensure SWMS is implemented, workers are competent and adequately supervised, and appropriate protective systems are used based on excavation depth and soil conditions. Failure to prepare and implement adequate SWMS for high-risk excavation work can result in prosecution with recent cases resulting in fines exceeding $500,000 for companies and personal fines for directors and supervisors where failures contributed to fatalities. Recent trench collapse fatalities demonstrate consequences of inadequate excavation controls. A Melbourne worker died when trench walls collapsed burying him in 2.5 metres of soil - investigation found no shoring was used despite depth and soil conditions clearly requiring protection, resulting in company prosecution and fines exceeding $300,000. A Queensland plumber died in similar circumstances when excavating sewer connection trench - trench depth was 2.2 metres in sandy soil and worker was in trench connecting pipes when collapse occurred. Company received maximum penalty available and director received personal fine. A Sydney incident resulted in two deaths when stormwater drainage trench collapsed burying workers - trench was 3 metres deep with vertical walls in clay soil that appeared stable but failed suddenly during heavy rain. These incidents share common factors including underestimation of collapse risk with perception that soil appears stable or has remained stable for hours or days leading to assumption it will remain stable, inadequate understanding of soil mechanics where workers and supervisors lack knowledge about how soil type, moisture content, vibration, and time affect stability, time pressure to complete work quickly discouraging proper shoring installation as 'too slow,' and normalization of unsafe practices where previous non-use of shoring without incident creates complacency. Beyond collapse risk, striking underground services during excavation creates severe hazards and substantial financial consequences. Striking high-pressure water mains releases water jets capable of causing injuries, creates flooding undermining adjacent structures, disrupts water supply to surrounding properties requiring emergency repairs, and exposes excavator to water authority charges for main repairs potentially tens of thousands of dollars plus consequential damage costs. Gas line strikes are particularly dangerous as gas release creates explosion and fire risk - natural gas or LPG leaking into trench or nearby structures can ignite from any ignition source including excavator electrical systems, nearby hot work, or static discharge. Gas explosions from excavation incidents have caused fatalities and destroyed nearby buildings. Electrical cable strikes cause electrocution particularly in wet excavations where water provides conduction path from struck cable to excavator and operator. Even low-voltage street lighting cables carry sufficient current to cause fatal electrocution. Telecommunications cable strikes while not creating safety hazards cause service disruptions affecting businesses and potentially emergency services, resulting in claims from service providers for repair costs and consequential losses from service disruption potentially exceeding $100,000 for major cable routes. Service strike prevention relies on comprehensive service location before excavation using Dial Before You Dig mandatory enquiry system providing service plans from all asset owners, electromagnetic location equipment physically locating cables and pipes, and careful excavation technique maintaining safe clearances from identified services with hand digging or hydro-vacuum excavation for final exposure near services. Despite these processes, service strikes continue occurring from inaccurate service plans showing services in positions different from actual locations, inadequate location where services are too deep or too close to other services for electromagnetic detection, and excavation technique failures where operators excavate too close to identified services or fail to adjust to unexpected services encountered. Recent legislative changes in some states impose strict liability for service strikes meaning excavators are liable for damage even if they followed reasonable location procedures, emphasizing need for extreme caution when excavating near identified services. Groundwater in excavations creates multiple hazards including trench wall instability as water infiltration weakens soil reducing stability and potentially causing sudden collapse, drowning risk if excavations flood faster than workers can escape particularly in deep narrow trenches, reduced visibility in muddy water obscuring hazards and dropped tools, and hypothermia from working in cold water particularly in winter. Dewatering using pumps manages groundwater but requires continuous operation and monitoring ensuring pumps remain operational - pump failure allowing water accumulation can rapidly create unstable conditions. Contaminated soil from previous industrial use, illegal dumping, or naturally occurring contaminants including asbestos, hydrocarbons, heavy metals, or organic contaminants creates health hazards requiring soil assessment before excavation, appropriate PPE during contaminated soil handling, and proper disposal at licensed facilities potentially adding substantial unexpected costs. The compounding nature of excavation hazards where multiple hazards interact creates complex risk scenarios - for example, striking water main while workers are in trench creates both flooding and potential for trench collapse from water infiltration, or groundwater presence near electrical cable strike creates enhanced electrocution risk. Systematic risk assessment identifying all hazards and appropriate controls for each hazard and their interactions is essential for safe excavation work. Professional excavation contractors maintain detailed procedures, competent supervision, appropriate equipment, and safety culture prioritizing protection over production. SWMS implementation, worker training, daily toolbox talks, and active supervision ensure planned controls are actually implemented throughout excavation work.

Reinforce licensing, insurance, and regulator expectations for Trench Excavation Safe Work Method Statement crews before they mobilise.

Hazard identification

Surface the critical risks tied to this work scope and communicate them to every worker.

Risk register

Trench Collapse and Engulfment of Workers

High

Trench walls failing and collapsing inward burying workers in excavation creates extreme life-threatening hazard. Soil weight prevents chest expansion and breathing causing asphyxiation within 3-5 minutes. Even partial burial immobilizing worker prevents escape if further collapse occurs. Collapse can occur suddenly without warning or gradually with minor sloughing preceding major failure. Contributing factors include inadequate shoring or battering for trench depth and soil type, soil conditions including cohesionless sandy soils or saturated soils with low stability, excavation depth exceeding soil's natural stable angle, groundwater infiltration weakening trench walls, vibration from nearby traffic, equipment, or impact causing soil disturbance, surcharge loads from spoil piles, materials, or equipment placed near trench edge loading soil, time effects where trenches appearing initially stable deteriorate over hours or days, and weather effects including rain saturating soil or freezing/thawing cycles weakening stability.

Striking Underground Services During Excavation

High

Excavating without adequate service location or excavating too close to identified services can strike underground utilities creating severe hazards and service disruptions. Striking high-pressure water mains releases pressurized water jets (typically 400-600 kPa supply pressure) capable of causing injuries, creates rapid flooding potentially undermining trench walls causing collapse, and disrupts water supply to surrounding properties. Gas main strikes release natural gas or LPG creating explosion and fire hazard - gas accumulating in trench or nearby structures can ignite from excavator electrical systems, static discharge, or other ignition sources. Electrical cable strikes create electrocution risk particularly in wet excavations where water conducts electricity from damaged cable to excavator and operator. Even low-voltage cables carry sufficient current for fatal electrocution. Telecommunications cable strikes cause massive service disruptions affecting businesses and emergency services. Service plans may be inaccurate showing services in incorrect positions, undocumented services from unauthorized installations may exist, and services can be deeper or shallower than documented depths.

Falls into Excavations

High

Workers or public approaching excavations without adequate barricades or edge protection can fall into trenches suffering serious fall injuries. Excavation edges may not be immediately visible particularly in poor lighting, long grass, or when excavations are recent and disturbed soil looks similar to undisturbed ground. Workers walking backward, carrying materials with obstructed vision, or distracted by other work activities may not see excavation edges. Public access to construction sites particularly children investigating site creates fall risk. Vehicle or equipment approaching excavations can drive into trenches particularly when ground conditions create edge failure under vehicle weight. Falls from heights exceeding 1.5 metres trigger serious injury potential including fractures, head injuries, and spinal injuries. Landing on pipes, equipment, or spoil in trench bottom increases injury severity.

Groundwater Ingress and Flooding

Medium

Excavations below water table or in areas with high groundwater encounter water infiltration requiring management. Groundwater seepage through trench walls collects in excavation bottom creating standing water. Heavy rain can rapidly fill excavations. Water infiltration weakens trench walls reducing stability and increasing collapse risk. Deep water in narrow trenches creates drowning hazard if workers slip or are trapped. Cold water creates hypothermia risk particularly in winter. Muddy water reduces visibility obscuring hazards and dropped tools. Water in excavations makes walking and working surfaces slippery increasing slip hazards. Electrical equipment in wet excavations creates enhanced electrocution risk. Rapid water accumulation from rain, burst mains, or sudden groundwater breakthrough can overwhelm dewatering capacity faster than workers can escape.

Contaminated Soil Exposure

Medium

Excavations may encounter contaminated soil from previous industrial use, illegal dumping, underground storage tank leaks, or naturally occurring contaminants. Common contaminants include asbestos from demolished buildings, hydrocarbons from fuel storage or vehicle operations, heavy metals from industrial processes, organic contaminants from chemical storage, and naturally occurring contaminated fill. Asbestos exposure occurs from disturbing asbestos-contaminated fill or buried asbestos materials creating airborne fiber exposure. Hydrocarbon contamination creates vapor exposure and skin contact hazards. Some contaminants are not immediately obvious without testing. Contaminated soil requires special handling, worker protection, and disposal at licensed facilities adding substantial unexpected costs. Inadequate containment allows contaminant migration to surrounding properties creating environmental harm liability.

Control measures

Deploy layered controls aligned to the hierarchy of hazard management.

Implementation guide

Trench Protective Systems Including Shoring and Benching

Engineering

Installing protective systems including trench shields, shoring, benching, or battering prevents trench collapse by physically supporting trench walls or reducing wall height to stable angles. This engineering control creates physical barrier preventing collapse rather than relying on soil stability assessment which involves uncertainty. Protective systems are mandatory for excavations exceeding 1.5 metres or any depth in unstable soil.

Implementation

1. Conduct soil assessment before excavation determining soil type (clay, sand, rock, mixed) and moisture conditions affecting stability requirements for protective systems 2. For excavations exceeding 1.5 metres depth in any soil or any depth in unstable soil (loose sand, saturated soil, previously disturbed fill), implement protective systems before workers enter excavation 3. Use trench shields (also called trench boxes) for most plumbing excavations - these are pre-fabricated steel or aluminum box structures lowered into excavation providing immediate protection as excavation deepens, sized to match trench width and depth with shields extending minimum 500mm above ground level preventing edge failure into trench 4. Install hydraulic shoring for wider trenches or irregular excavations - adjustable hydraulic struts spanning between shoring panels pushing against trench walls preventing collapse, with struts positioned at maximum 1.2 metre vertical spacing and shoring panels extending full excavation depth 5. Implement benching (stepped excavation) for excavations in competent soil creating stepped sides reducing wall height to stable dimension - typically 1.5 metre maximum vertical height per step with minimum 600mm horizontal step width 6. Use battering (sloped sides) for excavations where space permits sloping walls at safe angle typically 1:1.5 (1 metre vertical to 1.5 metres horizontal) in most soils eliminating collapse risk but requiring substantial excavation width 7. Never enter unprotected excavations exceeding 1.5 metres depth or any depth in unstable soil even briefly - protection must be in place before any entry regardless of work duration 8. Extend protective systems from excavation bottom to minimum 500mm above ground level preventing edge material falling into trench 9. Inspect protective systems daily before work commences and after any event potentially affecting stability including heavy rain, nearby vibration, or loading changes, verifying shoring remains secure with struts tight and no evidence of wall movement 10. Brief workers that protective systems must not be removed or modified without engineering approval and must remain in place until backfilling is complete

Comprehensive Underground Service Location

Elimination

Accurately locating all underground services before excavation eliminates hazard of striking services during excavation. This control involves obtaining service plans, physical location using electromagnetic equipment, and verification excavation using non-destructive methods. Compliance with Dial Before You Dig mandatory enquiry system ensures all asset owners are notified and provide service information.

Implementation

1. Submit Dial Before You Dig enquiry minimum 2 working days before excavation providing accurate excavation location using site plan or aerial imagery showing proposed trench alignment 2. Receive and review service plans from all asset owners including water, sewer, stormwater, electricity, gas, telecommunications, and any private services (irrigation, data cables), noting service depths, materials, and ages 3. Engage qualified service locator using electromagnetic location equipment tracing services and marking on ground surface using color-coded paint (blue for water, yellow for gas, red for electricity, green for sewer, orange for telecommunications) 4. For critical services including high-pressure gas or electricity cables, conduct verification excavation using hydro-vacuum excavation or hand digging exposing service at one location confirming actual position and depth before mechanical excavation 5. Establish safe clearance zones around identified services typically minimum 600mm horizontal clearance from service to edge of mechanical excavation, with final approach to this clearance by hand tools only 6. Use hand tools (shovels, spades) or hydro-vacuum excavation for final exposure within 600mm of identified services preventing striking services with excavator bucket teeth 7. Mark excavation alignment on ground surface showing safe clearance zones ensuring excavator operator can see marked alignment and clearances from operator position 8. Brief excavator operator on service locations and clearance requirements providing marked plans showing services relative to proposed excavation 9. Maintain active service awareness throughout excavation watching for service marker posts, valve pits, or other indicators of services not shown on plans 10. If services are encountered during excavation in positions different from plans, stop excavation immediately, confirm service type and owner, and reassess excavation approach with possible hand excavation or service relocation if required

Excavation Barricading and Edge Protection

Engineering

Installing barricades around excavation perimeter prevents falls into trenches by workers or public. This engineering control creates physical barrier preventing access to excavation edges. Barricades must be visible, substantial, and positioned at safe distance from excavation edge.

Implementation

1. Install barricades around full perimeter of excavations using temporary fencing, barrier mesh, or safety barriers positioned minimum 1.5 metres back from excavation edge allowing clearance for edge failure and spoil placement 2. Use highly visible barricading with orange or red barrier mesh, white and red tape, or solid barriers ensuring visibility in all lighting conditions including night-time 3. Install warning signage on barricades indicating "DEEP EXCAVATION," "DANGER," or "AUTHORIZED PERSONNEL ONLY" at regular intervals 4. Provide safe access points to excavation for workers using ladder access or excavated steps rather than climbing down trench walls, positioning access points away from excavation ends where collapse risk is highest 5. Install overhead protection if work must occur adjacent to excavations preventing materials or tools falling into trenches potentially striking workers below 6. For excavations in public areas or near building entries, install substantial barricades preventing public access using solid fencing or concrete barriers if barrier mesh inadequate 7. Illuminate excavations working during darkness or in areas with poor natural lighting using temporary lighting on barricades making excavation locations clearly visible 8. Inspect barricades daily verifying they remain in place and have not been removed or damaged, particularly checking after hours when site is unattended 9. Maintain clear sight lines to excavations from site access points allowing workers entering site to see excavation locations before approaching 10. Establish exclusion zones beyond barricades where mobile plant and vehicles are prohibited preventing edge loading from vehicle weight near excavations

Groundwater Management and Dewatering

Engineering

Implementing dewatering systems removes groundwater from excavations maintaining dry working conditions and trench wall stability. This engineering control uses pumps to continuously remove water preventing accumulation that would weaken walls or create drowning hazards. Dewatering system design must account for groundwater inflow rates and excavation depth.

Implementation

1. Assess groundwater conditions before excavation determining likely water table depth and inflow rates based on site location, season, and recent rainfall 2. Provide adequate dewatering equipment including submersible pumps sized for anticipated inflow rates (typically minimum 200 litres per minute for plumbing trenches), standby backup pump in case primary pump fails, and generator or reliable electrical supply ensuring continuous pump operation 3. Install sump points in excavation low points collecting groundwater for pump removal, using coarse aggregate around pump intake filtering sediment preventing pump clogging 4. Discharge pumped water to approved locations including stormwater system if water quality is acceptable, sediment basin for treatment before discharge, or tanker removal if water is contaminated or discharge is not permitted 5. Implement continuous pumping during excavation work maintaining excavation floor dry - do not rely on periodic pumping as water accumulation between pumping cycles undermines stability 6. Provide backup power supply ensuring pumps continue operating during power failures - sudden water accumulation from pump failure can create rapid stability deterioration 7. Monitor water accumulation rates adjusting pumping capacity if inflow exceeds initial estimates requiring larger or additional pumps 8. Brief workers on pump operation and monitoring requiring verification pumps are operational before workers enter excavations and continuous monitoring during work 9. Implement wet weather procedures ceasing excavation during heavy rain when water accumulation may exceed dewatering capacity, covering excavations if possible, and inspecting trench stability after rain events before resuming work 10. For excavations with severe groundwater problems, consider alternative methods including wellpoint dewatering lowering water table before excavation, or pipe jacking/boring avoiding open excavation in groundwater zones

Contaminated Soil Assessment and Management

Administrative/Engineering

Conducting contaminated soil assessment before excavation identifies contamination allowing appropriate controls including worker protection, contamination containment, and proper disposal. This control combines investigation (administrative) with containment and protective measures (engineering/PPE) managing contaminated soil hazards.

Implementation

1. Research site history before excavation identifying previous uses that may have caused contamination including industrial activities, fuel storage, dry cleaning operations, or known dumping sites 2. Conduct preliminary soil assessment if contamination is possible based on site history, engaging environmental consultant to test soil samples for likely contaminants including asbestos, hydrocarbons, heavy metals 3. If contamination is confirmed or strongly suspected, develop contamination management plan documenting contamination type and extent, worker protection requirements including PPE and hygiene, excavation and handling procedures preventing spread, and disposal requirements at licensed facilities 4. Provide enhanced PPE for contaminated soil work including chemical-resistant gloves, respiratory protection (minimum P2 for asbestos, organic vapor cartridges for hydrocarbon contamination), and disposable coveralls preventing contamination of regular clothing 5. Establish decontamination procedures including boot wash stations before leaving contaminated area, prohibition of eating or drinking in contaminated areas, and handwashing or sanitizer use before breaks 6. Contain contaminated soil preventing spread to surrounding areas using temporary bunding, plastic sheeting, or segregated stockpiling, and minimizing dust generation during handling using water sprays 7. Arrange disposal at appropriately licensed facilities for contamination type - asbestos to licensed asbestos disposal facility with waste tracking, hydrocarbons to contaminated soil treatment facility 8. Document contaminated soil quantities removed and disposal locations providing verification of proper disposal and compliance with environmental regulations 9. Brief workers on contamination hazards specific to contaminants identified and requirements for protection and decontamination 10. Notify principal contractor and building owner of contamination encountered providing documentation of management and disposal for future site records

Daily Pre-Start Excavation Inspections

Administrative

Conducting formal pre-start inspections daily before work commences verifies excavation remains safe addressing overnight changes from weather, groundwater, or vibration that may have affected stability. This administrative control establishes systematic verification procedures detecting deterioration before workers enter excavations.

Implementation

1. Designate competent person to conduct daily pre-start excavation inspections - typically site supervisor or experienced excavation worker trained in hazard recognition 2. Conduct inspection before any workers enter excavation each day checking trench walls for cracking, bulging, or sloughing indicating stability deterioration, protective systems (shoring, shields) remain secure with no loosening or displacement, groundwater accumulation from overnight inflow verifying dewatering pumps operated correctly, barricades remain in place and undamaged, and weather effects from overnight rain or frost 3. Document inspection using written checklist recording date, inspector name, conditions observed, and approval to commence work 4. Implement remedial actions if inspection identifies deficiencies including pumping accumulated water before entry, tightening or adjusting shoring if movement is detected, installing additional shoring if soil conditions deteriorated, or prohibiting entry and seeking engineering assessment if serious stability concerns exist 5. Repeat inspections after significant events affecting excavation including heavy rain, nearby vibration from traffic or piling, or extended periods without work where excavation remained open allowing deterioration 6. Brief workers each day on inspection results and any changes to excavation conditions or work procedures required 7. Maintain inspection records throughout excavation project documenting ongoing attention to safety and providing evidence of due diligence 8. Empower inspector to prohibit work if excavation is not safe regardless of schedule pressure, with authority to require engineering assessment if uncertainty exists about stability 9. Include inspection of excavator and dewatering equipment verifying operational condition before use 10. Review near-misses or incidents updating inspection checklist to include any new hazard types identified

Personal protective equipment

Requirement: Safety helmet to AS/NZS 1801 Type 1

When: Required during all excavation work providing protection from falling materials, overhead hazards from excavator bucket, and head protection if trench walls collapse striking workers. Mandatory in active excavation areas.

Requirement: Lace-up boots with steel toe caps, ankle support, waterproof construction

When: Required continuously during excavation work providing protection from crush injuries from pipes and equipment, penetration protection from rocks and debris in excavations, ankle support for stability on uneven ground, and waterproofing for work in wet excavations.

Requirement: Class D day/night high-visibility vest or shirt to AS/NZS 4602.1

When: Mandatory during all excavation work ensuring visibility to excavator operators and vehicle drivers. Critical for preventing struck-by incidents from plant and traffic near excavations.

Requirement: Heavy-duty work gloves with grip enhancement, chemical-resistant for contaminated soil

When: Required during pipe handling and manual excavation work providing protection from cuts and abrasions, improved grip on pipes and tools. Chemical-resistant gloves mandatory when handling contaminated soil.

Requirement: Impact-resistant safety glasses to AS/NZS 1337.1 with side shields

When: Required during all excavation work protecting from flying debris during machine excavation, dust during dry excavations, and impacts from hand tool use. Side shields provide peripheral protection.

Requirement: P2 particulate respirator for dust, P3 for asbestos, organic vapor cartridge for hydrocarbons

When: Required when excavating in dusty conditions, mandatory for asbestos-contaminated soil at P3 level, or when hydrocarbon contamination creates vapor exposure requiring organic vapor protection.

Requirement: Class 4-5 earplugs or earmuffs to AS/NZS 1270

When: Required when working near excavation equipment including excavators, compaction equipment, and concrete saws. Excavation creates sustained high noise levels requiring hearing protection.

Inspections & checks

Before work starts

  • Verify all workers hold current Construction Induction White Cards and appropriate excavation training
  • Confirm Dial Before You Dig service location enquiry submitted and responses received from all asset owners
  • Review service plans identifying all underground services within and near excavation area
  • Verify electromagnetic service location completed with services marked on ground
  • Check excavation protective systems (shields, shoring) are available and appropriate for soil conditions and depth
  • Confirm excavator and operators are competent with current plant operator tickets for excavation equipment
  • Verify dewatering equipment including pumps and backup power are available and functional
  • Check barricading materials are adequate for full excavation perimeter protection
  • Confirm first aid equipment and trained personnel are on site
  • Verify emergency contact numbers for service authorities are available if services are struck

During work

  • Monitor excavation depth and implement protective systems before depth exceeds 1.5 metres or immediately in unstable soil
  • Verify excavator maintains safe clearances from identified services with hand digging for final approach
  • Check barricades remain in place around excavation perimeter with no unauthorized access
  • Monitor dewatering pumps continue operating maintaining excavation floor dry
  • Verify workers in excavations are protected by shields, shoring, or other protective systems at all times
  • Check spoil piles and equipment are positioned minimum 1.5 metres from excavation edge preventing surcharge loading
  • Monitor soil conditions during excavation watching for groundwater seepage, soil type changes, or stability concerns
  • Verify ladder or safe access is provided for workers entering and exiting excavations
  • Check weather forecasts and implement wet weather procedures if rain is forecast
  • Monitor vibration from nearby traffic or equipment that may affect trench stability

After work

  • Conduct daily pre-start inspection before workers enter excavation checking for overnight stability changes
  • Verify protective systems remain secure with no evidence of movement or loosening
  • Check dewatering pumps operated correctly overnight with no water accumulation
  • Inspect barricades remain intact and undamaged
  • Document inspection results with written record of conditions and approval to proceed
  • Verify ladder access remains in place and secure
  • Check excavation signage remains visible and in place
  • Assess weather effects after rain or frost events before allowing work to resume
  • Document any near-misses or hazards identified during shift for continuous improvement
  • Brief following shift workers on excavation conditions and any changes from previous day

Step-by-step work procedure

Give supervisors and crews a clear, auditable sequence for the task.

Field ready
1

Underground Service Location and Excavation Planning

Commence excavation work with comprehensive service location ensuring all underground services are identified before any excavation. Submit Dial Before You Dig enquiry minimum 2 working days before proposed excavation providing accurate site location and excavation extent using site plan or aerial photograph. Receive service plan responses from all asset owners including water authority (water and sewer mains), electricity distributor (power cables), gas distributor (gas mains), telecommunications providers (phone and data cables), and local council (stormwater drains). Review all service plans identifying services within 10 metres of proposed excavation marking approximate positions on site plan. Note service depths, materials, and owner contact details. Engage qualified service locator using electromagnetic location equipment to physically locate buried services. Locator traces services marking actual positions on ground using color-coded paint (blue for water, yellow for gas, red for electricity, green for sewer, orange for telecommunications). For critical services particularly high-pressure gas or high-voltage electricity, conduct verification excavation using hydro-vacuum excavation or hand digging exposing service at one location confirming actual position and depth before mechanical excavation. Mark excavation alignment on ground using string lines or paint showing proposed trench centerline and edges. Mark safe clearance zones minimum 600mm from identified services within which hand tools only will be used. Brief excavator operator on service locations providing marked plan and physically showing marked services on ground. Establish emergency contact numbers for all service owners displayed prominently in case services are accidentally struck requiring immediate notification. Document service location work with photographs showing marked services and clearances providing record of due diligence.

Safety considerations

Comprehensive service location before excavation eliminates primary service strike hazard. Dial Before You Dig compliance ensures all asset owners are notified and provide service information. Physical location using electromagnetic equipment confirms actual service positions accounting for plan inaccuracies. Verification excavation for critical services provides visual confirmation before mechanical excavation. Safe clearance zones with hand digging near services prevents striking services with excavator bucket.

2

Excavation Establishment and Barricading

Establish excavation area with barricades before commencing digging. Install temporary fencing or barrier mesh around proposed excavation area positioned minimum 1.5 metres back from planned excavation edges allowing space for spoil placement and preventing access to excavation edges. Use highly visible orange or red barrier mesh secured to posts at regular intervals. Install warning signage on barricades at regular intervals using signs indicating "DEEP EXCAVATION DANGER" or "AUTHORIZED PERSONNEL ONLY." Position excavator and establish access routes for equipment and materials ensuring vehicles remain outside barricaded area. Create stockpile areas for excavated soil (spoil) positioned beyond barricades and minimum 1.5 metres from excavation edge preventing surcharge loading on trench walls. Establish safe access to excavation work area for workers using designated access points with signs. If excavation is in public area or near building entries, install solid fencing or concrete barriers preventing public access particularly children. For excavations near roads or traffic areas, coordinate with local authorities for traffic management and additional signage alerting drivers to excavation work. Ensure all site personnel are briefed on barricade locations and prohibition of entry to excavation areas except through authorized access points. For excavations remaining open overnight or unattended, verify barricades are secure and consider additional security measures including site security guards or CCTV if public access risk is high.

Safety considerations

Barricading before excavation commences prevents inadvertent access to excavation areas before excavation occurs. Visible barricades with signage clearly indicate hazard areas. Positioning barricades back from excavation edges accounts for potential edge failures preventing access to unstable zones. Separate spoil stockpile areas prevent surcharge loading on trench walls that could cause collapse. Public access prevention particularly protects children from fall hazards.

3

Progressive Excavation with Service Awareness

Begin excavation maintaining continuous awareness of underground services. Excavator operator commences excavation at marked alignment starting from point furthest from services or buildings working toward service areas. Maintain excavation depth initially shallow (under 1.5 metres) allowing inspection of soil conditions before deeper excavation. Watch for service indicators including valve pits, marker posts, cable markers, or concrete service covers indicating services may be present. As excavation approaches marked service locations (within 1.5 metres), transition to cautious excavation with reduced bucket size or depth of cut reducing strike risk. At safe clearance zone (600mm from service), cease mechanical excavation and hand dig for final exposure using shovels and hand tools. Carefully expose any services encountered verifying service type and confirming matches service plans or identifying unexpected services. If unexpected services are found, stop excavation and identify service owner consulting Dial Before You Dig plans or contacting service locator for assistance. Maintain adequate clearance to exposed services during continued excavation - typically minimum 300mm horizontal clearance for water and gas, 500mm for high-voltage electricity. Support exposed services using timber blocking or purpose-built supports preventing service weight stressing pipes or cables. If services require temporary relocation to allow excavation, engage appropriate service authority for relocation work - never relocate services without owner authorization. Document any deviations from service plans with photographs showing actual service positions and clearances maintained.

Safety considerations

Progressive careful excavation with service awareness prevents sudden service strikes. Reduced excavation pace near services allows early detection before strikes occur. Hand digging within safe clearance zones eliminates mechanical excavation strike risk. Support of exposed services prevents damage from service weight or excavation activities. Immediate stop on finding unexpected services allows safe identification before proceeding.

4

Installation of Trench Protective Systems

Install protective systems before excavation depth exceeds 1.5 metres or immediately if soil conditions are unstable. For typical plumbing trenches, lower trench shield (trench box) into excavation using excavator lifting capabilities, positioning shield to provide protection for pipe installation work area. Shields typically 2-3 metres long aluminum or steel box structures open at top and bottom. Position shield extending minimum 500mm above ground level preventing edge material falling into trench. If shield length is less than required trench length, excavate and install pipes in sections moving shield as work progresses (leapfrogging). For hydraulic shoring, install shoring panels against trench walls with hydraulic struts spanning between panels, adjusting strut pressure to secure panels firmly against walls. Space struts vertically at maximum 1.2 metre intervals ensuring continuous wall support. For wide trenches where shields don't fit, consider benching excavation creating stepped sides with maximum 1.5 metre vertical height per step, or battering sides at safe angle typically 1:1.5 eliminating collapse risk but requiring wider excavation. Never enter excavations exceeding 1.5 metres depth or any depth in unstable soil (sand, saturated soil) without protective systems in place even for brief periods. Brief workers that protective systems must remain in place whenever workers are in excavation and must not be removed or modified without engineering approval. Inspect protective systems daily verifying shields remain positioned correctly, shoring panels are secure against walls, hydraulic struts maintain pressure, and no evidence of wall movement behind shoring indicates system failure.

Safety considerations

Protective systems installed before excavation exceeds 1.5 metres prevents workers entering unprotected deep excavations. Trench shields provide immediate protection without requiring installation time allowing work to proceed efficiently. Shields extending above ground level prevent edge material falling into trench. Inspection procedures ensure systems remain effective throughout work. Prohibition of system removal while workers are in excavations maintains continuous protection.

5

Pipe Installation, Testing, and Backfilling

Install drainage pipes in prepared excavation working from within protected trench. Prepare trench bottom creating firm stable foundation for pipes using bedding material typically minimum 100mm clean sand or fine gravel providing uniform support. Check trench bottom grade using laser level or spirit level ensuring adequate fall for drainage typically minimum 1:60 for sewer pipes (approximately 17mm fall per metre). Position pipe sections in trench connecting joints using appropriate method for pipe material - rubber ring joints for PVC or concrete pipes, solvent cement for PVC where specified. Ensure pipes are straight and properly aligned with no kinks or misalignment. Backfill around pipes using selected material (clean sand or fine gravel) to minimum 300mm above pipe crown providing protection before general backfill. Compact bedding material using hand compaction or light mechanical compaction preventing damage to pipes. Test drainage before completing backfill using water test filling system with water and checking for leaks, or air test pressurizing drainage system and monitoring for pressure loss. Document test results. Complete backfilling using excavated material or imported fill as specified, installing in layers maximum 300mm thick with compaction of each layer preventing future settlement. Achieve compaction levels specified typically minimum 95% standard compaction for areas under pavements or structures. Remove protective systems progressively as backfilling proceeds ensuring workers remain protected until backfill level provides equivalent protection. Complete surface reinstatement matching existing surface conditions with pavement reconstruction, grass replacement, or temporary surface pending permanent restoration. Document completed work with as-constructed information showing pipe positions, depths, and connections providing record for future maintenance.

Safety considerations

Working within protective systems during pipe installation maintains collapse protection. Progressive backfilling allows protective system removal as fill provides equivalent protection. Testing before completing backfill verifies pipe integrity preventing failures after trench is closed requiring re-excavation. Controlled compaction prevents settlement while avoiding pipe damage. Surface reinstatement eliminates trip hazards and provides access for normal use.

Frequently asked questions

At what depth does trench excavation require protective systems like shoring or shields?

Under WHS Regulations, excavations are classified as high-risk construction work requiring mandatory protective systems when depth exceeds 1.5 metres or at any depth where risk of collapse or engulfment exists. The 1.5 metre threshold is not absolute safe depth but rather regulatory trigger point - excavations under 1.5 metres in unstable soil, saturated soil, or previously disturbed fill may still require protection even though depth is below trigger threshold. Conversely, excavations exceeding 1.5 metres in solid rock may not require protective systems as rock has inherent stability, though engineering assessment should verify. Protective system types include trench shields (trench boxes) which are prefabricated steel or aluminum box structures providing immediate protection as excavation deepens, hydraulic shoring using adjustable hydraulic struts pushing shoring panels against trench walls, benching where excavation is stepped creating maximum 1.5 metre vertical heights per step reducing wall height to stable dimension, and battering where sides are sloped at safe angle typically 1:1.5 (1 metre vertical to 1.5 metres horizontal) eliminating collapse risk but requiring substantial excavation width. Selection depends on soil type, excavation depth, groundwater conditions, and available space. For typical plumbing drainage trenches 1.5-3 metres deep, trench shields provide most practical solution balancing protection with work efficiency. Shields install quickly using excavator, protect workers immediately, and allow efficient pipe installation within protected zone. For shallower excavations under 1.5 metres, protective systems are not legally required but may still be appropriate if soil conditions are poor including loose sand, saturated soil from groundwater or rain, or previously disturbed fill with poor stability. Risk assessment considering soil conditions, duration of worker entry, and nature of work being performed determines whether protection is appropriate even below regulatory threshold. Conservative approach is to provide protection any time workers will spend extended periods in excavation or soil conditions create uncertainty about stability. Never base protection decisions on subjective assessment that soil 'looks stable' - appearance can be deceiving and sudden collapse can occur in soil that appeared stable for hours or days. Recent fatal incidents have resulted from failures to protect excavations that appeared stable but collapsed suddenly. Implement protection before workers enter excavations rather than entering first to assess whether protection is needed - this assessment can be fatal error if collapse occurs during assessment period. For excavations where protective systems are not used, implement strict controls including minimizing time workers spend in excavation with pipe preparation and cutting occurring outside excavation reducing in-trench time, positioning workers to avoid being between excavation walls (working at trench ends rather than between walls), and continuous monitoring of excavation walls for signs of instability including cracking, bulging, or minor sloughing indicating collapse risk. Document rationale for protection decisions in SWMS and risk assessment whether providing protection or determining it is not required based on depth and soil conditions. This documentation demonstrates due diligence and provides defendable record of decision-making process.

What is the Dial Before You Dig process and why is it legally required before excavation?

Dial Before You Dig is Australia-wide free referral service providing underground service location information to anyone planning excavation work. Legislative requirements in most Australian states and territories mandate that anyone proposing excavation work must submit Dial Before You Dig enquiry before commencing excavation, with failure to do so potentially resulting in liability for service strikes and fines. Process involves visiting Dial Before You Dig website or calling 1100 phone number, providing accurate excavation location using street address, lot number, or GPS coordinates along with site plan or aerial photograph showing proposed excavation area, describing excavation work including depth and extent, providing contact details for person responsible for excavation, and submitting enquiry minimum 2 working days before proposed excavation allowing time for asset owners to respond. System automatically identifies all utility asset owners with services in or near proposed excavation area including electricity distributors, gas distributors, water authorities, telecommunications companies, local councils, and private service owners like irrigation companies or private data networks. Asset owners receive notification and must respond providing service location information typically as PDF plans showing service positions, depths, materials, and contact details for queries. Enquirer receives consolidated response typically within 2 working days containing all service information from all asset owners in area. Service plans show approximate service locations based on asset owner records but may not be precisely accurate as construction variations, undocumented relocations, or plan errors can mean actual service positions differ from plans. After receiving Dial Before You Dig response, excavator's obligations include reviewing all service plans identifying services within or near excavation area, physically locating services using electromagnetic location equipment (cable locators) confirming actual positions, maintaining safe clearances to identified services during excavation typically minimum 600mm with hand digging only within this clearance, and contacting service owners before excavating within clearance zones or if uncertain about service positions. Legal framework around Dial Before You Dig varies by state but generally imposes strict liability for service strikes meaning excavator is liable for damage and repair costs even if they followed reasonable location procedures, with defenses only available if excavator can prove service location was impossible due to asset owner failures. This strict liability regime emphasizes importance of careful excavation technique even after thorough location work. Failure to submit Dial Before You Dig enquiry before excavation substantially worsens liability position in service strike incidents with courts taking dim view of contractors who skip this basic step. Recent cases have resulted in six-figure damage claims against contractors who struck major services without conducting Dial Before You Dig enquiry. Beyond legal liability, practical benefits of Dial Before You Dig include preventing service strikes that could cause worker injuries or fatalities from electrocution, gas explosion, or high-pressure water release, avoiding project delays from service damage requiring emergency repairs before work can continue, preventing substantial repair costs and consequential damage claims from service authorities potentially exceeding $100,000 for major services, and maintaining relationships with service authorities who track contractors' service strike history affecting future work opportunities. Dial Before You Dig enquiries remain valid for 2 months from enquiry date after which services may have changed requiring new enquiry if work is delayed. Retain Dial Before You Dig response documentation throughout project including service plans from all asset owners, demonstrating compliance if service strike incidents occur. Provide Dial Before You Dig reference number and service plans to excavator operators before work commences ensuring they have service information. Some projects require multiple Dial Before You Dig enquiries as work extends along routes or in stages requiring separate enquiries for each area. Establish practice of routine Dial Before You Dig use for all excavation work regardless of depth or perceived service risk creating consistent safe approach rather than selective use that may miss critical services.

How should excavation work proceed if groundwater is encountered during trench excavation?

Groundwater encountered during trench excavation requires immediate management as water infiltration creates both direct hazards (drowning, hypothermia) and substantially increases trench collapse risk by weakening trench walls. Initial response upon encountering groundwater involves stopping excavation if water accumulation is rapid, assessing water inflow rate determining if it is minor seepage or significant flow requiring substantial dewatering capacity, positioning dewatering pump in excavation low point beginning water removal immediately, and evaluating trench wall stability as water weakens soil reducing stability and potentially requiring additional protective systems beyond originally planned. Dewatering system requirements depend on inflow rate with minor seepage (few litres per minute) manageable using single small submersible pump, moderate inflow (50-200 litres per minute) requiring larger capacity pump with backup pump available in case of primary pump failure, and severe inflow (exceeding 200 litres per minute) potentially requiring wellpoint dewatering or other specialized techniques. Pump selection must account for anticipated inflow including variations from rainfall, tidal influences if near coast, or seasonal groundwater level changes. Position pump in sump excavated at trench low point allowing water to collect for pump intake, surround pump intake with coarse aggregate (20-40mm gravel) acting as filter preventing sediment clogging pump, ensure pump discharge hose is adequate diameter preventing restriction and positioned to prevent discharged water returning to excavation. Electrical supply for pumps requires RCD protection preventing electrocution hazards in wet environment with backup power source (generator) ensuring pump operation continues during power failures as sudden water accumulation from pump failure creates rapid stability deterioration. Continuous pumping operation is critical maintaining excavation floor dry rather than periodic pumping allowing water accumulation between pumping cycles. Some excavators attempt to save costs by pumping water out then ceasing pumping during work - this is extremely dangerous as groundwater continues entering excavation and even shallow water accumulation undermines trench wall stability. Monitor water levels throughout work verifying pumps maintain excavation dry and adjusting pumping capacity if inflow increases. Groundwater effects on trench stability are significant with saturated soil having approximately half the stability of dry soil meaning protective systems designed for dry conditions may be inadequate in wet conditions. Consider enhanced protective systems including closer shoring strut spacing, heavier shoring panels, or transition from benching to full shoring if benching was used in dry conditions. Never assume trench walls that were stable before groundwater appearance will remain stable after saturation. Install trench shields or shoring before groundwater level rises to worker positions in excavation preventing workers being in unsupported wet excavation. For severe groundwater problems where conventional pumping is inadequate, specialist dewatering techniques include wellpoint systems installing perforated pipes around excavation connected to suction pump lowering water table before excavation begins, deep well pumping for deeper water tables using submersible pumps in deep wells around excavation, or cutoff walls using sheet piling or other barriers preventing water entry to excavation. These techniques require specialist contractors and add substantial cost but may be only safe approach in extreme groundwater conditions. Alternative construction methods avoiding open excavation in groundwater zones include pipe jacking or boring installing pipes without trench excavation, or raising finished pipe level reducing excavation depth below water table if design allows. Discharge of pumped groundwater requires consideration with typically discharge to stormwater system acceptable if water quality is good (clear groundwater without contamination), sediment basin required if pumped water contains suspended sediment requiring settlement before discharge, environmental authority approvals potentially required for large-scale dewatering affecting local water table or discharging to sensitive receiving waters, and tanker removal necessary if groundwater is contaminated from site contamination. Brief workers on groundwater hazards including enhanced collapse risk requiring strict compliance with protective system use, prohibition of entering excavations with significant standing water without pumps operating, and emergency procedures if pumps fail including immediate evacuation and prohibition of re-entry until pumping is restored and water is removed. Document groundwater conditions encountered, dewatering measures implemented, and any stability concerns arising from groundwater providing record for project files and informing future similar work. Remember that groundwater conditions can change rapidly during work due to rainfall, tidal influences, or seasonal water table variations requiring adaptable dewatering approach rather than fixed unchanging system.

What are the requirements for daily inspections of excavations before workers enter?

Daily pre-start excavation inspections are mandatory requirement under WHS Regulations for high-risk excavation work, requiring competent person to inspect excavation before workers enter each day verifying conditions remain safe. Competent person conducting inspection must have knowledge and experience in excavation work sufficient to identify hazards and assess stability including understanding soil types and behavior, ability to recognize signs of instability such as cracking, bulging, or sloughing, knowledge of protective system requirements and proper installation, and authority to prohibit work if excavation is not safe. Typically site supervisor, experienced excavation worker, or specifically trained inspector conducts daily inspections with some larger projects requiring qualified geotechnical engineer inspections particularly for deep or complex excavations. Inspection must occur each day before any workers enter excavation accounting for overnight changes from weather, groundwater fluctuations, vibration from nearby traffic, or time-dependent soil behavior where trench walls that were stable can deteriorate over hours or days. Inspection checklist should systematically verify trench walls show no signs of instability checking for tension cracks in soil at excavation edges indicating potential slip surfaces, vertical or near-vertical cracks in trench walls indicating wall movement, bulging or outward movement of walls indicating pressure buildup behind walls, and sloughing or raveling of soil from walls indicating cohesion loss. Protective systems remain secure and functional including trench shields positioned correctly with minimum 500mm extending above ground level, hydraulic shoring struts maintaining pressure with no evidence of loosening, shoring panels tight against walls with no gaps allowing soil movement, and no damage to protective systems from excavation work or overnight events. Groundwater conditions are managed with dewatering pumps operational and maintaining excavation floor dry, no excessive water accumulation from overnight rain or groundwater inflow, discharge hoses functional and positioned correctly, and backup power and spare pumps available and functional. Barricades and safety measures remain effective including perimeter barricades intact with no unauthorized removal or damage, warning signage visible and in place, ladder or safe access to excavation properly positioned, and spoil piles and equipment remain minimum 1.5 metres from excavation edge preventing surcharge loading. Weather effects are assessed including rainfall effects on soil moisture and stability, frost damage potentially affecting soil structure (freeze-thaw cycles weaken stability), and strong winds potentially affecting exposed service supports or equipment near excavation. Document inspection using written checklist recording date, inspector name, weather conditions, observations of trench walls and protective systems, water management status, any deficiencies identified, corrective actions implemented, and approval to commence work or prohibition if deficiencies require resolution before work can safely proceed. Deficiencies identified during inspection require immediate remedial action before workers enter excavation including pumping accumulated water if dewatering pumps failed overnight, installing additional shoring or tightening existing shoring if wall movement is detected, excavating sloughed material and assessing walls for further instability if sloughing occurred, seeking engineering assessment if serious concerns exist about stability that inspector cannot resolve. Inspector has authority to prohibit entry to excavation if unsafe conditions exist regardless of schedule pressure or client expectations - this authority must be genuine and supported by site management not merely theoretical. Empower inspectors to make safety decisions without fear of negative consequences from production delays. Additional inspections required after significant events potentially affecting stability including heavy rain exceeding 25mm particularly if accompanied by sustained period of lighter rain, vibration from nearby piling, blasting, or earthquake, extended periods without work where excavation remained open allowing time-dependent deterioration (minimum weekly inspections for excavations open but inactive), and any incidents including minor wall sloughing, equipment entering excavation, or near-miss events. Brief workers each day on inspection results including any changes to excavation conditions overnight, any areas requiring special caution or modified procedures, and emergency procedures if sudden stability deterioration occurs during work. Maintain inspection records throughout project creating documented evidence of systematic safety management and due diligence. These records are critical in incident investigations demonstrating regular attention to excavation safety and can be evidence supporting defense if incidents occur. Consider photographic documentation as supplement to written records showing excavation condition at inspection time providing visual reference if later questions arise about conditions. Train multiple personnel in competent person inspection procedures ensuring backup inspectors are available if regular inspector is absent, and establishing consistency in inspection standards across different inspectors preventing variability in hazard recognition. Inspection programs should continuously improve learning from near-miss incidents or hazards identified by updating checklists to include newly identified hazard types and providing feedback to inspectors on effectiveness of inspections and any hazards they missed.

What emergency procedures should be established for trench collapse incidents?

Trench collapse emergency procedures must be established before excavation work commences as rescue from collapsed trench is time-critical specialized operation requiring immediate coordinated response to save buried workers' lives. Immediate response upon trench collapse involves anyone witnessing collapse immediately calling for help alerting all site personnel, calling emergency services (000) immediately reporting trench collapse with exact location, number of persons potentially buried, and excavation depth and conditions, and implementing emergency shutdown stopping all excavation equipment and preventing additional workers approaching collapse area as additional collapse may occur or rescue workers may be endangered. Initial rescue coordination requires designating incident commander (typically site supervisor) coordinating rescue efforts, accounting for all workers determining who may be buried and their likely position, establishing exclusion zone around collapse preventing unauthorized access or additional loading near collapse, and summoning specialist rescue resources including fire and rescue services with confined space and collapse rescue capability, ambulance services, and if available mine rescue or other specialist heavy rescue resources. Worker extraction approach depends on burial extent and conditions with surface rescuers attempting to reach partially buried workers using hand tools carefully removing soil from around buried person, but strictly prohibiting entry into collapsed excavation or excavating using machines near buried persons as this creates additional collapse risk and machine excavation may injure buried persons. Proper collapse rescue requires specialized equipment and trained personnel that most construction sites do not possess including trench rescue shoring to stabilize collapse area before rescuers enter preventing secondary collapse burying rescuers, vacuum excavation or air knife equipment allowing rapid soil removal without mechanical force that could injure buried person, breathing apparatus allowing rescuers to work in potentially oxygen-depleted or contaminated atmosphere, and vertical rescue equipment for extracting victims from deep excavations. Fire and rescue services maintain specialized trench collapse rescue capability with trained personnel and equipment responding to construction site collapse incidents. While awaiting emergency services arrival, site personnel should attempt to communicate with buried person if possible providing reassurance and determining their condition, but must not enter collapsed excavation attempting rescue as secondary collapses commonly occur burying would-be rescuers creating additional casualties. Difficult as it is to resist attempting immediate rescue, waiting for properly equipped rescue services provides best chance of successful rescue without additional casualties. Preventive measures reduce need for emergency rescue including daily pre-start inspections identifying deteriorating conditions before collapse occurs, protective systems properly installed eliminating collapse risk for workers within protected zones, weather monitoring ceasing work during conditions increasing collapse risk, and worker training recognizing collapse warning signs like cracking, bulging, or sloughing allowing workers to exit before collapse. Emergency rescue equipment that should be available on excavation sites includes rope and harnesses for extracting workers from excavations, first aid equipment including oxygen resuscitation equipment and trauma supplies, communication equipment including two-way radios and cell phones with emergency numbers programmed, and lighting equipment for night-time rescue operations. Document emergency procedures in SWMS including emergency contact numbers prominently displayed, roles and responsibilities during emergencies, evacuation procedures for workers in adjacent excavations if collapse affects multiple trenches, and assembly points for accounting for all personnel. Conduct emergency drills periodically testing emergency procedures and coordination, particularly on large projects with multiple excavation crews. After any collapse incident regardless of severity, implement stand-down ceasing all excavation work across project, incident investigation determining collapse causes and whether similar conditions exist in other excavations, notifications to WHS regulators as workplace fatality or serious incident triggering mandatory reporting, and review and update of SWMS and procedures implementing learnings from incident. Provide trauma counseling and support for workers who witnessed collapse or participated in rescue as these events cause significant psychological impact affecting workers' wellbeing and ability to return to similar work. Remember that trench collapse rescue is extremely difficult time-critical operation with survival times measured in minutes, making prevention through proper protective systems and inspections far preferable to relying on emergency rescue capability.

Related SWMS documents

Browse all documents

plumbing

CCTV Drain Inspection Safe Work Method Statement

Comprehensive SWMS for CCTV drainage investigation including confined space entry, sewage exposure controls, camera equipment operation, and inspection reporting procedures.

View document

plumbing

Electric Fusion - Poly Pipe Butt Welding (PPW) Safe Work Method Statement

Comprehensive SWMS for electric fusion and butt fusion welding of polyethylene pipes including hot work controls, equipment operation, surface preparation, and pressure testing procedures.

View document

plumbing

Gas-Water Leak Detection Safe Work Method Statement

Comprehensive SWMS for gas and water leak detection including electronic detection equipment, acoustic listening, tracer gas methods, and emergency response procedures for gas and water system leaks.

View document

plumbing

Gross Pollutant Trap Cleaning Safe Work Method Statement

Comprehensive SWMS for gross pollutant trap cleaning including confined space entry, contaminated waste removal, vacuum equipment operation, and stormwater protection procedures.

View document

plumbing

Guided Boring Pipe Jacking Works Safe Work Method Statement

Comprehensive SWMS for guided boring and pipe jacking trenchless installation including service location, confined space entry, drilling equipment operation, and strike prevention procedures.

View document

plumbing

Medical Gas Pipe System Installation Safe Work Method Statement

Comprehensive SWMS for installing medical gas pipeline systems in healthcare facilities including oxygen, medical air, vacuum, and anaesthetic gas distribution with contamination prevention and pressure testing protocols.

View document
Trusted by 1,500+ Australian construction teams

Trench Excavation SWMS Sample

Professional SWMS created in 5 seconds with OneClickSWMS

  • Instant PDF & shareable link
  • Auto-filled risk matrix
  • Editable Word download
  • State-specific compliance
  • Digital signature ready
  • Version history preserved
Manual creation2-3 hours
OneClickSWMS5 seconds
Save 99% of admin time and eliminate manual errors.

No credit card required • Instant access • Unlimited drafts included in every plan

PDF Sample

Risk Rating

BeforeHigh
After ControlsLow

Key Controls

  • • Pre-start briefing covering hazards
  • • PPE: hard hats, eye protection, gloves
  • • Emergency plan communicated to crew

Signature Ready

Capture digital signatures onsite and store revisions with automatic timestamps.